[Federal Register Volume 60, Number 117 (Monday, June 19, 1995)]
[Notices]
[Pages 32001-32003]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-14858]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. EG95-56-000, et al.]
North America Energy Services Company, et al. Electric Rate and
Corporate Regulation Filings
June 12, 1995.
Take notice that the following filings have been made with the
Commission:
1. North American Energy Services
[Docket No. EG95-56-000]
On June 7, 1995, North American Energy Services Company, a
Washington corporation (``Applicant''), with its principal executive
office at Issaquah, Washington, filed with the Federal Energy
Regulatory Commission an application for determination of exempt
wholesale generator status pursuant to Part 365 of the Commission's
regulations (the ``Application'').
Applicant has entered into an operation and maintenance subcontract
with Cortes Operating Company, S.A. de C.V., a company organized under
the laws of Honduras, to operate and maintain an 80-megawatt fuel oil-
fired, electric generating plant located near Puerto Cortes, Honduras
(the ``Project''). Project facilities also include a heavy fuel line,
fuel storage tanks and a 138-kV transmission line that is owned by
Empresa Nacional De Energia Electrica, a Honduran utility. The Project
commenced generating electric power during May 1994.
Comment date: July 3, 1995, in accordance with Standard Paragraph E
at the end of this notice. The Commission will limit its consideration
of comments to those that concern the adequacy or accuracy of the
application.
2. Midwest Power Systems Inc.
[Docket No. EL95-51-000]
Take notice that on June 1, 1995, Midwest Power, a division of
Midwest Power Systems Inc. (Midwest Power), filed a Petition for
Declaratory Order pursuant to Rule 207(a)(2) of the Commission's Rules
of Practice and Procedure. Midwest requests the Commission to rule on
the constitutionality of Iowa Code Secs. 476.41-.45.
Comment date: July 13, 1995, in accordance with Standard Paragraph
E at the end of this notice.
3. Texican Energy Ventures, Inc.
[Docket No. ER94-1362-001]
Take notice that on June 1, 1995, Texican Energy Ventures, Inc.
(Texican) filed certain information as required by the Commission's
July 25, 1994, order in Docket No. ER94-1362-000. Copies of Texican's
informational filing are on file with the Commission and are available
for public inspection.
4. CLP Hartford Sales, L.L.C
[Docket No. ER95-393-002]
Take notice that on May 24, 1995, CLP Hartford Sales, L.L.C. (CLP
Hartford) filed certain information as required by the Commission's
February 22, 1995, order in Docket No. ER95-393-002. Copies of CLP
Hartford's informational filing are on file with the Commission and are
available for public inspection.
5. Potomac Electric Power Company
[Docket No. ER95-543-000]
Take notice that on May 3, 1995, Potomac Electric Power Company
submitted a further revised explanation of Pepco's treatment of the
cost of emission allowances in its coordination rates in compliance
with Order No. 579.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
6. Vermont Electric Power Company, Inc.
[Docket No. ER95-741-000]
Take notice that Vermont Electric Power Company, Inc. on June 8,
1995, tendered for filing an amendment in the above-referenced docket.
[[Page 32002]]
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
7. Boston Edison Company
[Docket Nos. ER95-773-000, ER95-774-000 and ER95-775-000]
Take notice that on June 7, 1995 Boston Edison Company tendered for
filing a corrected version of Revised Original Page No. of Schedule II
of FERC Electric Tariff, Original Volume No. 6, Power Sales and
Exchange Tariff.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
8. Northern Indiana Public Service Commpany
[Docket No. ER95-842-000]
Take notice that on May 24, 1995 Northern Indiana Public Service
Company (Northern) tendered for filing an Addendum to the Interchange
Agreement Between Northern Indiana Public Service Company and Rainbow
Energy Marketing Corporation.
The Addendum specifies the treatment of emissions allowance costs
included as out-of-pocket costs for sales by Northern.
Copies of this filing have been sent to Rainbow Energy Marketing
Corporation and the Indiana Utility Regulatory Commission.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
9. CNB/Olympic Gas Services
[Docket No. ER95-964-000]
Take notice that on June 2, 1995, CNB/Olympic Gas Services tendered
for filing additional information to its April 27, 1995 filing in the
above-referenced docket.
Comment date: June 23, 1995, in accordance with Standard Paragraph
E at the end of this notice.
10. Florida Power & Light Company
[Docket No. ER95-1120-000]
Take notice that on May 30, 1995, Florida Power & Light Company
(FPL) tendered for filing proposed Service Agreements with the City of
St. Cloud for transmission service under FPL's Transmission Tariff Nos.
2 and 3.
FPL requests that the proposed Service Agreements be permitted to
become effective on June 1, 1995, or as soon thereafter as practicable.
FPL states that this filing is in accordance with Section 35 of the
Commission's regulations.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
11. Carolina Power & Light Company
[Docket No. ER95-1139-000]
Take notice that on May 31, 1995, Carolina Power & Light Company,
tendered for filing an application for approval of the rate of return
on equity to be effective under the Power Coordination Agreement
between Carolina Power & Light Company and North Carolina Electric
Membership Corporation.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
12. Northern Indiana Public Service Company
[Docket No. ER95-1140-000]
Take notice that on May 31, 1995, Northern Indiana Public Service
Company, tendered for filing an Interchange Agreement between Northern
Indiana Public Service Company and Stand Energy Corporation.
The Interchange Agreement allows for General Purpose transactions
and Negotiated Capacity transactions. General Purpose transactions are
economy based energy transactions which may be made available from the
supplying party's resources from time to time. Negotiated Capacity
transactions provide capacity and energy to the buyer, customized to
the specific needs at the time of the reservation.
Copies of this filing have been sent to Stand Energy Corporation
and to the Indiana Utility Regulatory Commission.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
13. Central Power and Light Company
[Docket No. ER95-1141-000]
Take notice that on May 31, 1995, Central Power and Light Company
(CPL), submitted for filing an unexecuted Transmission Service
Agreement, dated May 31, 1995, between CPL and Rio Grande Electric
Cooperative, Inc. (Rio Grande). Under the TSA, CPL will provide
wheeling service to Rio Grande which will permit Rio Grande to
substitute West Texas Utilities Company as the full-requirements
supplier for Rio Grande load currently served by CPL.
CPL requests an effective date of June 1, 1995 and, accordingly,
seeks waiver of the Commission's notice requirements. Copies of this
filing were served upon Rio Grande and the Public Utility Commission of
Texas.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
14. The Washington Water Power Company
[Docket No. ER95-1142-000]
Take notice that on May 31, 1995, The Washington Water Power
Company (WWP), tendered for filing with the Federal Energy Regulatory
Commission pursuant to 18 CFR 35.13, a Notice of Cancellation
concerning Rate Schedule FERC No. 185. Effective July 31, 1995 the
capacity and energy sales agreement between WWP and the Public Utility
District No. 1 of Pen Oreille County (Pend Oreille) is canceled.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
15. Western Resources, Inc.
[Docket No. ER95-1150-000]
Take notice that on June 1, 1995, Western Resources, Inc. (Western
Resources), tendered for filing a change in Service Agreement No. 2
under its FERC Electric Tariff, Original Volume No. 1. Western
Resources states that the change is to amend Exhibit A to the
Transmission Service Agreement between Western Resources and the City
of Fredonia, Kansas to reflect increase contract capacity.
Copies of this filing were served upon the City of Fredonia and the
Kansas Corporation Commission.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
16. Central Illinois Public Service Company
[Docket No. ER95-1151-000]
Take notice that on June 1, 1995, Central Illinois Public Service
Company (CIPS), submitted service agreements establishing ten new
customers under CIPS' Rate Schedule for Sales of Next Hour
Interruptible Energy, Next-Hour Non-Interruptible Energy and Next Hour
Firm Wheeling Service (Rate Schedule HSW).
CIPS requests an effective date of May 15, 1995 for the ten service
agreements, and, accordingly, seeks waiver of the Commission's notice
requirements. Copies of this filing were served upon the ten customers
and the Illinois Commerce Commission.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
17. Florida Power Corporation
[Docket No. ER95-1152-000]
Take notice that on June 1, 1995, Florida Power Corporation,
tendered for filing an amendment to its interchange contract with
Alabama Electric Cooperative, Inc., pursuant to which the
[[Page 32003]] parties have agreed to the interchange of Backup
Interchange Service and Opportunity Sales Interchange Service. Florida
Power requests that the amendment become effective on August 1, 1995.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
18. Kentucky Utilities Company
[Docket No. ER95-1153-000]
Take notice that on June 1, 1995, Kentucky Utilities Company filed
Letter Agreements providing for power sales between itself and Louis
Dreyfus Electric Power Inc. and Electric Clearinghouse, Inc. KU
requests waiver and an effective date of June 1, 1995.
Comment date: June 26, 1995, in accordance with Standard Paragraph
E at the end of this notice.
Standard Paragraph
E. Any person desiring to be heard or to protest said filing should
file a motion to intervene or protest with the Federal Energy
Regulatory Commission, 825 North Capitol Street, N.E., Washington, D.C.
20426, in accordance with Rules 211 and 214 of the Commission's Rules
of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such
motions or protests should be filed on or before the comment date.
Protests will be considered by the Commission in determining the
appropriate action to be taken, but will not serve to make protestants
parties to the proceeding. Any person wishing to become a party must
file a motion to intervene. Copies of this filing are on file with the
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 95-14858 Filed 6-16-95; 8:45 am]
BILLING CODE 6717-01-P