94-14352. Williams Natural Gas Co.; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 59, Number 113 (Tuesday, June 14, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-14352]
    
    
    [[Page Unknown]]
    
    [Federal Register: June 14, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP94-586-000]
    
     
    
    Williams Natural Gas Co.; Notice of Request Under Blanket 
    Authorization
    
    June 8, 1944.
        Take notice that on June 3, 1994, Williams Natural Gas Company 
    (WNG), P.O. Box 3288, Tulsa, Oklahoma 74101, filed in Docket No. CP94-
    586-000 a request pursuant to Sec. 157.205 of the Commission's 
    Regulations under the Natural Gas Act (18 CFR 157.205) for 
    authorization to install a total of approximately 12 miles of 16-inch 
    lateral pipeline, measuring, regulating and appurtenant facilities for 
    the delivery of transportation gas to Empire District Electric Company 
    (Empire) at two locations in Jasper County, Missouri under WNG's 
    blanket certificate issued in Docket No. CP82-479-000 pursuant to 
    Section 7 of the Natural Gas Act, all as more fully set forth in the 
    request that is on file with the Commission and open to public 
    inspection.
        WNG states that the total projected volume of delivery is estimated 
    to be approximately 9.5 Bcf annually with a total peak day volume 
    estimated to be 30 Mmcf. WNG further states that the estimated cost of 
    construction is $4,315,680 which would be paid with available funds.
        WNG says that this charge is not prohibited by an existing tariff 
    and it has sufficient capacity to accomplish the deliveries specified 
    without detriment or disadvantage to its other customers.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Sec. 157.205 of the 
    Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the 
    request. If no protest is filed within the time allowed therefor, the 
    proposed activity shall be deemed to be authorized effective the day 
    after the time allowed for filing a protest. If a protest is filed and 
    not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 94-14352 Filed 6-13-94; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
06/14/1994
Department:
Energy Department
Entry Type:
Uncategorized Document
Document Number:
94-14352
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: June 14, 1994, Docket No. CP94-586-000