2011-15857. Transcontinental Gas Pipe Line Company, LLC; Notice of Availability of the Environmental Assessment for the Proposed Mid-South Expansion Project  

  • Start Preamble

    The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the Mid-South Expansion Project proposed by Transcontinental Gas Pipe Line Company, LLC (Transco) in the above-referenced docket. Transco requests authorization to construct and operate five new pipeline loops,[1] construct one new compressor station, add compression at two existing compressor stations, and perform other modifications to five compressor stations. The MSEP would provide about 451 million standard cubic feet of natural gas per day to Transco's existing mainline system from the Clean Energy LNG import terminal currently under construction in Pascagoula, Mississippi, with existing capacity on Transco's Mobile Bay Lateral, down to existing Compressor Station 85. According to Transco, its project would expand delivery capacity on its existing pipeline system to growing markets in the east as far downstream as Rockingham County, North Carolina.

    The EA assesses the potential environmental effects of the construction and operation of the Mid-South Expansion Project in accordance with the requirements of the National Environmental Policy Act of 1969 (NEPA). The FERC staff concludes that approval of the proposed project, with appropriate mitigating measures, would not constitute a major Federal action significantly affecting the quality of the human environment.

    The proposed Mid-South Expansion Project includes the following facilities:

    • Five pipeline loops located in Coosa and Randolph Counties, Alabama, and Gaston, Rowan and Davidson Counties, North Carolina;
    • One new compressor station, Station 95, to be located in Dallas County, Alabama;
    • Additional new compression at two existing compressor stations:

    ○ Station 90 in Marengo County, Alabama; and

    ○ Station 125 in Walton County, Georgia;Start Printed Page 37110

    • Modifications at the following existing compressor stations:

    ○ Station 105 in Coosa County, Alabama;

    ○ Station 115 in Coweta County, Georgia;

    ○ Station 120 in Henry County, Georgia;

    ○ Station 140 in Spartanburg County, South Carolina; and

    ○ Station 145 in Cleveland County, North Carolina.

    The planned loops would be constructed with 42-inch-diameter steel pipe and would have a combined total length of about 22.6 miles.

    The EA has been placed in the public files of the FERC and is available for public viewing on the FERC's Web site at http://www.ferc.gov using the eLibrary link. A limited number of copies of the EA are available for distribution and public inspection at: Federal Energy Regulatory Commission, Public Reference Room, 888 First Street, NE., Room 2A, Washington, DC 20426, (202) 502-8371.

    Copies of the EA have been mailed to Federal, State, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American tribes; potentially affected landowners and other interested individuals and groups; newspapers and libraries in the project area; and parties to this proceeding.

    Any person wishing to comment on the EA may do so. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are properly recorded and considered prior to a Commission decision on the proposal, it is important that the FERC receives your comments in Washington, DC on or before July 20, 2011.

    For your convenience, there are three methods you can use to submit your comments to the Commission. In all instances, please reference the project docket number (CP11-18-000) with your submission. The Commission encourages electronic filing of comments and has dedicated eFiling expert staff available to assist you at (202) 502-8258 or efiling@ferc.gov.

    (1) You may file your comments electronically by using the eComment feature, which is located on the Commission's Web site at http://www.ferc.gov under the link to Documents and Filings. An eComment is an easy method for interested persons to submit brief, text-only comments on a project;

    (2) You may file your comments electronically by using the eFiling feature, which is located on the Commission's Web site at http://www.ferc.gov under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making. A comment on a particular project is considered a “Comment on a Filing”; or

    (3) You may file a paper copy of your comments at the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Room 1A, Washington, DC 20426.

    Although your comments will be considered by the Commission, simply filing comments will not serve to make the commenter a party to the proceeding. Any person seeking to become a party to the proceeding must file a motion to intervene pursuant to Rule 214 of the Commission's Rules of Practice and Procedures (18 CFR 385.214).[2] Only intervenors have the right to seek rehearing of the Commission's decision.

    Affected landowners and parties with environmental concerns may be granted intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which would not be adequately represented by any other parties. You do not need intervenor status to have your comments considered.

    Additional information about the project is available from the Commission's Office of External Affairs, at (866) 208-FERC or on the FERC Web site (http://www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on “General Search” and enter the docket number excluding the last three digits in the Docket Number field (i.e., CP11-18-000). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings.

    In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to http://www.ferc.gov/​esubscribenow.htm.

    Start Signature

    Dated: June 20, 2011.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.  A pipeline loop is constructed parallel to an existing pipeline to increase capacity.

    Back to Citation

    2.  Interventions may also be filed electronically via the Internet in lieu of paper. See the previous discussion on filing comments electronically.

    Back to Citation

    [FR Doc. 2011-15857 Filed 6-23-11; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Comments Received:
0 Comments
Published:
06/24/2011
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2011-15857
Pages:
37109-37110 (2 pages)
Docket Numbers:
Docket No. CP11-18-000
PDF File:
2011-15857.pdf