95-15469. Amended Notice of Intent to Prepare an Environmental Impact Statement for the Continued Operation of the Pantex Plant and Associated Storage of Nuclear Weapon Components  

  • [Federal Register Volume 60, Number 121 (Friday, June 23, 1995)]
    [Notices]
    [Pages 32661-32663]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-15469]
    
    
    
    -----------------------------------------------------------------------
    
    
    DEPARTMENT OF ENERGY
    
    Amended Notice of Intent to Prepare an Environmental Impact 
    Statement for the Continued Operation of the Pantex Plant and 
    Associated Storage of Nuclear Weapon Components
    
    AGENCY: Department of Energy.
    
    ACTION: Amended Notice of Intent.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Department of Energy (DOE) issued a Notice of Intent for 
    the preparation of a site-wide Environmental Impact Statement (EIS) for 
    the Continued Operation of the Pantex Plant and Associated Storage of 
    Nuclear Weapon Components (59 FR 26635, May 23, 1994). In that notice, 
    alternatives involving the potential relocation of selected Pantex 
    Plant operations to other sites were not fully defined. DOE published 
    an EIS Implementation Plan (DOE/EIS-0225-IP, December 1994) which 
    defined the proposed scope of the EIS and the process of identifying 
    potential alternate sites. DOE has now identified the potential 
    reasonable alternate sites for relocation of selected Pantex Plant 
    operations which will be analyzed in the EIS, and is issuing this 
    amended Notice of Intent to announce these modifications to the scope 
    of the EIS and to solicit public comments regarding these changes.
    
    DATES: DOE invites the general public, other government agencies, and 
    all other interested parties to comment on the amended scope and 
    content of this EIS. DOE is soliciting additional oral and written 
    comments, suggestions, requests for information, and requests for 
    public meetings no later than July 24, 1995. These comments will 
    receive equal consideration to comments presented during the June 1994 
    scoping period. [[Page 32662]] 
    
    Oral Comments
    
        All interested parties are invited to record their comments, 
    suggestions, and requests concerning this EIS by calling the Pantex 
    Plant EIS Hotline at 1-800-788-0306. The Hotline will give instructions 
    on how to record your comments.
    
    Written Comments
    
        Written comments to assist DOE in identifying significant 
    environmental issues and the appropriate scope of this EIS, questions 
    concerning the Pantex Plant or the other sites involved, requests to be 
    placed on the Pantex Plant EIS mailing list, requests for copies of the 
    Implementation Plan, requests to be placed on the EIS distribution 
    list, and requests for public meetings should be directed to: Ms. 
    Nanette Founds, U.S. Department of Energy, Albuquerque Operations 
    Office, P.O. Box 5400, Albuquerque, New Mexico 87185-5400.
        Written comments, suggestions, and requests can be submitted using 
    the Pantex Plant EIS Faxline at 1-800-822-5499. Facsimiles should be 
    marked: Pantex Plant EIS.
    
    FOR FURTHER INFORMATION CONTACT: For information on DOE's NEPA process, 
    please contact: Ms. Carol Borgstrom, Director, Office of NEPA Policy 
    and Assistance (EH-42), U.S. Department of Energy, 1000 Independence 
    Avenue SW., Washington, DC 20585, 202-586-4600 or 1-800-472-2756.
    
    ADDRESSES: In addition to those locations listed in the original Notice 
    of Intent, copies of all written comments, transcripts of all oral 
    comments, and copies of the Implementation Plan will be prepared and 
    retained by DOE for inspection by the public at the following 
    additional locations:
    
    Pantex SWEIS Public Information Center, c/o Tetra Tech, Inc., 6900 I-40 
    West, Suite 260, Amarillo, Texas 79106, 806-355-9480
    U.S. Department of Energy, Public Reading Room, Washington State 
    University, 100 Sprout Road, Richland, WA 99352, 509-376-8583
    
    SUPPLEMENTARY INFORMATION:
    
    Program Changes
    
        The Implementation Plan (Plan) summarized the comments received 
    during scoping in June 1994, described the scope of the EIS, the 
    alternatives that were planned to be evaluated, and the methodology for 
    preparing the EIS. After publication of the Plan in December 1994, the 
    proposed action and alternatives for relocating some of the Pantex 
    Plant operations were modified. These modifications are described 
    below:
        Relocating Pantex Plant Weapons Operations: In the Plan, DOE 
    proposed to analyze the impacts of relocating some or all of the Pantex 
    Plant operations to one or more sites. The Nevada Test Site was 
    identified as the only alternate site for relocation of Pantex 
    operations involving disassembly, modification, maintenance, or quality 
    assurance of nuclear weapons components. Since the publication of the 
    Plan, DOE has begun planning a
        Stockpile Stewardship and Management Programmatic EIS (60 FR 31291, 
    June 14, 1995) that will address the nuclear weapons complex 
    requirements in the year 2005 and beyond. One of the anticipated 
    alternatives of this Programmatic EIS is the possible relocation of the 
    Pantex nuclear weapons operations to another site. Any decision on 
    relocation of Pantex nuclear weapons operations will be made in the 
    Record of Decision for the
        Stockpile Stewardship and Management Programmatic EIS and not the 
    Pantex site-wide EIS. Therefore, the Pantex site-wide EIS will not 
    examine the impacts at any other site of relocating the Pantex nuclear 
    weapons operations to that site. However, for completeness of analysis, 
    the Pantex site-wide EIS will evaluate the impacts at Pantex of 
    relocating these operations to another site. (See Implementation Plan, 
    Section 3.2.3, Option A.)
        Relocating Plutonium Pits Interim Storage Operations: The Pantex 
    site-wide EIS will analyze alternatives to the interim storage of 
    plutonium pits from disassembled weapons at Pantex pending decisions on 
    their disposition. Initially, DOE identified four DOE sites as 
    potential alternate pit storage locations pending future site 
    identification activities. These were: The Nevada Test Site; The 
    Savannah River Site in South Carolina; the Oak Ridge Reservation in 
    Tennessee; and the Los Alamos National Laboratory in New Mexico. Based 
    on further examination of more than 70 DOE and Department of Defense 
    (DOD) sites, DOE has modified the list of alternative sites for 
    relocating interim storage of plutonium pits. The Pantex site-wide EIS 
    will now analyze relocating interim pit storage from Pantex to each of 
    the following candidate sites: the Nevada Test Site; the Hanford 
    Reservation, the Savannah River Site, and DOD's Manzano Facility at 
    Kirtland Air Force Base in New Mexico. The Oak Ridge Reservation and 
    the Los Alamos National Laboratory have been eliminated as reasonable 
    interim pit storage sites due to inadequate storage space.
        Analysis of Storage of Depleted Uranium: DOE currently ships 
    depleted uranium components from disassembled weapons to the Oak Ridge 
    Reservation for routine processing and storage. The Plan identified 
    four alternate sites for interim storage of depleted uranium components 
    (See Implementation Plan, Section 3.2.3., Option B-3). However, DOE has 
    determined that there are currently no reasonable alternative sites for 
    the receipt of depleted uranium from disassembled weapons in the 5 to 
    10 year period covered by the Pantex Site-Wide EIS because of the lack 
    of facilities to perform the routine processing (demilitarization or 
    recycling) of this material at any site other than the Oak Ridge 
    Reservation. Therefore, the processing and storage of depleted uranium 
    will not be addressed in the Pantex site-wide EIS.
        Potential New Missions: Pantex has been identified as a reasonable 
    alternative location for actions being analyzed in other DOE EISs. 
    Pantex is one of the reasonable alternatives for the proposed new 
    tritium facility in the Tritium Supply and Recycling Programmatic EIS 
    (60 FR 14433, March 17, 1995). Pantex is also under consideration for 
    long-term plutonium component storage in the Long-Term Storage and 
    Disposition of Weapons-Usable Fissile Materials Programmatic EIS (59 FR 
    31985, June 21, 1994). In addition, Pantex may be identified as an 
    alternative for other defense missions during preparation of the 
    Stockpile Stewardship and Management Programmatic EIS. The Pantex site-
    wide EIS will consider the potential receipt of such new activities in 
    its cumulative impact analysis; however, decisions on where to locate 
    these new missions will be made on the basis of the programmatic EISs, 
    and not on the basis of the Pantex site-wide EIS.
    
    Subsequent Document Preparation
    
        After the completion of this additional public scoping process, DOE 
    will prepare an addendum to the Implementation Plan and make it 
    available in the public reading rooms. The addendum will record the 
    results of the additional comment period. DOE intends to complete the 
    draft EIS in December 1995 and will announce its availability in the 
    Federal Register. DOE will solicit comments from the public, 
    organizations, and other agencies on the draft EIS, and will consider 
    all comments in its preparation of the final EIS.
    
        [[Page 32663]] Issued in Washington, DC, on June 19, 1995.
    Tara O'Toole,
    Assistant Secretary Environment, Safety and Health.
    [FR Doc. 95-15469 Filed 6-22-95; 8:45 am]
    BILLING CODE 6450-01-P
    
    

Document Information

Published:
06/23/1995
Department:
Energy Department
Entry Type:
Notice
Action:
Amended Notice of Intent.
Document Number:
95-15469
Dates:
DOE invites the general public, other government agencies, and all other interested parties to comment on the amended scope and content of this EIS. DOE is soliciting additional oral and written comments, suggestions, requests for information, and requests for public meetings no later than July 24, 1995. These comments will receive equal consideration to comments presented during the June 1994 scoping period. [[Page 32662]]