94-15482. Yankee Atomic Electric Company (Yankee Nuclear Power Station); Exemption  

  • [Federal Register Volume 59, Number 122 (Monday, June 27, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-15482]
    
    
    [[Page Unknown]]
    
    [Federal Register: June 27, 1994]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-029]
    
     
    
    Yankee Atomic Electric Company (Yankee Nuclear Power Station); 
    Exemption
    
    I
    
        The Yankee Atomic Electric Company (YAEC or the licensee), is the 
    holder of Facility Operating License (Possession Only) No. DPR-3 which 
    authorizes possession and maintenance of the Yankee Nuclear Power 
    Station (YNPS or plant). The license provides, among other things, that 
    the licensee is subject to all rules, regulations, and orders of the 
    Commission now or hereafter in effect.
        The facility is a permanently shutdown pressurized water reactor, 
    currently in the process of being prepared for decommissioning, and is 
    located at the licensee site in Franklin County, Massachusetts.
    
    II
    
        The licensee, by letter dated February 27,1992, supplemented by 
    letter dated January 19,1 993, informed the NRC and YAEC had 
    permanently ceased power operations, removed the fuel from the reactor 
    to the fuel pool, and had begun to develop detailed plans to 
    decommission the facility. The reactor was actually shut down on 
    October 1, 1991; thus, the fuel has now undergone over two years and 
    seven months of decay. The NRC in a license amendment dated August 5, 
    1992, modified License No. DPR-3 to possession only status. The license 
    is conditioned so that YAEC is not authorized to operate the reactor 
    and fuel may not be placed in the reactor vessel, thus formalizing the 
    YAEC commitment to permanently cease power operations.
        By letter dated September 28, 1992, the licensee requested an 
    amendment to the Yankee Atomic Electric Company (YAEC) Indemnity 
    Agreement No. B-17 which would reduce the primary level of financial 
    protection maintained at the plant to $4.5 million from the current 
    level of $200 million and provide relief from participation in the 
    industry retrospective rating plan (secondary level). This letter was 
    supplemented by the licensee letter to the Commission dated January 19, 
    1993.
    
    III
    
        The justification presented by the licensee for amendment of its 
    indemnity agreement is that because of the permanently shutdown status 
    of the plant, defueled condition of the reactor, and possession only 
    license amendment (which prohibits operation), 10 CFR 140.11 no longer 
    applies to YAEC. Given these considerations, the licensee contends that 
    10 CFR 140.12, which describes financial protection for reactors not 
    covered by 10 CFR 140.11, applies to YAEC. The licensee also addressed 
    past NRC actions with respect to relief granted to the consolidated 
    Edison facility, Indian Point Unit 1. Consequently, the licensee has 
    requested that its indemnity agreement be amended such that the 
    licensee would no longer be required to participate in the secondary 
    protection program, and that its primary financial protection be 
    reduced to the minimum required under 10 CFR 140.12, which is $4.5 
    million.
        The staff has determined on its own initiative that an exemption 
    from the requirements of 10 CFR 140.11 is required in order to 
    implement an amendment to the licensee indemnity agreement. The bases 
    for providing this exemption to 10 CFR 140.11(a)(4) are provided 
    herein.
        The NRC staff independently evaluated the legal and technical 
    issues associated with the application of the Price-Anderson Act to 
    permanently shut down reactors in SECY-93-127, ``Financial Protection 
    Required of Licensees of Large Nuclear Power Plants During 
    Decommissioning,'' dated May 10, 1993. In this evaluation, the staff 
    concluded that the Commission has discretionary authority to respond to 
    licensee requests for a reduction in the level of primary financial 
    protection and withdrawal from participation in the industry 
    retrospective rating plan. Depending on the plant-specific 
    configuration and the time since permanent shutdown, the staff also 
    concluded that potential hazards may exist at permanently shutdown 
    reactors for which financial protection is warranted. The staff 
    concluded that accidents and hazards insured against under the Price-
    Anderson Act go beyond design basis accidents and beyond those 
    considered ``credible'' as that term is used in 10 CFR Part 100 and 
    cases interpreting the application of that regulation. The Commission 
    issued a SRM in response to SECY-93-127 on July 13, 1993. In this SRM, 
    the Commission approved a staff recommendation to permit a reduction of 
    primary level coverage to $100 million through the exemption process 
    after an appropriate spent fuel cooling period and after allowing 
    withdrawal from participation in the secondary level of financial 
    protection.
        In the exercise of its discretionary authority, the Commission may, 
    as long as a potential hazard exists at a permanently shutdown reactor, 
    require the full amount of primary financial protection and full 
    participation in the industry retrospective rating plan. At such time 
    that the hazard is determined to no longer exist or to be significantly 
    reduced, the Commission may reduce the amount of primary financial 
    protection and permit the licensee to withdraw from participation in 
    the industry retrospective rating plan.
        Since the legislative history of the Price-Anderson Act does not 
    explicitly consider the potential hazards that might exist after 
    termination of operation, the staff generically evaluated the offsite 
    consequences associated with normal and abnormal operations, design 
    basis accidents, and beyond design basis accidents for reactors that 
    have been permanently defueled and shut down. The staff concluded that 
    where an appropriate cooling time has elapsed since plant shutdown, 
    aside from the handling, storage, and transportation of spent fuel and 
    radioactive materials, no reasonably conceivable potential accident 
    exists that could cause significant offsite damage.
        As summarized in SECY-93-127, a severe transportation accident 
    could potentially result in local contamination requiring cleanup and 
    offsite liabilities resulting from traffic disruption and consequential 
    damages. This type of accident would warrant maintaining some level of 
    liability insurance. The liabilities an indemnification requirements 
    associated with the transfer of spent fuel from the licensee to the 
    Department of Energy will be evaluated on a case-by-case basis at a 
    future time when spent fuel is shipped to a repository.
        As further set forth in SECY-93-127, the most significant accident 
    sequence for a permanently defueled and shutdown reactor involves the 
    complete loss of water from a light water reactor spent fuel pool. This 
    beyond-design-basis accident sequence could result in a zirconium fuel 
    cladding fire that could propagate through the spent fuel storage pool 
    and result in significant offsite consequences. The potential 
    consequences of such an accident could involve billions of dollars. 
    Although such an accident is beyond the design bases, it may be 
    considered ``reasonably conceivable'' and could warrant requiring 
    substantial financial protection. Such an accident is possible during 
    the first year after reactor shutdown for a low density spent fuel 
    storage configuration and during the first two or three years after 
    shutdown for spent fuel stored in certain high density configurations.
        Accident scenarios involving blockage of coolant channels in 
    conjunction with loss of spent fuel pool water could hypothetically 
    extend the time within which a zirconium fuel cladding fire could 
    occur. However, in addition to being less likely than loss of water, 
    air flow to react with the zirconium and to disperse fission products 
    would likely be inhibited by such blockage. The staff believes that 
    this sequence approaches the strictly hypothetical.
        Once the requisite cooling period after reactor shutdown has 
    elapsed, the zirconium fuel cladding fire sequence after a postulated 
    loss of spent fuel pool water is no longer a concern since the fuel 
    would air cool sufficiently to avoid zirconium fuel cladding 
    combustion. Possible accident scenarios, after these cooling period 
    have elapsed, have greatly reduced consequences but could still result 
    in small releases or precautionary evacuations which could result in 
    offsite liability.
        With respect to the Yankee Nuclear Power Station plant-specific 
    evaluation, the NRC staff independently evaluated the legal and 
    technical justifications for this exemption. In particular, the NRC 
    evaluated the current Yankee status, that is, the plant is permanently 
    shut down and defueled, the license has been amended to authorize 
    ``possession only,'' the possession only license amendment prohibits 
    fuel movement from the spent fuel pool into the reactor building, and 
    the fuel is stored in a low density configuration. The staff concludes, 
    after evaluation of the remaining spectrum of accidents and considering 
    that the stored fuel has decayed for over two years and seven months 
    and is stored in a low density configuration, that any such accident 
    would result in greatly reduced offsite consequences. Thus, the staff 
    further concludes that the YNPS meets the criterion established in 
    SECY-93-127 for relief from the full financial protection requirements.
        Although the licensee presented legal views and opinions regarding 
    the applicability of 10 CFR 140.12 versus 10 CFR 140.11(a)(4), the 
    staff did not concur with those legal views and opinions and concludes 
    that the licensee has not demonstrated the applicability of 10 CFR 
    140.12 to the YNPS. The staff has also concluded that the Three Mile 
    Island Unit 2 (TMI-2) claims settlement experience (an accident which 
    did not result in a significant release of radioactivity) provides a 
    reasonable basis for establishing the appropriate level of primary 
    insurance coverage. Because TMI-2 claims have reached $60 million and a 
    large number of TMI-2 claims are still unsettled, the staff concluded 
    that a level of $100 million for primary financial protection coverage 
    is warranted. This level of primary insurance coverage is consistent 
    with the SRM dated July 13, 1993, based on SECY-93-127, for relief from 
    financial protection requirements.
    
    IV
    
        The staff, based on its independent evaluation, consistent with the 
    Commission July 13, 1993 SRM based on SECY-93-127, ``Financial 
    Protection Required of Licensees of Large Nuclear Power Plants During 
    Decommissioning,'' has concluded that sufficient bases exist for 
    approval of a partial exemption from the financial protection 
    requirements for the YNPS. The staff has also concluded that granting 
    the proposed exemption does not increase the probability or 
    consequences of any accidents or reduce the margin of safety at the 
    facility.
    
    V
    
        Based on the discussion presented in Sections III and IV above, the 
    Commission has determined, that pursuant to 10 CFR 140.8, this 
    exemption is authorized by law and is otherwise in the public interest. 
    Therefore, the Commission grants an exemption from the requirements of 
    10 CFR 140.11(a)(4) to the extent that primary financial protection in 
    the amount of $100 million shall be maintained, and an exemption from 
    participation in the industry retrospective rating plan (secondary 
    level financial protection) is granted for the YNPS.
        Pursuant to 10 CFR 51.32, the Commission has determined that the 
    granting of this exemption will not have a significant effect on the 
    quality of the human environment (59 FR 31651).
        This exemption is effective immediately.
    
        Dated at Rockville, Maryland, this 20th day of June 1994.
    
        For the Nuclear Regulatory Commission.
    Brian K. Grimes,
    Director, Division of Operating Reactor Support, Office of Nuclear 
    Reactor Regulation.
    [FR Doc. 94-15482 Filed 6-24-94; 8:45 am]
    BILLING CODE 7590-01-M
    
    
    

Document Information

Published:
06/27/1994
Department:
Nuclear Regulatory Commission
Entry Type:
Uncategorized Document
Document Number:
94-15482
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: June 27, 1994, Docket No. 50-029