02-15287. In the Matter of J. L. Shepherd & Associates, San Fernando, CA; Confirmatory Order Relaxing Order (Effective Immediately)
-
Start Preamble
I
J. L. Shepherd & Associates (JLS&A) was the holder of Quality Assurance (QA) Program Approval for Radioactive Material Packages No. 0122 (Approval No. 0122), issued by the U.S. Nuclear Regulatory Commission (NRC or Commission) pursuant to 10 CFR part 71, subpart H. QA activities authorized by Approval No. 0122 include: design, procurement, fabrication, assembly, testing, modification, maintenance, repair, and use of transportation packages subject to the provisions of 10 CFR part 71. Approval No. 0122 was originally issued January 17, 1980. Based on JLS&A's failure to comply with 10 CFR part 71, QA Program Approval No. 0122 was withdrawn by the immediately effective NRC Order, dated July 3, 2001, (66 FR 36603, July 12, 2001).
II
The NRC issued the July 3, 2001, Order (July 2001 Order) because the NRC lacked confidence that JLS&A would implement the QA Program approved by the NRC in accordance with 10 CFR part 71, subpart H, in a manner that would assure the required preparation and use of transportation packages in full conformance with the terms and conditions of an NRC Certificate of Compliance (CoC) and with 10 CFR part 71.
Subsequent to the July 2001 Order, JLS&A requested interim relief on several occasions, from the July 2001 Order based on JLS&A's proposed Near-Term Corrective Action Plan, to allow shipments in U.S. Department of Transportation specification packaging designated as 20WC. Based on a showing of good cause, the NRC issued Confirmatory Orders, dated September 19, 2001, (66 FR 49708, September 28, 2001), December 13, 2001, (66 FR 67556, December 31, 2001), March 29, 2002, (67 FR 16457, April 5, 2002), and April 26, 2002, (67 FR 22462, May 3, 2002), which relaxed the July 2001 Order by granting interim relief to allow specific shipments to identified customers in 20WC packages in accordance with JLS&A's Near-Term Corrective Action Plan, provided JLS&A satisfactorily completed certain commitments.
III
By letters dated February 26, 2002, as supplemented March 13, 18, and 25, 2002, JLS&A requested authorization to make additional shipments to customers not approved by the September 19, 2001, Order. JLS&A proposes to use the Near-Term Corrective Action Plan specified in the September 19, 2001, Confirmatory Order. JLS&A committed to: (1) Inspect the 20WC package (both shield and overpack); (2) document the inspection in a separate report; (3) perform the shipping and inspection function only by trained personnel; and (4) have the Independent Auditor verify compliance of each shipment with the foregoing commitments and certify such compliance in the monthly reports to the NRC. NRC withheld a decision on this part of the JLS&A request until after a pre-decisional enforcement conference was held with JLS&A. This Order represents NRC's final decision on JLS&A's February 26, 2002, request.
In addition, on May 23, 2002, JLS&A consented to issuance of this Confirmatory Order granting interim relief from the July 2001 Order subject to the foregoing commitments, as set forth in Section IV below, and agreed that this Confirmatory Order is to be effective upon issuance, and agreed to waive its right to a hearing on this action. Implementation of these commitments will provide assurance that sufficient resources will be applied to the QA program, and that the program will be conducted safely and in accordance with NRC requirements.
I find that JLS&A's commitments as set forth in Section IV are acceptable and necessary and conclude that with these commitments the public health and safety are reasonably assured. The NRC staff reviewed JLS&A's relief request and JLS&A's safety performance under the above mentioned relaxation Orders, to determine whether to grant the requested relief with assurances that public health and safety are maintained. Furthermore, the NRC staff has recommended that an extension of JLS&A's request is warranted. In view of the foregoing, I have determined that the public health and safety require that JLS&A's commitments be confirmed by this Confirmatory Order. Based on the above and JLS&A's consent, this Confirmatory Order is effective immediately upon issuance.
IV
Accordingly, pursuant to Sections 62, 81, 161b, 161i, 182 and 186 of the Atomic Energy Act of 1954, as amended, and the Commission's regulations in 10 CFR Section 2.202 and 10 CFR Parts 71 and 110, It is hereby ordered, Effective Immediately, that the July 3, 2001, Order is relaxed to grant JLS&A Interim Relief, To Complete shipments in 20WCs to or From Any Customer, Until May 31, 2003, In Accordance with JLS&A's Near-Term Corrective Action Plan, Provided:
1. JLS&A uses the implementing procedures for the 1995 QA program plan, as revised, and the Near-Term Corrective Action Plan to complete an inspection of the 20WC packages involved in the shipments. The inspection will confirm that the packages and associated procedures are in conformance with 49 CFR 178.362, “Specification 20WC wooden protective jacket.” Each inspection will include, at a minimum, actual physical measurements, and visual inspections for damage, corrosion, or other potentially unacceptable conditions; Start Printed Page 41532
2. JLS&A documents the results of each inspection in separate reports approved by the QA Administrator and prepared in accordance with the revised 1995 QA program plan and implementing procedures. The report will include the list of attributes verified, the acceptance criteria, and the results for each attribute;
3. JLS&A uses JLS&A's staff, contractors, and sub-contractors, trained in the Near-Term Corrective Action Plan and the revised 1995 QA program plan and implementing procedures for conducting the inspections listed in the above conditions;
4. JLS&A uses an Independent Auditor, approved by the Commission, to ensure that the three conditions listed above have been completed. Additionally, the Independent Auditor shall conduct quarterly QA program audits and will provide NRC with a report by the 20th of the month following the quarter. The Independent Auditor shall verify the compliance of each shipment with the three Conditions listed above and certify to the Commission in its quarterly reports and,
5. JLS&A will stop all shipping operations if the audit conducted by the Independent Auditor identifies significant safety concerns associated with the JLS&A conduct of shipping operations. In such an event, JLS&A shall inform the NRC of the audit findings and JLS&A proposed corrective actions within 3 business days of the identification of the audit findings to JLS&A by the Independent Auditor. JLS&A will suspend all shipping operation until the safety concerns are corrected and the Independent Auditor has found the corrective action acceptable. The Independent Auditor will inform NRC of the audit findings, JLS&A corrective actions, and the results of the Independent Auditor's review of the corrective actions in its quarterly audits.
The Director, Office of Enforcement, or the Director, Office of Nuclear Material Safety and Safeguards, may in writing, relax or rescind this Confirmatory Order upon demonstration of good cause by JLS&A.
V
In accordance with 10 CFR Section 2.202, any person, other than JLS&A, adversely affected by this Confirmatory Order may request a hearing within 20 days of its issuance. Where good cause is shown, consideration will be given to extending the time to request a hearing. A request for extension of time must be made in writing to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555, and include a statement of good cause for the extension. Any request for a hearing shall be submitted to the Secretary, U.S. Nuclear Regulatory Commission, ATTN: Rulemakings and Adjudications Staff, Washington, DC 20555. Copies of the hearing request also should be sent to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555, to the Director, Office of Nuclear Material Safety and Safeguards at the same address, to the Assistant General Counsel for Materials Litigation and Enforcement at the same address, to the Regional Administrator, NRC Region IV, 611 Ryan Plaza Drive, Suite 400, Arlington, TX 76011, and to JLS&A. If such person requests a hearing, that person shall set forth with particularity the manner in which his or her interest is adversely affected by this Confirmatory Order and shall address the criteria set forth in 10 CFR Section 2.714(d).
If a hearing is requested by a person whose interest is adversely affected, the Commission will issue an Order designating the time and place of any hearing. If a hearing is held, the issue to be considered at such hearing shall be whether this Confirmatory Order should be sustained.
In the absence of any request for hearing, or written approval of an extension of time in which to request a hearing, the provisions specified in Section IV above shall be final 20 days from the date of this Confirmatory Order without further Order or proceedings. If an extension of time for requesting a hearing has been approved, the provisions specified in Section IV shall be final when the extension expires if a hearing request has not been received. A request for hearing shall not stay the immediate effectiveness of this confirmatory order.
Start SignatureDated this 6th day of June 2002.
For the Nuclear Regulatory Commission.
Frank J. Congel,
Director, Office of Enforcement.
[FR Doc. 02-15287 Filed 6-17-02; 8:45 am]
BILLING CODE 7590-01-P
Document Information
- Published:
- 06/18/2002
- Department:
- Nuclear Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 02-15287
- Pages:
- 41531-41532 (2 pages)
- Docket Numbers:
- Docket No. 71-0122, Approval No. 0122, EA-01-164
- PDF File:
- 02-15287.pdf