2017-12812. Notice of Final Federal Agency Actions on The Hampton Roads Crossing Study in the Cities of Hampton and Norfolk, Virginia  

  • Start Preamble

    AGENCY:

    Federal Highway Administration (FHWA), DOT.

    ACTION:

    Notice of limitation on claims for judicial review of actions by FHWA.

    SUMMARY:

    This notice announces actions taken by FHWA that are final. The actions relate to the widening of Interstate 64 to a consistent six-lane facility between Interstates 664 and 564 and the addition of a new bridge-tunnel parallel to the existing Interstate 64 Hampton Roads Bridge Tunnel. Those actions grant licenses, permits, and approvals for the project.

    DATES:

    By this notice, FHWA is advising the public of final agency actions subject to 23 U.S.C. 139(l)(1). A claim seeking judicial review of the Federal agency actions on the project will be barred unless the claim is filed on or before November 20, 2017. If the Federal law that authorizes judicial review of a claim provides a time period of less than 150 days for filing such claim, then that shorter time period still applies.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    For FHWA: Mr. Edward Sundra, Director of Program Development, FHWA Virginia Division, 400 North 8th Street, Richmond, Virginia 23219; telephone: Start Printed Page 28733(804) 775-3357; email: Ed.Sundra@dot.gov. The FHWA Virginia Division Office's normal business hours are 8:00 a.m. to 4:30 p.m. (Eastern Time). For the Virginia Department of Transportation: Scott Smizik, 1401 East Broad Street, Richmond, Virginia 23219; email: Scott.Smizik@VDOT.Virginia.gov; telephone: (804) 371-4082. The Virginia Department of Transportation's normal business hours are 7:00 a.m. to 4:00 p.m.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Notice is hereby given that FHWA has taken final agency actions subject to 23 U.S.C. 139(l)(1) by issuing licenses, permits, and approvals for the following project in the State of Virginia: Hampton Roads Crossing Study in the Cities of Hampton and Norfolk. The project involves the widening of Interstate 64 to a consistent six-lane facility between Interstates 664 and 564 and the addition of a new bridge-tunnel parallel to the existing Interstate 64 Hampton Roads Bridge Tunnel. The actions taken by FHWA, and the laws under which such actions were taken, are described in the Final Supplemental Environmental Impact Statement (SEIS) and Record of Decision (ROD). The Final SEIS was signed on April 25, 2017. The ROD was signed on June 12, 2017. The Final SEIS, ROD and other supporting documentation can be viewed on the project's Web site at: http://hamptonroadscrossingstudy.org/​. These documents and other project records are also available by contacting FHWA or the Virginia Department of Transportation at the phone numbers and addresses listed above.

    This notice applies to all Federal agency decisions as of the issuance date of this notice and all laws under which such actions were taken, including but not limited to:

    1. General: National Environmental Policy Act (NEPA) [42 U.S.C. 4321-4351]; Federal-Aid Highway Act (FAHA) [23 U.S.C. 109 and 23 U.S.C. 128].

    2. Air: Clean Air Act [42 U.S.C. 7401-7671(q)].

    3. Land: Section 4(f) of the Department of Transportation Act of 1966 [49 U.S.C. 303; 23 U.S.C. 138].

    4. Wildlife: Endangered Species Act [16 U.S.C. 1531-1544 and Section 1536].

    5. Historic and Cultural Resources: Section 106 of the National Historic Preservation Act of 1966, as amended [54 U.S.C. 306108].

    6. Social and Economic: Farmland Protection Policy Act [7 U.S.C. 4201-4209].

    (Catalog of Federal Domestic Assistance Program Number 20.205, Highway Planning and Construction. The regulations implementing Executive Order 12372 regarding intergovernmental consultation on Federal programs and activities apply to this program.)

    Start Authority

    Authority: 23 U.S.C. 139(l)(1).

    End Authority Start Signature

    Issued On: June 13, 2017.

    Edward Sundra,

    Director of Program Development

    End Signature End Supplemental Information

    [FR Doc. 2017-12812 Filed 6-22-17; 8:45 am]

    BILLING CODE 4910-RY-P

Document Information

Published:
06/23/2017
Department:
Federal Highway Administration
Entry Type:
Notice
Action:
Notice of limitation on claims for judicial review of actions by FHWA.
Document Number:
2017-12812
Dates:
By this notice, FHWA is advising the public of final agency actions subject to 23 U.S.C. 139(l)(1). A claim seeking judicial review of the Federal agency actions on the project will be barred unless the claim is filed on or before November 20, 2017. If the Federal law that authorizes judicial review of a claim provides a time period of less than 150 days for filing such claim, then that shorter time period still applies.
Pages:
28732-28733 (2 pages)
PDF File:
2017-12812.pdf
Supporting Documents:
» Final Federal Agency Actions: Proposed Highway in California
» Final Federal Agency Actions: Proposed Highway Projects in Texas
» Transfer and Sanction Programs
» Experimental Project To Evaluate Proposals for Delegation of Certain Program-Wide FHWA Responsibilities to States
» Environmental Impact Statements; Availability, etc.: Multiple Counties in Alabama; Rescission
» Federal Agency Actions: SH 205 From North of John King (Rockwall County Line) to SH 78 in Collin County, TX
» Federal Agency Actions: Interstate 95 in City of Fredericksburg and Counties of Spotsylvania, Stafford, Prince William, and Fairfax, VA
» Environmental Impact Statements; Availability, etc.: I-495 and I-270 Managed Lanes Study, Montgomery and Prince George's Counties, MD and Fairfax County, VA
» Federal Agency Actions: Proposed Highway in California
» Federal Agency Actions: California; Proposed Highway