2023-13079. Pyrites Hydro, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions  

  • Start Preamble

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

    a. Type of Application: New Major License.

    b. Project No.: 6115–016.

    c. Date filed: August 31, 2021.

    d. Applicant: Pyrites Hydro, LLC (Pyrites Hydro).

    e. Name of Project: Pyrites Hydroelectric Project (Pyrites Project or project).

    f. Location: On the Grass River near the Town of Canton, St. Lawrence County, New York.

    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825(r).

    h. Applicant Contact: Curtis Mooney, Manager, Regulatory Affairs, Patriot Hydro, LLC, 59 Ayers Island Road, Bristol, New Hampshire 03222; (603) 744–0846 or cmooney@patriothydro.com.

    i. FERC Contact: Josh Dub at (202) 502–8138, or email at joshua.dub@ferc.gov.

    j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice.

    The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the Commission's eFiling system at https://ferconline.ferc.gov/​FERCOnline.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/​QuickComment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Pyrites Hydroelectric Project P–6115–016.

    The Commission's Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    k. This application has been accepted and is now ready for environmental analysis.

    The Council on Environmental Quality (CEQ) issued a final rule on April 20, 2022, revising the regulations under 40 CFR parts 1502, 1507, and 1508 that Federal agencies use to implement the National Environmental Policy Act (NEPA) (see National Environmental Policy Act Implementing Regulations Revisions, 87 FR 23,453–70). The final rule became effective on May 20, 2022. Commission staff intends to conduct its NEPA review in accordance with CEQ's new regulations.

    l. The Pyrites Project consists of: (1) a 170-foot-long and 12-foot-high concrete Ambursen overflow spillway with 1.5-foot-high flashboards, a 115-foot-long concrete auxiliary spillway, and a 208-foot-long non-overflow dam, which includes a 50-foot-wide intake structure; (2) a 6-foot-diameter, 700-foot-long steel penstock running from the intake structure to an upper powerhouse and a 10-foot-diameter, 2,160-foot-long penstock running from the intake structure to a lower powerhouse; (3) a 21-foot by 31-foot upper powerhouse located 700 feet downstream of the intake structure containing one 1.2-megawatt (MW) turbine/generator unit operating under a rated head of 76 feet and a 50-foot by 53-foot lower powerhouse located 1,200 feet downstream of the tailrace containing two 3.5–MW turbine/generator units operating under a rated head of 111 feet; (4) a 50-foot by 97-foot, 115/4.16/2.3-kilovolt (kV) switchyard and substation for use by both powerhouses; (5) a 470-foot-long 2.3-kV transmission line connecting the upper powerhouse to the switchyard; (6) a 1,150-foot-long 4.16-kV transmission line connecting the lower powerhouse to the switchyard; and (7) appurtenant facilities.

    The Pyrites Project is operated in a run-of-river mode with an average annual generation of 27,865 megawatt-hours.

    Pyrites Hydro proposes to continue to operate the project in a run-of-river mode and maintain a continuous minimum flow to the bypassed reach of 45 cubic feet per second or inflow to the impoundment, whichever is less.

    m. A copy of the application can be viewed on the Commission's website at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. At this time, the Commission has suspended access to the Commission's Public Reference Room. For assistance, contact FERC at FERCOnline Support@ferc.gov or call toll-free, (886) 208–3676 or TTY, (202) 502–8659.

    All filings must (1) bear in all capital letters the title “COMMENTS,” “REPLY COMMENTS,” “RECOMMENDATIONS,” “TERMS AND CONDITIONS,” or “PRESCRIPTIONS;” (2) set forth in the heading the name of the applicant and Start Printed Page 39842 the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.

    You may also register online at http://www.ferc.gov/​docs-filing/​esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

    n. The applicant must file no later than 60 days following the date of issuance of this notice: (1) a copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. Please note that the certification request must comply with 40 CFR 121.5(b), including documentation that a pre-filing meeting request was submitted to the certifying authority at least 30 days prior to submitting the certification request. Please also note that the certification request must be sent to the certifying authority and to the Commission concurrently.

    o. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate.

    MilestoneTarget date
    Filing of Comments, Recommendations, Terms and Conditions, and PrescriptionsAugust 2023.
    Filing of Reply CommentsSeptember 2023

    p. The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ferc.gov.

    Start Signature

    Dated: June 13, 2023.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. 2023–13079 Filed 6–16–23; 8:45 am]

    BILLING CODE 6717–01–P

Document Information

Published:
06/20/2023
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2023-13079
Pages:
39841-39842 (2 pages)
Docket Numbers:
Project No. 6115-016
PDF File: