2011-15254. Distrigas of Massachusetts LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Heating Value and Wobbe Index Reduction Project and Request for Comments on Environmental Issues  

  • Start Preamble

    The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Heating Value and Wobbe Index Reduction Project (Project) involving construction and operation of facilities by Distrigas of Massachusetts LLC (DOMAC) in Everett, Massachusetts. This EA will be used by the Commission in its decision-making process to determine whether the project is in the public convenience and necessity.

    This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the Project. Your input will help the Commission staff determine what issues need to be evaluated in the EA. Please note that the scoping period will close on July 14, 2011.

    This notice is being sent to the Commission's current environmental mailing list for this project. State and local government representatives are asked to notify their constituents of this planned project and encourage them to comment on their areas of concern.

    A fact sheet prepared by the FERC entitled “An Interstate Natural Gas Facility On My Land? What Do I Need To Know?” was attached to the project notice DOMAC provided to landowners. This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission's proceedings. It is also available for viewing on the FERC Web site (http://www.ferc.gov).

    Summary of the Proposed Project

    DOMAC proposes to design, construct, operate, and maintain a liquid nitrogen injection facility at its liquefied natural gas (LNG) Import Terminal in Everett, Massachusetts. The Project would allow DOMAC to retain its capability to adjust the heating value and Wobbe Index of regasified LNG while complying with the gas quality and interchangeability specifications of applicable FERC Gas Tariffs. The liquid nitrogen injection facility would replace DOMAC's limited air injection system for all of its regasified LNG send-out. Following completion of the Project, DOMAC would decommission and remove the air injection system. Liquid nitrogen would be supplied by truck to the Terminal at the liquid nitrogen truck offloading station for storage in the two proposed storage tanks. DOMAC anticipates construction of the Project to begin in April 2012 with an expected in-service date of October 1, 2012.

    The Project would consist of the following facilities:

    • Two liquid nitrogen storage tanks, each with a nominal capacity of 120,000 gallons;
    • Associated piping support systems and ancillary systems; andStart Printed Page 35883
    • A liquid nitrogen truck offloading station.

    The general location of the project facilities is shown in appendix 1.[1]

    Land Requirements for Construction

    The site of the Project would be located on a 4.69-acre parcel entirely within the DOMAC LNG Import Terminal and immediately adjacent to DOMAC's existing LNG truck loading area. Following construction, 0.69 acre would be maintained permanently for operation of the liquid nitrogen injection facility.

    The EA Process

    The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us [2] to discover and address concerns the public may have about proposals. This process is referred to as “scoping”. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. All comments received will be considered during the preparation of the EA.

    In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings:

    • Geology and soils;
    • Land use;
    • Water resources, fisheries, and wetlands;
    • Cultural resources;
    • Vegetation and wildlife;
    • Air quality and noise;
    • Endangered and threatened species; and
    • Public safety.

    We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas.

    Our independent analysis of the issues will be presented in the EA. The EA will be placed in the public record and, depending on the comments received during the scoping process, may be published and distributed to the public. A comment period will be allotted if the EA is published for review. We will consider all comments on the EA before we make our recommendations to the Commission. To ensure your comments are considered, please carefully follow the instructions in the Public Participation section on this page.

    With this notice, we are asking agencies with jurisdiction and/or special expertise with respect to environmental issues to formally cooperate with us in the preparation of the EA. These agencies may choose to participate once they have evaluated the proposal relative to their responsibilities. Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice.

    Public Participation

    You can make a difference by providing us with your specific comments or concerns about the Project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that they will be received in Washington, DC on or before July 14, 2011.

    For your convenience, there are three methods which you can use to submit your comments to the Commission. In all instances please reference the project docket number (CP11-485-000) with your submission. The Commission encourages electronic filing of comments and has expert eFiling staff available to assist you at (202) 502-8258 or efiling@ferc.gov.

    (1) You may file your comments electronically by using the eComment feature, which is located on the Commission's Web site at http://www.ferc.gov under the link to Documents and Filings. An eComment is an easy method for interested persons to submit brief, text-only comments on a project;

    (2) You may file your comments electronically by using the eFiling feature, which is located on the Commission's Web site at http://www.ferc.gov under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making. A comment on a particular project is considered a “Comment on a Filing;” or

    (3) You may file a paper copy of your comments at the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Room 1A, Washington, DC 20426.

    Environmental Mailing List

    The environmental mailing list includes Federal, State, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission's regulations) who own homes within certain distances of aboveground facilities and anyone who submits comments on the Project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed Project.

    If the EA is published for distribution, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2).

    Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want to become an “intervenor” which is an official party to the Commission's proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission's final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are included in the User's Guide under the “e-filing” link on the Commission's Web site.

    Additional Information

    Additional information about the project is available from the Commission's Office of External Affairs, at (866) 208-FERC, or on the FERC Web site at http://www.ferc.gov using the Start Printed Page 35884“eLibrary” link. Click on the eLibrary link, click on “General Search” and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP11-485). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings.

    In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to http://www.ferc.gov/​esubscribenow.htm.

    Finally, public meetings or site visits will be posted on the Commission's calendar located at http://www.ferc.gov/​EventCalendar/​EventsList.aspx along with other related information.

    Start Signature

    Dated: June 14, 2011.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.  The appendices referenced in this notice are not being printed in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at http://www.ferc.gov using the link called “eLibrary” or from the Commission's Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502-8371. For instructions on connecting to eLibrary, refer to the last page of this notice.

    Back to Citation

    2.  “We,” “us,” and “our” refer to the environmental staff of the Commission's Office of Energy Projects.

    Back to Citation

    [FR Doc. 2011-15254 Filed 6-17-11; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Comments Received:
0 Comments
Published:
06/20/2011
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2011-15254
Pages:
35882-35884 (3 pages)
Docket Numbers:
Docket No. CP11-485-000
PDF File: