2013-15261. Vogtle Electric Generating Plant, Unit 4; Inspections, Tests, Analyses, and Acceptance Criteria  

  • Start Preamble

    AGENCY:

    Nuclear Regulatory Commission.

    ACTION:

    Determination of inspections, tests, analyses, and acceptance criteria completion.

    SUMMARY:

    The U.S. Nuclear Regulatory Commission (NRC) staff has determined that the inspections, tests, and analyses have been successfully completed, and that the specified acceptance criteria are met for Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) E.2.5.04.05.05.01, for the Vogtle Electric Generating Plant, Unit 4.

    ADDRESSES:

    Please refer to Docket ID NRC-2008-0252 when contacting the NRC about the availability of information regarding this document. You may access information related to this document, which the NRC possesses and is publicly available, using any of the following methods:

    • Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0252. Address questions about NRC dockets to Carol Gallagher; telephone: 301-492-3668; email: Carol.Gallagher@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
    • NRC's Agencywide Documents Access and Management System (ADAMS): You may access publicly available documents online in the NRC Library at http://www.nrc.gov/​reading-rm/​adams.html. To begin the search, select “ADAMS Public Documents” and then select “Begin Web-based ADAMS Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced in this document (if that document is available in ADAMS) is provided the first time that a document is referenced.
    • NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Brian Anderson, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-9967, email: Brian.Anderson@nrc.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Licensee Notification of Completion of ITAAC

    On May 7, 2013, Southern Nuclear Operating Company, Inc. (the licensee) submitted an ITAAC closure notification (ICN) under § 52.99(c)(1) of Title 10 of the Code of Federal Regulations (10 CFR) informing the NRC that the licensee has successfully performed the required inspections, tests, and analyses for ITAAC E.2.5.04.05.05.01, and that the specified acceptance criteria are met for Vogtle Electric Generating Plant, Unit 4 (ADAMS Accession No. ML13127A390). This ITAAC was approved as part of the issuance of the combined license, NPF-92, for this facility.

    NRC Staff Determination of Completion of ITAAC

    The NRC staff has determined that the inspections, tests, and analyses have been successfully completed, and that the specified acceptance criteria are met for Vogtle Electric Generating Plant, Unit 4, ITAAC E.2.5.04.05.05.01. This notice fulfills the staff's obligations under 10 CFR 52.99(e)(1) to publish a notice in the Federal Register of the NRC staff's determination of the successful completion of inspections, tests, and analyses.

    The documentation of the NRC staff's determination is in the ITAAC Closure Verification Evaluation Form (VEF), dated June 5, 2013 (ADAMS Accession No. ML13162A231). The VEF is a form that represents the NRC staff's structured process for reviewing ICNs. The ICN presents a narrative description of how the ITAAC was completed, and the NRC's ICN review process involves a determination on whether, among other things, (1) the ICN provides sufficient information, including a summary of the methodology used to perform the ITAAC, to demonstrate that the inspections, tests, and analyses have been successfully completed; (2) the ICN provides sufficient information to demonstrate that the acceptance criteria are met; and (3) any required inspections for the ITAAC have been completed and any ITAAC findings associated with the ITAAC have been closed.

    The NRC staff's determination of the successful completion of this ITAAC is based on information available at this time and is subject to the licensee's ability to maintain the condition that the acceptance criteria are met. If new information disputes the NRC staff's determination, this ITAAC will be reopened as necessary. The NRC staff's determination will be used to support a subsequent finding, pursuant to 10 CFR 52.103(g), at the end of construction that all acceptance criteria in the combined license are met. The ITAAC closure process is not finalized for this ITAAC until the NRC makes an affirmative finding under 10 CFR 52.103(g). Any future updates to the status of this Start Printed Page 38412ITAAC will be reflected on the NRC's Web site at http://www.nrc.gov/​reactors/​new-reactors/​oversight/​itaac.html.

    Start Signature

    Dated at Rockville, Maryland, this 19th day of June 2013.

    For the Nuclear Regulatory Commission.

    Brian Anderson,

    Senior Project Manager, Licensing Branch 4, Division of New Reactor Licensing, Office of New Reactors.

    End Signature End Supplemental Information

    [FR Doc. 2013-15261 Filed 6-25-13; 8:45 am]

    BILLING CODE 7590-01-P

Document Information

Comments Received:
0 Comments
Published:
06/26/2013
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Action:
Determination of inspections, tests, analyses, and acceptance criteria completion.
Document Number:
2013-15261
Pages:
38411-38412 (2 pages)
Docket Numbers:
Docket No. 052-00026, NRC-2008-0252
PDF File:
2013-15261.pdf
Supporting Documents:
» Southern Nuclear Operating Company Inc; Vogtle Electric Generating Plant Units 3 and 4
» Southern Nuclear Operating Company Inc; Vogtle Electric Generating Plant Units 3 and 4
» Southern Nuclear Operating Company, Inc.; Vogtle Electric Generating Plant, Units 3 and 4; Inspections, Tests, Analyses, and Acceptance Criteria
» Southern Nuclear Operating Company, Inc.; Vogtle Electric Generating Plant, Units 3 and 4; Main Control Room Emergency Habitability System Changes
» Southern Nuclear Operating Company, Inc.; Vogtle Electric Generating Plant, Units 3 and 4; PXS/ADS Line Resistance Changes
» Southern Nuclear Operating Company, Inc.; Vogtle Electric Generating Plant, Units 3 and 4; Pipe Rupture Hazard and Flooding Analysis
» Southern Nuclear Operating Company, Inc., Vogtle Electric Generating Station, Units 3 and 4; Addition of a Residual Heat Removal Suction Relief Valve for Low-Temperature Overpressure Protection; Exemption and Combined License Amendment; Issuance
» Southern Nuclear Operating Company, Inc., Vogtle Electric Generating Plant, Units 3 and 4; Clarification of Raceway and Raceway System Designations; Issuance of Exemption and Combined License Amendment
» Southern Nuclear Operating Company, Inc., Vogtle Electric Generating Plant, Units 3 and 4; Central Chilled Water System Optimization Changes; Issuance of Exemption and Combined License Amendment
» Southern Nuclear Operating Company, Inc. Vogtle Electric Generating Plant, Units 3 and 4, Inspections, Tests, Analyses, and Acceptance Criteria; Determination of Successful Completion of Inspections, Tests, and Analyses