2011-15697. Kodiak Electric Association, Inc.; Notice of Application Accepted for Filing, Ready for Environmental Analysis, Soliciting Comments, Motions To Intervene, Protests, Recommendations, Terms and Conditions, and Fishway Prescriptions  

  • Start Preamble

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection:

    a. Type of Application: Amendment of License.

    b. Project No.: 2743-071.

    c. Date Filed: May 20, 2011.

    d. Applicant: Kodiak Electric Association, Inc.

    e. Name of Project: Terror Lake Project.

    f. Location: The project is located on the Terror and Kizhuyak Rivers in Kodiak Island Borough, Alaska. The project occupies federal lands managed by the U.S. Fish and Wildlife Service within the Kodiak National Wildlife Refuge and on lands managed by the U.S. Coast Guard.

    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.

    h. Applicant Contact: Darron Scott, President/CEO, Kodiak Electric Association, Inc. P.O. Box 787, Kodiak, AK 99615-0787, (907) 486-7707.

    i. FERC Contact: Mr. Steven Sachs (202) 502-8666 or Steven.Sachs@ferc.gov.

    j. Deadline for filing motions to intervene and protests, comments, recommendations, terms and conditions, and fishway prescriptions is 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice.

    All documents may be filed electronically via the Internet. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site at http://www.ferc.gov/​docs-filing/​efiling.asp. If unable to be filed electronically, documents may be paper-filed. To paper-file, an original and seven copies should be mailed to: Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at http://www.ferc.gov/​docs-filing/​ecomment.asp. You must include your name and contact information at the end of your comments.

    Please include the project number (P-2743-071) on any comments, motions, recommendations, or terms and conditions filed.

    k. Description of Request: The applicant proposes to install a third turbine-generator unit at the project. The new unit would have an installed capacity of 11.25 megawatts (MW) and be contained entirely within the project's powerhouse. The proposal would increase the hydraulic capacity of the project from 300 to 435 cubic feet per second and the authorized installed capacity from 22.5 to 33.75 MW. Because the project was constructed with provisions for the third unit, no significant modifications to conduits, structures, or electrical equipment would be required.

    l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission's Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502-8371. This filing may also be viewed on the Commission's Web site at http://www.ferc.gov/​docs-filing/​efiling.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at http://www.ferc.gov/​docs-filing/​esubscription.asp to be notified via e-mail of new filings and issuances related to this or other pending projects. For assistance, call 1-866-208-3676 or e-mail FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is also available for inspection and reproduction at the address in item (h) above.

    m. Individuals desiring to be included on the Commission's mailing list should so indicate by writing to the Secretary of the Commission.

    n. Comments, Protests, or Motions To Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.

    o. Filing and Service of Responsive Documents: All filings must (1) Bear in all capital letters the title Start Printed Page 36912“COMMENTS”, “PROTEST”, “MOTION TO INTERVENE”, “TERMS AND CONDITIONS” or “FISHWAY PRESCRIPTIONS” as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the amendment. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.

    p. As provided for in 18 CFR 4.34(b)(5)(i), a license applicant must file, no later than 60 days following the date of issuance of this notice of acceptance and ready for environmental analysis: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification.

    Start Signature

    Dated: June 16, 2011.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. 2011-15697 Filed 6-22-11; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Comments Received:
0 Comments
Published:
06/23/2011
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2011-15697
Pages:
36911-36912 (2 pages)
Docket Numbers:
Project No. 2743-071
PDF File:
2011-15697.pdf