97-16582. Columbia Gas Transmission Corporation; Notice of Request Under Blanket Authorization
[Federal Register Volume 62, Number 122 (Wednesday, June 25, 1997)]
[Notices]
[Page 34240]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-16582]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP97-578-000]
Columbia Gas Transmission Corporation; Notice of Request Under
Blanket Authorization
June 19, 1997.
Take notice that on June 11, 1997, Columbia Gas Transmission
(Columbia), 1700 MacCorkle Avenue, S.E. Charleston, West Virginia
25314-1599, filed a request with the Commission in Docket No. CP97-578-
000, pursuant to Sections 157.205, and 157.216(b) of the Commission's
Regulations under the Natural Gas Act (NGA) for authorization to modify
an existing point of delivery to Baltimore Gas & Electric Company (BGE)
authorized in blanket certificate issued in Docket No. CP83-76-000, all
as more fully set forth in the request on file with the Commission and
open to public inspection.
Columbia proposes to modify an existing point of delivery by
replacing measurement, regulation and appurtenances to provide
increased capacity for interruptible transportation service. Columbia
states BGE would use the gas for industrial purposes as a result of
obtaining a government contract. Columbia further states that the
quantities to be provided will have no impact on Columbia's existing
design day and annual obligations to its customers as a result of the
modification to the existing point of delivery.
Columbia reports that the estimated cost to modify the existing
point of delivery would be approximately $392,700 and that BGE has
agreed to reimburse Columbia in full, plus an estimated $133,100 for
gross up for income taxes incurred by Columbia as a result of BGE's
contribution.
Any person or the Commission's staff may, within 45 days after the
Commission has issued this notice, file pursuant to Rule 214 of the
Commission's Procedural Rules (18 CFR 385.214) a motion to intervene or
notice of intervention and pursuant to Section 157.205 of the
Regulations under the NGA (18 CFR 157.205) a protest to the request. If
no protest is filed within the allowed time, the proposed activity
shall be deemed to be authorized effective the day after the time
allowed for filing a protest. If a protest is filed and not withdrawn
within 30 days after the time allowed for filing a protest, the instant
request shall be treated as an application for authorization pursuant
to Section 7 of the NGA.
Lois D. Cashell,
Secretary.
[FR Doc. 97-16582 Filed 6-24-97; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 06/25/1997
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 97-16582
- Pages:
- 34240-34240 (1 pages)
- Docket Numbers:
- Docket No. CP97-578-000
- PDF File:
-
97-16582.pdf