98-15400. License Term for Medical Use Licenses  

  • [Federal Register Volume 63, Number 111 (Wednesday, June 10, 1998)]
    [Rules and Regulations]
    [Pages 31604-31607]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-15400]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    10 CFR Part 35
    
    RIN 3150-AF77
    
    
    License Term for Medical Use Licenses
    
    AGENCY: Nuclear Regulatory Commission.
    
    ACTION: Final rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Nuclear Regulatory Commission is amending its regulations 
    pertaining to the medical use of byproduct material to eliminate the 5-
    year term limit for medical use licenses. License terms for licenses 
    issued under these regulations will be set by policy. Other materials 
    licenses are issued for up to 10 years. The NRC will issue some 
    licenses for shorter terms if warranted by the individual circumstances 
    of license applicants. The amendment reduces the administrative burden 
    of license renewals on a 5-year cycle for both NRC and licensees and 
    supports NRC's goal of streamlining the licensing process.
    
    EFFECTIVE DATE: This regulation becomes effective on July 10, 1998.
    
    FOR FURTHER INFORMATION CONTACT: Jayne M. McCausland, Office of Nuclear 
    Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555, telephone (301) 415-6219, e-mail JMM2 @ nrc.gov.
    
    SUPPLEMENTARY INFORMATION:
    
    I. Background.
    II. Discussion.
    III. Statement of Regulatory Action.
    IV. Discussion of Public Comments.
    V. Agreement State Compatibility.
    VI. Environmental Impact: Categorical Exclusion.
    VII. Paperwork Reduction Act Statement.
    VIII. Regulatory Analysis.
    IX. Regulatory Flexibility Certification.
    X. Backfit Analysis.
    
    I. Background
    
        In 1995, the NRC's Office of Nuclear Material Safety and Safeguards 
    (NMSS) initiated a review to determine whether the license term for 
    materials licenses could be lengthened so that NRC's licensing 
    resources could be redirected to other areas of the materials program. 
    At that time, the resources devoted to renewals constituted over 50 
    percent of the total resources expended for licensing. NMSS undertook 
    this review as a part of NRC's ``business process redesign'' efforts.
        The license renewal process has been used as an opportunity for the 
    Commission to review the history of the licensee's operating 
    performance (e.g., the record on compliance with regulatory 
    requirements) and the licensee's overall materials safety program. This 
    review is performed to ascertain if the licensee employs up-to-date 
    technology and practices in the protection of health, safety, and the 
    environment, and complies with any new or amended regulations. As part 
    of a license renewal, the licensee is asked to provide information on 
    the current status of its program as well as any proposed changes in 
    operations (types and quantities of authorized materials), personnel 
    (authorized users and radiation safety officers), facility, equipment, 
    or applicable procedures. The renewal process has been perceived to 
    benefit both the licensee and NRC because it requires both to take a 
    comprehensive look at the licensed operation. However, in practice, 
    comprehensive program reviews occur when proposed changes are 
    identified and requested by licensees as license amendments rather than 
    during the license renewal process.
        License terms have been reviewed on numerous occasions since 1967. 
    On May 12, 1967 (32 FR 7172), the Commission amended 10 CFR part 40 to 
    eliminate a 3-year limit on the term of source material licenses. At 
    that time, there was no restriction on the term of byproduct licenses 
    under 10 CFR part 30 or special nuclear material licenses under 10 CFR 
    part 70. In the notice of proposed rulemaking associated with amending 
    10 CFR part 40, dated December 22, 1966, NRC indicated that if the 
    proposed amendment to eliminate the 3-year restriction were adopted, 
    licenses would be issued for 5-year terms, except when the nature of 
    the applicant's proposed activities indicated a need for a shorter 
    license period. At that time, the Commission believed there was little 
    justification for granting licenses under 10 CFR parts 30, 40, and 70 
    for terms of less than 5 years, in view of the cumulative experience up 
    to that time and the means available to NRC to suspend, revoke, or 
    modify such licenses if public health and safety or environment so 
    required.
        In March 1978, NMSS conducted a study (SECY-78-284, ``The License 
    Renewal Study for parts 30, 40, and 70 Licenses'') to consider changing 
    the 5-year renewal period for parts 30, 40, and 70 licenses. The study 
    concluded, in part, that the NRC should continue its practice of 
    issuing specific licenses for 5-year terms and should retain an option 
    to write licenses for shorter terms, if deemed necessary, for new types 
    of operations or if circumstances warranted.
        On July 26, 1985 (50 FR 30616), NRC proposed revising 10 CFR part 
    35, ``Medical Use of Byproduct Material.'' The proposed rulemaking 
    indicated that the Commission had selected a term of five years for a 
    license. It was believed that a term shorter than 5 years would not 
    benefit health and safety because past experience indicated that 
    medical programs did not generally change significantly over that 
    period of time. The notice also indicated that a longer term may 
    occasionally result in unintentional abandonment of the license. On 
    October 16, 1986 (51 FR 36932), NRC issued the final rule that 
    consolidated and clarified radiation safety requirements related to the 
    medical use of byproduct materials, and included a license term of 5 
    years.
        On June 19, 1990 (55 FR 24948), the Commission announced that the 
    license term for major operating fuel cycle licensees (i.e., licenses 
    issued pursuant to 10 CFR parts 40 or 70) would be increased from a 5-
    year term to a 10-year term at the next renewal of the affected 
    licenses. This change enabled NRC resources to be used to improve the 
    licensing and inspection programs. The bases for this change were that 
    major operating fuel cycle facilities had become stable in terms of 
    significant changes to their licenses and operations and that licensees 
    would be required to update the safety demonstration sections of their 
    licenses every 2 years.
        On July 2, 1996, the Commission approved the NRC staff's proposal 
    to extend the license term for uranium recovery facilities from 5 years 
    to 10 years. Extending the license term reduces the administrative 
    burden associated with the license renewal process for both the NRC 
    staff and the uranium recovery licensees. Also, the extension reduces 
    licensee fees, makes the license term for these facilities more 
    commensurate with the level of risk, and supports NRC's goal of 
    streamlining the licensing process. Licensees were informed of the 
    extensions in July 1996.
        On February 6, 1997 (62 FR 5656), the Commission gave notice that 
    the license term for materials licenses issued pursuant to 10 CFR parts 
    30, 40, or 70 would be increased from a 5-year term to up to a 10-year 
    term at the next renewal of the affected licenses. However, whereas the 
    10-year term for
    
    [[Page 31605]]
    
    other licenses was set by this policy, the term for licenses issued 
    pursuant to 10 CFR part 35 was established by regulation at 5 years.
        On July 31, 1997 (62 FR 40975), the NRC published a proposed rule 
    to revise 10 CFR part 35 to eliminate the 5-year term limit in 10 CFR 
    35.18 for medical use licenses. The term for medical licenses could 
    then be set by policy for up to 10 years. The NRC could issue a license 
    for a shorter term, depending on the individual circumstances of the 
    license applicant. The public comment period closed on October 14, 
    1997. A summary of the public comments is provided in Section IV, 
    below.
    
    II. Discussion
    
        The change described above (i.e., increasing the license term for 
    materials licenses issued under 10 CFR parts 30, 40, and 70 to up to 10 
    years) has created an inconsistency between the license terms for 
    medical use and nonmedical use materials licenses. NRC believes that 
    the license duration period for medical use licenses may also be 
    extended without adverse impacts on public health and safety, such as 
    increases in the unintentional abandonment of licensed material or 
    decreases in the licensees' attention to licensed activities, for the 
    following reasons:
        (1) Licensees would continue to be required to adhere to the 
    regulations and their license conditions, and to apply for license 
    amendments for certain proposed changes to their programs;
        (2) No changes in either the frequency or elements of the medical 
    inspection program are being proposed;
        (3) NRC would continue to be in a position to identify, by 
    inspection or other means, violations of its regulations or the license 
    conditions that affect public health and safety, and to take 
    appropriate enforcement actions;
        (4) Cases of abandonment of NRC licenses would be identified 
    through nonpayment of the annual licensing fees and regional NRC office 
    follow-up;
        (5) The NRC staff would continue to make licensees aware of health 
    and safety issues through the issuance of generic communications (such 
    as information notices, generic letters, bulletins, and the NMSS 
    Licensee Newsletter); and
        (6) NRC is moving to a more performance-based regulatory approach, 
    where emphasis is placed on the licensee's execution of commitments 
    rather than on rereview of the details of the licensee's program.
    
    III. Statement of Regulatory Action
    
        The NRC is revising part 35 to eliminate the 5-year term limit in 
    10 CFR 35.18 for medical use licenses so that the term for medical use 
    licenses will be set by policy.
    
    IV. Discussion of Public Comments
    
        Five letters of public comment were received on the proposed rule. 
    Comments were received from National Physics Consultants, Ltd., the 
    American Association of Clinical Endocrinologists, the Mayo Clinic, the 
    University of Cincinnati, and the American Hospital Association.
        All commenters fully supported the proposed amendment to eliminate 
    the reference to the 5-year term limit for medical use licenses in 10 
    CFR 35.18. In addition, the commenters endorsed the change in license 
    terms for licenses issued pursuant to part 35, to be set by policy for 
    as many as 10 years, as are the license terms for other material 
    licenses.
        In general, commenters disparaged the license renewal process, on a 
    5-year frequency, as requiring a significant expenditure of time and 
    fees with minimal benefit, and supported NRC's proposal to eliminate 
    this requirement, citing a reduction of staff time and costs for both 
    the NRC and individual licensees with no decrease in public health and 
    safety. Commenters recognized that the NRC may issue some licenses for 
    shorter terms if warranted by the individual circumstances of license 
    applicants.
        One commenter stated that routine license reviews by the local 
    Radiation Safety Committee will ensure operation of a radiation safety 
    program that protects public health and safety.
        Another commenter indicated that because the NRC is in contact with 
    the licensees on an ongoing basis, any changes in operations, 
    personnel, facility, equipment, or applicable procedures are identified 
    during the inspection and license amendment process.
        One of the commenters agreed that the radiation safety programs at 
    most medical facilities are very stable and pointed out that 
    significant changes in the radiation safety program require license 
    amendments.
        Another commenter recommended that NRC extend the license term for 
    medical use licenses from 5 years to 10 years as soon as possible to 
    reduce the license fees and achieve further cost savings. This 
    commenter expressed support for the NRC's ``business process redesign'' 
    efforts to reduce both the administrative burden of license renewals 
    and license fees. According to the commenter, this will allow that 
    organization's members to redirect their resources to support and 
    implement NRC's initiative to move to a more performance-based 
    regulatory approach.
    
    V. Agreement States Compatibility
    
        This rulemaking will be a matter of compatibility between the NRC 
    and the Agreement States. Compatibility Category D has been assigned to 
    the changes in 10 CFR 35.18. Category D means the provisions are not 
    required for purposes of compatibility. No problems have been 
    identified regarding Agreement State compatibility implementation of 
    this rule change.
    
    VI. Environmental Impact: Categorical Exclusion
    
        The Commission has determined that this final rule is the type of 
    action described in categorical exclusion 10 CFR 51.22(c)(3)(i) for 
    amendments to Part 35 that relate to renewals of licenses. Therefore, 
    neither an environmental statement nor an environmental assessment has 
    been prepared for this final regulation.
    
    VII. Paperwork Reduction Act Statement
    
        This final rule reduces the burden for both medical licensees and 
    the NRC because license terms for Part 35 licensees could be 
    established by policy, for as many as 10 years, as is the case for 
    other materials licensees. However, the reduced burden from less 
    frequent license renewal will not be realized in the near future 
    because the affected licenses are operating under a 5-year extension of 
    current licenses granted in 1995. The impact of that one-time extension 
    is addressed in the current supporting statement for NRC Form 313, 
    ``Application for Material License,'' which was approved by the Office 
    of Management and Budget (OMB) under OMB Clearance No. 3150-0120 and 
    which expires on July 31, 1999. The data on reduced burden from 
    extension of the license term for all material licenses and from other 
    actions taken to streamline the licensing process will be included in 
    the request for renewal of the information collection requirements on 
    NRC Form 313 in 1999. This is appropriate because the next OMB 
    clearance extension will cover 1999-2002, when the medical licenses 
    currently under the 5-year extension will expire and will be affected 
    by this rulemaking. Send comments on any aspect of this information 
    collection, including suggestions for further reducing the burden, to 
    the Information and Records Management Branch (T-6F33), U.S. Nuclear 
    Regulatory
    
    [[Page 31606]]
    
    Commission, Washington, DC 20555-0001, or by Internet electronic mail 
    at [email protected]; and to the Desk Officer, Office of Information and 
    Regulatory Affairs, NEOB-10202 (3150-0014), Office of Management and 
    Budget, Washington, DC 20503.
    
    Public Protection Notification
    
        If a document used to impose an information collection does not 
    display a currently valid OMB control number, the NRC may not conduct 
    or sponsor, and a person is not required to respond to, the information 
    collection.
    
    VIII. Regulatory Analysis
    
    Problem
    
        The current rule requirement, regarding the term of medical 
    licenses, is codified in 10 CFR 35.18 and states that ``The Commission 
    shall issue a license for the medical use of byproduct material for a 
    term of five years.'' The license term of other materials licenses, as 
    established by Commission policy, is up to 10 years. There is an 
    inconsistency as to duration and manner of specifying the license terms 
    of medical use licenses and all other materials licenses. Based on the 
    above, the following options were considered.
    
    Alternative Approaches
    
        1. Take no Action: Maintain the requirement that licenses issued 
    pursuant to Part 35 would be issued for 5 years.
        This option would continue the inconsistencies between medical 
    licenses and all other materials licenses as to the duration and 
    specification of license terms. Terms for medical use licenses are 
    established in codified regulations, whereas the term for other 
    materials licenses is now set by policy. Also, this option would result 
    in disparities in the duration of the term for materials licenses. 
    Medical use licenses would continue to be issued for 5-year terms 
    whereas the duration of the term for other materials licenses is up to 
    10 years.
        2. Revise 10 CFR 35.18: Revise the regulations to delete any 
    reference to the license term for licenses issued pursuant to part 35.
        This option would result in consistency between how license terms 
    for medical licenses and all other materials licenses are established 
    and in the duration of these licenses. Commission decisions regarding 
    the duration of a materials license could therefore apply uniformly to 
    all types of materials licenses. After final rulemaking action to 
    revise 10 CFR 35.18, the license term for licenses issued pursuant to 
    part 35 would be set by the already established policy for as many as 
    10 years.
    
    Value and Impact
    
        The license renewal process is resource-intensive for both the 
    licensee and NRC. At the time of license renewal, licensees submit to 
    NRC any changes in operations, personnel, facility, equipment, or 
    applicable procedures. Because NRC is in contact with the licensees on 
    an ongoing basis, many of these changes are identified during the 
    inspection and license amendment process. Therefore, the rulemaking to 
    remove the 5-year license term for medical use of byproduct material 
    would not change the health and safety requirements imposed on 
    licensees.
        By removing the reference to the 5-year term in 10 CFR 35.18 and, 
    with the Commission's February 1997 extension of the license term for 
    as many as 10 years for all materials licenses issued pursuant to parts 
    30, 40, and 70, there is a reduction in the regulatory burden for 
    approximately 1,900 NRC licensees that use byproduct material for 
    medical procedures. Estimated savings are based on the assumption that 
    these licensees would only be required to submit a renewal application 
    every 10 years as opposed to every 5 years, resulting, on average, in a 
    savings of 190 applications per year. However, offsetting these 
    savings, medical licensees may need to submit an average of one 
    additional amendment during the 10-year period to account for changes 
    in operations that would have routinely been addressed when the license 
    was renewed on a 5-year cycle. Assuming that a typical license renewal 
    application and typical amendment involves 19 hours and 4 hours of 
    licensee professional effort, respectively, there would be a net 
    savings per licensee of 15 hours. Based on an industry professional 
    labor rate of $125 per hour, the annual industry-wide savings would 
    approximate $356,000. Over a 30-year time frame, based on a 7-percent 
    real discount rate, the present worth savings to industry would 
    approximate $4.4 million.
        Similarly, this rulemaking is also cost effective for the NRC 
    because fewer resources would be required to review and process renewal 
    applications. On average, it takes approximately 14 hours of NRC 
    professional time to renew a medical license and 4 hours to review and 
    issue a license amendment. This means a net savings to the NRC of 10 
    hours per licensee. Assuming an NRC labor rate of $125 per hour, and on 
    average, 190 applications per year, the annual NRC savings would equal 
    $237,000. The 30-year present worth savings to the NRC would 
    approximate $2.9 million.
    
    Conclusion
    
        This rulemaking, to remove the 5-year license term for medical use 
    of byproduct material, is promulgated so the term for medical licenses 
    will be consistent with that of other materials licenses (set by policy 
    to be as many as 10 years). The extension will reduce the 
    administrative burden of license renewals for both NRC and licensees 
    and will support NRC's goal of streamlining the licensing process 
    without any reduction in health and safety. NRC may issue some licenses 
    for shorter terms if warranted by the individual circumstances of 
    license applicants.
    
    Decisional Rationale
    
        Based on the desire to reduce burden whenever it is possible to do 
    so without reducing protection of public health and safety, to maintain 
    consistency among license terms for materials licensees, and the cost 
    effectiveness of longer license terms, the NRC is amending 10 CFR part 
    35 to eliminate the 5-year term limit for medical use licenses and 
    allow the license term to be set by policy, as is the case for other 
    materials licenses.
    
    IX. Regulatory Flexibility Certification
    
        As required by the Regulatory Flexibility Act of 1980, 5 U.S.C. 
    605(b), the Commission certifies that this rule will not have a 
    significant economic impact on a substantial number of small entities. 
    By removing the reference to the 5-year license term in 10 CFR 35.18, 
    the duration of medical use licenses will be set by policy, resulting 
    in a reduction in the regulatory burden for NRC medical use licensees.
    
    X. Backfit Analysis
    
        The NRC has determined that the backfit rule, 10 CFR 50.109, does 
    not apply to this final rule and, therefore, that a backfit analysis is 
    not required for this final rule because the amendment does not involve 
    any provision that would impose backfits as defined in 10 CFR 
    50.109(a)(1).
    
    Small Business Regulatory Enforcement Fairness Act
    
        In accordance with the Small Business Regulatory Enforcement 
    Fairness Act of 1996, the NRC has determined that this action is not a 
    ``major rule'' and has verified this determination with the Office of 
    Information and Regulatory Affairs, Office of Management and Budget.
    
    [[Page 31607]]
    
    List of Subjects in 10 CFR Part 35
    
        Byproduct material, Criminal penalties, Drugs, Health facilities, 
    Health professions, Medical devices, Nuclear materials, Occupational 
    safety and health, Radiation protection, Reporting and recordkeeping 
    requirements.
        For the reasons set out in the preamble and under the authority of 
    the Atomic Energy Act of 1954, as amended, the Energy Reorganization 
    Act of 1974, as amended, and 5 U.S.C. 552 and 553, the NRC is adopting 
    the following amendment to 10 CFR part 35.
    
    PART 35--MEDICAL USE OF BYPRODUCT MATERIAL
    
        1. The authority citation for part 35 continues to read as follows:
    
        Authority: Secs. 81, 161, 182, 183, 68 Stat. 935, 948, 953, 954, 
    as amended (42 U.S.C. 2111, 2201, 2232, 2233); sec. 201, 88 Stat. 
    1242, as amended (42 U.S.C. 5841).
    
        2. The introductory text of Sec. 35.18 is revised to read as 
    follows:
    
    
    Sec. 35.18  License issuance.
    
        The Commission shall issue a license for the medical use of 
    byproduct material if:
    * * * * *
        Dated at Rockville, Md., this 20th day of May 1998.
    
        For the Nuclear Regulatory Commission.
    L. Joseph Callan,
    Executive Director for Operations.
    [FR Doc. 98-15400 Filed 6-9-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Effective Date:
7/10/1998
Published:
06/10/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Rule
Action:
Final rule.
Document Number:
98-15400
Dates:
This regulation becomes effective on July 10, 1998.
Pages:
31604-31607 (4 pages)
RINs:
3150-AF77: License Term for Medical Licenses
RIN Links:
https://www.federalregister.gov/regulations/3150-AF77/license-term-for-medical-licenses
PDF File:
98-15400.pdf
CFR: (1)
10 CFR 35.18