June 17, 1996.
Take notice that on May 31, 1996, Natural Gas Pipeline Company of
America (Natural), 701 East 22nd Street, Lombard, Illinois 60148, filed
in Docket No. CP96-552-000 an application pursuant to Section 7(b) of
the Natural Gas Act for permission and approval to abandon a sale,
exchange and transportation of natural gas involving Colorado
Interstate Gas Company (CIG), all as more fully set forth in the
application on file with the Commission and open to public inspection.
Natural proposes to abandon the services which were carried out
under
[[Page 31931]]
agreements on file with the Commission as Natural's Rate Schedules X-
56, X-83, and X-111 and authorized by the Commission in Docket Nos.
CP75-183, CP77-190 and CP79-204, as amended, respectively. It is stated
that under Rate Schedule X-56 Natural was receiving from CIG up to
10,000 Mcf of gas per day on a firm basis (plus additional volumes on a
best efforts basis, if available) from CIG's reserves in Lea County,
New Mexico, and delivering equivalent volumes to CIG at
interconnections in Texas and Oklahoma. It is further stated that
Natural had the option to purchase 25 percent of the volumes from CIG.
It is stated that under Rate Schedule X-83 CIG was receiving up to
2,000 Mcf of gas per day from Natural and delivering equivalent volumes
to Natural at interconnections in Beaver County, Oklahoma. It is stated
that under Rate Schedule X-111 CIG and Natural were transporting and
exchanging gas on a system-wide basis. It is asserted that CIG and
Natural have recently reached agreement resulting in the resolution of
imbalances. Natural states that it will cancel the 3 rate schedules on
receipt of abandonment authorization. Natural explains that no
facilities will be abandoned, and no customers will lose service as a
result of the proposed abandonments.
Any person desiring to be heard or to make any protest with
reference to said application should on or before July 8, 1996, file
with the Federal Energy Regulatory Commission, Washington, D.C. 20426,
a motion to intervene or a protest in accordance with the requirements
of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10).
All protests filed with the Commission will be considered by it in
determining the appropriate action to be taken but will not serve to
make the protestants parties to the proceeding. Any person wishing to
become a party to a proceeding or to participate as a party in any
hearing therein must file a motion to intervene in accordance with the
Commission's Rules.
Take further notice that, pursuant to the authority contained in
and subject to the jurisdiction conferred upon the Federal Energy
Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and
the Commission's Rules of Practice and Procedure, a hearing will be
held without further notice before the Commission or its designee on
this application if no motion to intervene is filed within the time
required herein, if the Commission on its own review of the matter
finds that a grant of the certificate is required by the public
convenience and necessity. If a motion for leave to intervene is timely
filed, or if the Commission on its own motion believes that a formal
hearing is required, further notice of such hearing will be duly given.
Under the procedure herein provided for, unless otherwise advised,
it will be unnecessary for Natural to appear or be represented at the
hearing.
Lois D. Cashell,
Secretary.
[FR Doc. 96-15812 Filed 6-20-96; 8:45 am]