[Federal Register Volume 63, Number 104 (Monday, June 1, 1998)]
[Notices]
[Pages 29724-29725]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-14355]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP98-552-000]
Northern Natural Gas Company; Notice of Request Under Blanket
Authorization
May 26, 1998.
Take notice that on May 14, 1998, Northern Natural Gas Company
(Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed
in Docket No. CP98-552-000 a request pursuant to Sections 157.205 and
157.212 of the Commission's Regulations under the Natural Gas Act (18
CFR 157.205, 157.212) for authorization to install and operate a new
delivery point located in O'Brien County, Iowa to provide
transportation service to AG Processing, Inc. (AGP) near Sheldon, Iowa,
under Northern's blanket certificate issued in Docket No. CP82-401-000
\1\ pursuant to Section 7 of the Natural Gas Act, all as more fully set
forth in the request that is on file with the Commission and open to
public inspection.
---------------------------------------------------------------------------
\1\ See, 20 FERC para. 62,410 (1982).
---------------------------------------------------------------------------
Northern states that it is currently providing service to the
MidAmerican Energy Company (MIDAM) for retail service to AGP at its
Sheldon, Iowa plant. AGP has requested the new delivery point and
transportation service. Upon approval of the requested authorization
herein, Northern will be providing service directly to AGP under
[[Page 29725]]
Northern's currently effective firm and interruptible throughput
service agreements or by access to released capacity of other shippers.
Northern states that the proposed deliveries to AGP at the AGP #1
TBS are 1,800 MMBtu on a peak day and 525,600 MMBtu on an annual basis.
These volumes represent no incremental change to Northern's current
volumes. Northern estimates a cost of installing the delivery point of
$162,000. AGP will construct and maintain a downstream line and
appurtenant facilities.
Northern further states that MIDAM and the Iowa State Commission
have been notified of this proposal and application.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 98-14355 Filed 5-29-98; 8:45 am]
BILLING CODE 6717-01-M