94-15510. Regulatory Review: Hazardous Liquid and Carbon Dioxide Pipeline Safety Standards  

  • [Federal Register Volume 59, Number 123 (Tuesday, June 28, 1994)]
    [Unknown Section]
    [Page ]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-15510]
    
    
    [Federal Register: June 28, 1994]
    
    
    _______________________________________________________________________
    
    Part VII
    
    
    
    
    
    Department of Transportation
    
    
    
    
    
    _______________________________________________________________________
    
    
    
    Research and Special Programs Administration
    
    
    
    _______________________________________________________________________
    
    
    
    49 CFR Part 195
    
    
    
    Regulatory Review: Hazardous Liquid and Carbon Dioxide Pipeline Safety 
    Standards; Final Rule
    DEPARTMENT OF TRANSPORTATION
    
    Research and Special Programs Administration
    
    49 CFR Part 195
    
    [Docket PS-127; Amdt. 195-52]
    RIN 2137-AC27
    
    
    Regulatory Review: Hazardous Liquid and Carbon Dioxide Pipeline 
    Safety Standards
    
    AGENCY: Research and Special Programs Administration (RSPA), DOT.
    
    ACTION: Final rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: This rulemaking amends miscellaneous hazardous liquid and 
    carbon dioxide pipeline safety standards to provide clarity, eliminate 
    unnecessary or overly burdensome requirements, and foster economic 
    growth. The changes result from the regulatory review RSPA carried out 
    in response to the President's directive of January 28, 1992, on 
    reducing the burden of government regulation. The changes reduce costs 
    in the liquid pipeline industry without compromising safety.
    
    EFFECTIVE DATE: This regulation is effective July 28, 1994. The 
    incorporation by reference of certain publications listed in the 
    regulations is approved by the Director of the Federal Register as of 
    July 28, 1994.
    
    FOR FURTHER INFORMATION CONTACT: J. Willock, (202) 366-2392, regarding 
    the subject matter of this final rulemaking, or the Dockets Unit, (202) 
    366-5046, regarding copies of this final rulemaking or other material 
    that is referenced herein.
    
    SUPPLEMENTARY INFORMATION:
    
    Background
    
        In a January 28, 1992, memorandum, the President wrote to 
    Department and agency heads about the need to reduce the burden imposed 
    by government regulation. The President was concerned that agencies 
    were not doing enough to review and revise existing regulations to 
    eliminate unnecessary and overly burdensome requirements. The President 
    recognized that regulations that do not keep pace with new technologies 
    and innovations impose needless costs and impede economic growth.
        In response to the President's memorandum, DOT published a notice 
    requesting public comment on the Department's regulatory programs (57 
    FR 4745; Feb. 7, 1992). Commenters were asked to identify regulations 
    that substantially impede economic growth, may no longer be necessary, 
    are unnecessarily burdensome, impose needless costs or red tape, or 
    overlap or conflict with other DOT or federal regulations. The deadline 
    for submitting comments was March 2, 1992.
        RSPA received comments from six organizations about the pipeline 
    safety regulations in part 195. Comments were from three regulated 
    pipeline companies, a pipeline trade association, a state pipeline 
    safety agency, and a federal agency. RSPA considered all comments in 
    its review of the regulations, and these comments are available in the 
    docket. Some comments will be considered in future rulemakings. 
    Additionally, RSPA has published a separate rulemaking ``Update of 
    Standards Incorporated by Reference'' (58 FR 14519; March 18, 1993) 
    which updates the editions of the industry standards that are 
    incorporated in part 195.
        On November 27, 1992, RSPA published a Notice of Proposed 
    Rulemaking, NPRM, (57 FR 56304) proposing 18 changes to the regulations 
    based on the comments received from the public and asked for further 
    comments regarding the proposed changes. RSPA received comments from 21 
    organizations: 15 pipeline companies, 3 pipeline trade associations, 2 
    environmental organizations, and 1 county government. RSPA considered 
    all comments in preparation of the final rulemaking and the comments 
    are available in the Docket.
    
    Advisory Committee
    
        The Technical Hazardous Liquid Pipeline Safety Standards Committee 
    (THLPSSC), consisting of 15 members, was established by statute to 
    consider the feasibility, reasonableness, and practicability of 
    proposed pipeline regulations. RSPA implemented the committee balloting 
    process by mail. After initial balloting, the process allowed each 
    member to review the ballots, including comments, of all other members, 
    and to change his or her vote or initial comment if desired. Although 
    some THLPSSC members did not vote on every proposed change, a tally of 
    the second ballots showed that a large majority of THLPSSC members 
    found all the proposed changes technically feasible, reasonable, and 
    practicable. Nonetheless, in developing the final regulations, RSPA 
    considered all final THLPSSC votes and comments, including minority 
    positions. The following discussion explains how RSPA treated THLPSSC 
    positions and public comments on the proposed amendments in developing 
    the final rule.
    
    Changes to Part 195 Safety Standards
    
        The following discussion explains the changes to various standards 
    in part 195:
    
    Section 195.1  Applicability.
    
        Offshore production. Part 195 does not apply to pipelines used in 
    offshore production, whether on the Outer Continental Shelf or in state 
    offshore waters. However, this exception is clearly stated in part 195 
    only for production on the Outer Continental Shelf (Sec. 195.1(b)(5)). 
    To clarify that all offshore pipelines used in production are outside 
    part 195, RSPA proposed to delete from Sec. 195.1(b)(5) the phrase ``on 
    the Outer Continental Shelf''.
        The 10 THLPSSC members who voted on the proposed amendment to 
    Sec. 195.1(b)(5) all approved the amendment.
        In addition, RSPA received comments from three operators and two 
    pipeline-related associations in support of the amendment and no 
    adverse comments. Therefore, Sec. 195.1(b)(5) is amended as proposed in 
    the NPRM.
        We also requested comments on whether there is a gap in the 
    regulation of production lines in state offshore waters. Only one 
    commenter responded. This commenter opined that existing state and 
    federal programs adequately regulate production lines in state waters. 
    In Louisiana, the Departments of Natural Resources and Environmental 
    Quality were said to have comprehensive regulations on facility 
    installation, operation, integrity, and removal, and sufficient 
    authority to address any ``gap'' that is identified. Since the other 
    states with production lines in state waters have similar regulations, 
    RSPA does not believe there is a gap in the regulation of production 
    lines in state waters.
        In-plant piping. Part 195 does not apply to pipeline transportation 
    through onshore production, refining, or manufacturing facilities, or 
    storage or in-plant piping systems associated with such facilities 
    (Sec. 195.1(b)(6)). Because the physical distinction between a 
    regulated pipeline serving a plant and unregulated in-plant piping is 
    unclear, RSPA proposed to add a definition of ``in-plant piping 
    system'' to Sec. 195.2. The definition proposed was: ``In-plant piping 
    system means piping that is located on the grounds of a plant and used 
    to transfer hazardous liquid or carbon dioxide between plant facilities 
    or between plant facilities and a pipeline, not including any device 
    and associated piping that are necessary to control pressure in the 
    pipeline.'' The NPRM explained that we would consider in-plant piping 
    to extend to the plant boundary in the absence of a necessary pressure 
    control device on plant grounds.
        All ten THLPSSC members who voted on this proposal supported it. 
    However, four members believed that because the NPRM primarily 
    concerned pipeline transportation rather than production, refining, or 
    manufacturing plants, it did not give plant owners adequate notice that 
    the proposed definition could affect plant piping. These members wanted 
    RSPA to publish a separate NPRM on the subject of in-plant piping.
        RSPA does not agree that another NPRM is needed. The subject of in-
    plant piping and the associated issues were clearly discussed in the 
    published NPRM. Also, all interested persons, including plant owners as 
    well as pipeline operators, were given an opportunity to comment on the 
    subject of in-plant piping.
        RSPA received comments on the proposed definition from seven 
    operators, two pipeline-related associations, and one state agency. Two 
    operators and one association fully supported the proposal.
        One operator and a pipeline-related association thought plant 
    owners were not adequately notified of the proposed rule, and that RSPA 
    should treat the subject in a separate NPRM. Our position on this issue 
    is given supra in response to a similar criticism by four THLPSSC 
    members.
        Another operator was concerned that the proposed definition would 
    cause operator-owned components, such as pipe, meters, instruments, and 
    manifolds, that are located on plant grounds downstream from the 
    operator's pressure control device to fall outside part 195. The 
    operator was worried that other agencies would regulate these 
    components as non-transportation related facilities. We are not 
    persuaded, however, that the potential for such regulation is 
    sufficient reason to exclude the components from the definition of in-
    plant piping system. The aim of the proposed definition was to 
    distinguish unregulated piping, not to limit the jurisdiction of other 
    government agencies.
        In contrast, an operator of gathering and processing facilities was 
    concerned that part 195 would apply to plant piping that lies between 
    any necessary pressure control device and the connection to a pipeline. 
    This commenter apparently did not realize that such piping is subject 
    to part 195. RSPA has applied part 195 to such piping because it is 
    subject to pressure which is controlled by a device operators must have 
    to meet Sec. 195.406(b). However, this application has had little 
    effect on plant owners, because we hold the pipeline operator, not the 
    plant owner, responsible for compliance.
        An operator commenting on the plant device exclusion in the 
    proposed definition advised us to change ``control pressure'' to 
    ``prevent overpressure.'' This commenter said the change would avoid 
    making pipeline operators responsible under part 195 for nonessential 
    pressure control devices. We agree the suggested rewording would better 
    convey the intent of the proposal. But, in the final definition, we 
    have changed ``control pressure in the pipeline'' to ``control pressure 
    in the pipeline under Sec. 195.406(b)'' to convey the intent even more 
    precisely.
        The state agency commented that if piping on plant grounds does not 
    include a device necessary to control pipeline pressure, the 
    jurisdiction of part 195 over the pipeline should not end at the plant 
    boundary. Instead, the state agency recommended ending jurisdiction at 
    a component inside the plant, such as a flange, where the pipeline can 
    be isolated for purposes of testing. Although operators may use such 
    components, part 195 does not require that they be on the pipeline. 
    Also, we believe the plant boundary is a more convenient demarcation of 
    in-plant piping than an unspecific inside-the-plant component. Thus, 
    the state agency's comment is not incorporated in the final definition.
        The state agency, an operator, and a pipeline-related association 
    were concerned that because segments of transfer piping located off 
    plant grounds were not included in the proposed definition, a large 
    number of short pipelines would come under part 195. RSPA recognizes 
    that production, refining, or manufacturing plants often install 
    transfer piping off plant grounds. A plant may use this piping to 
    transfer hazardous liquids between its different facilities located on 
    the same grounds; between its different facilities located on separate 
    grounds (usually separated by a roadway, railway, waterway, or 
    industrial area); between its facilities and a transportation system, 
    such as a railroad or pipeline; or between its facilities and the 
    facilities of another plant or industrial consumer. The three 
    commenters thought the off-grounds segments should qualify as in-plant 
    piping if they connect facilities of the same plant. The association 
    also wanted to include under the definition off-grounds segments that 
    connect facilities of different plants. In addition, the operator and 
    association argued that the off-grounds segments pose minimum risk to 
    public safety and the environment, because the segments generally are 
    located in industrial areas, roadways, or railways. The association 
    further argued that a plant has the same operational control, including 
    response capability, over the off-grounds segments as it does over 
    piping on plant grounds.
        In response to these comments, we note that Sec. 195.1(b)(6) echoes 
    section 201(3) of the Hazardous Liquid Pipeline Safety Act of 1979 
    (HLPSA), (49 U.S.C. app. 2001(3)), which excludes certain ``in-plant 
    piping systems'' from regulation under the HLPSA. Since neither the 
    HLPSA nor its legislative history explain ``in-plant piping,'' we adopt 
    an ordinary, reasonable understanding of the term. Therefore, we do not 
    accept the interpretation that the term includes piping that crosses 
    the property of others outside plant grounds. However, many plants are 
    separated by a public thoroughfare, and plant transfer piping crosses 
    the thoroughfare. A single public thoroughfare would include any road, 
    from a country lane to an interstate highway, but it does not include a 
    railroad. Because transfer piping that crosses such thoroughfares is 
    comparable in most respects to other in-plant piping, RSPA considers 
    the in-plant piping exception to include the thoroughfare crossings. 
    The thoroughfare exception does not apply to inter-facility lines or 
    delivery lines, because these lines are distinct from in-plant piping. 
    We did not intend the proposed definition of ``in-plant piping 
    systems'' to expand our present interpretation of the term. So the 
    final definition does not incorporate any of the comments concerning 
    piping located off plant grounds other than for thoroughfare crossings.
        However, the proposed definition's first use of the term 
    ``pipeline'' is changed to ``pipeline or other mode of 
    transportation.'' This change is needed to include, within the 
    definition, piping on plant grounds that transfer hazardous liquid or 
    carbon dioxide between plant facilities and modes of transportation 
    other than pipeline.
        Terminal facilities. Part 195 does not apply to the transportation 
    of hazardous liquid or carbon dioxide by vessel, aircraft, tank truck, 
    tank car, or other vehicle, or by terminal facilities used exclusively 
    to transfer hazardous liquid or carbon dioxide between such modes of 
    transportation (Sec. 195.1(b)(7)). RSPA proposed to amend 
    Sec. 195.1(b)(7) to clarify that terminal facilities located off 
    terminal grounds are subject to part 195, and to distinguish 
    unregulated terminal facilities from a regulated pipeline entering or 
    leaving the terminal. As with the proposed in-plant piping definition, 
    any device and associated piping on terminal grounds necessary to 
    control pressure in a regulated pipeline would not be excepted from 
    part 195.
        The THLPSSC voted to approve this proposal, but four members 
    believed the NPRM did not give terminal owners adequate notice that the 
    proposed amendment could affect their piping. These members wanted RSPA 
    to publish a separate NPRM on the subject. For the reasons stated supra 
    in response to a similar argument by these THLPSSC members concerning 
    in-plant piping, RSPA does not agree that another NPRM is needed.
        Five operators and two pipeline-related associations commented on 
    the proposed amendment to Sec. 195.1(b)(7). Of these commenters, two 
    operators and one association agreed with the proposal.
        A few commenters expressed the same concerns about the proposed 
    amendment to Sec. 195.1(b)(7) as they did about the proposed in-plant 
    piping definition. These concerns were that the NPRM did not adequately 
    notify plant (terminal) owners of the proposed rule, and that some 
    operator-owned components located on plant (terminal) grounds would 
    fall outside part 195. Our response to these concerns is the same as 
    stated supra regarding in-plant piping.
        In regard to transfer lines located outside terminal grounds at 
    ports, an operator and a pipeline-related association pointed out that 
    the U.S. Coast Guard regulates transfers between terminal storage and 
    dock facilities. These commenters suggested that RSPA and Coast Guard 
    develop a memorandum of understanding to limit Coast Guard's 
    regulations to dock facilities.
        We recognize that Coast Guard and RSPA jurisdictions overlap in 
    port areas, but the two agencies have different responsibilities. Also, 
    the overlap does not automatically result in regulatory conflicts, and 
    the commenters did not mention any. Nonetheless, though we have not 
    changed the final rule as a result of this comment, in enforcing part 
    195 at port areas, RSPA will act appropriately to resolve any 
    unnecessary regulatory burdens.
        Carbon dioxide injection system. Section 195.1(b)(8) provides that 
    part 195 does not apply to ``[t]ransportation of carbon dioxide 
    downstream from a point in the vicinity of the well site at which 
    carbon dioxide is delivered to a production facility.'' RSPA proposed 
    to amend this section to clarify that the exception covers pipelines 
    used in the injection of carbon dioxide for oil recovery operations.
        The THLPSSC approved the proposed amendment (10 voted in favor and 
    5 did not vote), and we received no adverse comments from the public. 
    The proposed amendment to Sec. 195.1(b)(8) is, therefore, adopted as 
    final.
    
    Section 195.2  Definitions.
    
        The proposed revision of the definition of ``Secretary'' is not 
    adopted in this rulemaking. Instead, it is being handled in an omnibus 
    rulemaking covering all regulations involving pipeline safety.
        The definition of ``In-plant piping system'' is discussed above in 
    Sec. 195.1 Applicability.
        Two commenters objected to the proposed definition for petroleum 
    products because of its use of the terms ``flammable'', ``toxic'', and 
    ``corrosive'' which are not defined under part 195. The commenters 
    stated that absent specific definitions for these terms, their 
    applicability could be unclear.
        RSPA agrees with the comments about the lack of clarity in the 
    proposed definition for petroleum products. So, the final rule for this 
    section includes new definitions for ``flammable'', ``toxic'', and 
    ``corrosive'' that come from the definitions contained in 49 CFR part 
    173 for Transportation and Packaging of Hazardous Materials for the 
    terms ``flammable liquid'', ``poisonous material'', and ``corrosive 
    material'', respectively. RSPA has adopted the definition of 
    ``poisonous material'' for ``toxic'' because it considers the terms 
    synonymous.
    
    Sections 195.2, 195.106, 195.112, 195.212 and 195.413  (Nominal Outside 
    Diameter of the Pipe in Inches)
    
        RSPA proposed to standardize the dimensioning of pipe size 
    throughout part 195 (Changes are made to Secs. 195.2, 195.106(b), 
    195.106(c), 195.112(c), 195.212(b)(3)(ii) and 195.413(a)). All 10 
    THLPSSC members who voted were in favor of the proposal and no 
    commenter objected thereto. Accordingly, the proposed amendment is 
    adopted as final.
    
    Section 195.3  Matter incorporated by reference.
    
        Section 195.3 sets out the general requirements for the 
    incorporation in the regulations of industry standards for the design, 
    construction and operation of hazardous liquid and carbon dioxide 
    pipelines. Paragraph 195.3(a) states that incorporation of a document 
    by reference has the same force as if the document were copied in the 
    regulations. Some operators have misinterpreted this section to mean 
    that they must comply with all of the terms contained in a referenced 
    document. Accordingly, RSPA hereby revises Sec. 195.3(a) to clarify 
    that an entire document is not incorporated when the document is 
    incorporated by reference; rather, only those portions specifically 
    referenced in the regulations are incorporated.
        The rule is being revised to conform to a recent update of 
    references in another rulemaking (Update of Standards Incorporated by 
    Reference (58 FR 14519; March 18, 1993)). Also, references to ASME/ANSI 
    Codes B31.8 and B31.G are being added. The 10 THLPSSC members who voted 
    and 7 commenters favored the revision.
    
    Section 195.5  Conversion to service subject to this part.
    
        Section 195.5 regulates the conversion of steel pipelines to 
    hazardous liquid or carbon dioxide service that is subject to part 195. 
    Under Sec. 195.5(a)(4), a converted pipeline must be hydrostatically 
    tested to substantiate the maximum operating pressure (MOP) permitted 
    by Sec. 195.406.\1\
    ---------------------------------------------------------------------------
    
        \1\Section 195.5(a)(4) actually uses the term ``maximum 
    allowable operating pressure,'' but for consistency with 
    Sec. 195.406, this term is changed below to MOP by removing the word 
    ``allowable.''
    ---------------------------------------------------------------------------
    
        To substantiate the MOP of a converted pipeline, an operator must 
    know the pipe design pressure (see current Sec. 195.406(a)(1)). 
    Consequently, if pipe design pressure is unknown, a steel pipeline may 
    not be converted under Sec. 195.5. Although the design pressure of 
    components is an MOP factor under Sec. 195.406(a)(2), pipeline 
    components are normally designed to be as strong or stronger than 
    attached pipe. Thus, pipe design is the critical factor in 
    substantiating MOP under Sec. 195.5(a)(4), and lack of knowledge of 
    component design pressure is not a significant safety concern.
        RSPA proposed to amend Sec. 195.5 to permit conversion using an 
    approach found in section 845.214 and Appendix N of ASME B31.8 for gas 
    pipelines whose design pressure is unknown. Under this proposal, 
    operators would pressure test the pipeline under Appendix N until pipe 
    yield occurs. Instead of design pressure, this yield test pressure 
    would be used to compute MOP by applying certain reduction factors to 
    80 percent of the first pressure that produces pipe yield.
        All THLPSSC members who voted on the proposed amendment to 
    Sec. 195.5 supported it in concept. However, two members thought the 
    wording of Appendix N should be copied directly into part 195 to avoid 
    referencing a gas pipeline code in liquid pipeline regulations. We 
    believe the principles of Appendix N apply equally to gas and liquid 
    pipelines. And since the B31.8 Code is widely used, operators of 
    hazardous liquid or carbon dioxide pipelines will not find it difficult 
    to obtain and apply Appendix N.
        RSPA received five comments on the proposed amendment to 
    Sec. 195.5. Two operators and a pipeline-related association agreed 
    with the proposed amendment.
        One operator suggested that if pipelines operating at less than 20 
    percent of specified minimum yield strength (SMYS) are subject to 
    Sec. 195.5, RSPA should allow operators up to 10 years to meet the 
    testing requirements. At present, none of the standards in part 195, 
    including Sec. 195.5, applies to pipelines operating at less than 20 
    percent of SMYS (see Sec. 195.1(b)(3)). However, this commenter may 
    have had in mind Sec. 206 of the Pipeline Safety Act of 1992 (Pub. L. 
    102-508), which provides that exceptions to regulations under the 
    Hazardous Liquid Pipeline Safety Act of 1979 (49 U.S.C. app. 2001 et 
    seq.), such as part 195, may not be based solely on low internal 
    stress. Because of this statutory mandate, RSPA has proposed to apply 
    part 195 to certain low-stress hazardous liquid pipelines (Docket PS-
    117; 58 FR 12213; March 3, 1993). Still, that proposal would not 
    require any existing low-stress hazardous liquid pipeline to be tested 
    under Sec. 195.5, because such pipelines would not be converted 
    pipelines. Of course, if part 195 becomes applicable to low stress 
    pipelines, any pipeline converted to low stress hazardous liquid 
    service subject to part 195 would have to be tested under Sec. 195.5. 
    But, since testing is the backbone of the conversion process, RSPA does 
    not believe Sec. 195.5 should be amended to extend the time for testing 
    to 10 years.
        A state agency was concerned that if test pressure must be measured 
    at the high elevation point of test segments, the test could stress the 
    low point of the segment beyond yield. However, the Appendix N test 
    method should not result in overstress at the low elevation, because 
    the method does not require increases in test pressure after the first 
    yield occurs in the test segment.
        In a separate rulemaking proceeding (Docket No. PS-124; 57 FR 
    39572; August 31, 1992), RSPA proposed to allow the use of the Appendix 
    N method in converting pipelines to gas service under 49 CFR 192.14. 
    This gas pipeline conversion standard is similar to Sec. 195.5. 
    Comments to that notice argued that pressure testing to yield is 
    unnecessary to qualify certain pipelines that operate at low stress 
    (generally pipelines 12\3/4\ inches or less in nominal outside diameter 
    operating at pressures of 200 psig or less). RSPA believes these 
    comments are also relevant to hazardous liquid pipelines. All other 
    factors being equal, hazardous liquid pipelines operating at low 
    internal stress present less risk of failure from time-dependent 
    defects than higher stress hazardous liquid pipelines. Because of the 
    lower risk, RSPA has modified the final rule to provide that pipelines 
    12\3/4\ inches or less in nominal outside diameter to be operated at a 
    pressure of 200 psig or less may be converted without testing to yield. 
    The MOP of such pipelines may be determined under Sec. 195.406 by using 
    200 psig as pipe design pressure.
        The proposed rule has been redrafted to improve clarity, to better 
    relate conversion to design pressure and MOP under Sec. 195.406, and to 
    include the changes discussed supra. In the final rule, the proposed 
    amendment to Sec. 195.5(a)(1) is revised and published as an amendment 
    to Sec. 195.406(a)(1). This latter section deals specifically with pipe 
    design pressure and MOP. As set forth infra, revised Sec. 195.406(a)(1) 
    provides that when pipe design pressure is unknown for steel pipelines 
    being converted, a reduced value of first yield hydrostatic test 
    pressure may be used as design pressure to compute MOP. If the pipeline 
    to be converted is 12\3/4\ inches or less in nominal outside diameter 
    and is not yield tested, 200 psig may be used as design pressure.
    
    Section 195.8  Transportation of hazardous liquid or carbon dioxide in 
    pipelines constructed with other than steel pipe.
    
        The proposal to replace the word ``he'' with ``the Secretary'' to 
    remove any implication of gender is not adopted in this rulemaking. 
    Instead, this proposal will be handled in an omnibus rulemaking to make 
    minor clarifications and error corrections covering all the pipeline 
    safety regulations.
    
    Section 195.50  Reporting accidents and Sec. 195.52 Telephonic notice 
    of certain accidents.
    
        Sections 195.50(f) and 195.52(a)(3) require operators to prepare 
    reports and give telephonic notice of accidents, respectively, when the 
    estimated property damage due to an accident exceeds $5,000. RSPA 
    discovered from its regulatory review and previous enforcement cases 
    that a significant amount of confusion exists among pipeline operators 
    as to which cost estimates must be included in calculating the 
    ``estimated property damage to the property of the operator or others * 
    * *'' Frequently, when reporting accidents, pipeline operators fail to 
    include as ``property damage'' the fair market value of the product 
    released or those costs associated with clean-up and recovery efforts. 
    RSPA believes these costs should be included when reporting accidents.
        Because the $5,000 reporting requirement requires the reporting of 
    minor accidents, RSPA proposed amending Secs. 195.50(f) and 
    195.52(a)(3) to increase the reporting threshold to $50,000, the same 
    level as required in 49 CFR part 192 and to include as property damage 
    the value of the product released and the costs associated with clean-
    up and recovery efforts. The THLPSSC voted 10 to 0 in favor of the 
    change (5 members did not vote). Two of those favoring the proposed 
    changes recommended that RSPA modify the final rule to limit property 
    damage to fair market value of the lost product and initial clean-up 
    and product recovery costs. One member said that clean-up and recovery 
    costs should not be included in total property damage.
        Three commenters disagreed with the proposed changes and 
    recommended that the rule be withdrawn. One complaint was that the 
    statistical base would be discontinuous because, in the future, RSPA 
    would not receive information on accidents costing between $5,000 and 
    $50,000. Another complaint was that the change could affect the 
    development of environmental protection requirements. RSPA understands 
    that a change in reporting levels will cause a slight skewing due to 
    truncation of the data, but believes requiring operators to report 
    accidents based solely on the $5,000 property damage criterion is 
    unnecessary and burdensome. Significant accidents will still be 
    reported because the other criteria (especially those that are 
    environmentally related) requiring reports will be unchanged: (1) 
    Explosion or fire, (2) loss of 50 barrels of liquid, (3) escape of five 
    barrels a day of highly volatile liquids, (4) a death, (5) bodily harm, 
    or (6) resulted in the pollution of any stream. Because these 
    requirements remain unchanged, those operators with more frequent small 
    releases will still be identified. As to a skewing of the data, those 
    organizations that keep track of such statistical data should be able 
    to make adjustments to account for such changes. Also, as explained in 
    the NPRM, this change will make the liquid safety reporting 
    requirements consistent with the gas safety reporting requirements 
    which will eliminate confusion. The rule change should have little, if 
    any, effect on the environment because the same spill volume reporting 
    criteria remain in effect. Only the dollar level of the reporting 
    criterion is being changed.
        Two commenters supported the rule changes as they were written. 
    Five others favored the changes, but proposed modification of the rules 
    to explain more fully the meaning of ``estimated total damage'' in 
    order to spell out the items that must be covered. They said that 
    ``estimated total damage'' is ambiguous and confusing and subject to 
    interpretation. One commenter stated that the costs of subsurface 
    restoration should be excluded from property damage because it is 
    nearly impossible to estimate the subsurface restoration costs within 
    the time allowed to report the accident.
        RSPA agrees that early estimates of the costs to clean-up a liquid 
    spill may not be exact; however, the operator should, at a later date, 
    submit a revised report that provides more reliable cost figures for 
    the clean-up.
        RSPA is clarifying the issue by amending Sec. 195.50(f) to read: 
    ``(f) Estimated property damage, including cost of clean-up and 
    recovery, value of lost product, and damage to the property of the 
    operator or others, or both, exceeding $50,000'' and Sec. 195.52(a)(3) 
    to read: ``(3) Caused estimated property damage, including cost of 
    clean-up and recovery, value of lost product, and damage to the 
    property of the operator or others, or both, exceeding $50,000.''
    
    Section 195.106  Internal design pressure.
    
        Section 195.106(a) prescribes the formula for calculating the 
    design pressure of steel pipe. In addition, Sec. 195.106(b) regulates 
    the pipe yield strength used in the design pressure formula. When the 
    specified minimum yield strength (SMYS) of pipe is unknown, 
    Sec. 195.106(b) requires that yield strength be derived from tensile 
    tests on random samples of pipe. Based on a comparable gas pipeline 
    safety standard (49 CFR 192.107(b)(2)), RSPA proposed to amend 
    Sec. 195.106(b) to allow operators to use 24,000 psi as yield strength 
    if pipe of unknown SMYS is not tensile tested. Editing changes to 
    Sec. 195.106(b) were also proposed.
        The 10 THLPSSC members who voted on the proposed amendment of 
    Sec. 195.106(b) supported it (5 did not vote). In addition, RSPA 
    received comments from four operators and one pipeline-related 
    association. The association and three of the operators agreed with the 
    proposal. One of these operators suggested further editing, part of 
    which RSPA has included in the final rule.
        One operator was concerned that the proposed rule could 
    unjustifiably reduce the MOP of its pipelines. The operator said its 
    pipelines are made of Grade B pipe (yield strength at least 35,000 psi) 
    or better. However, some pipelines may contain pipe for which 
    documentation of yield strength or tensile testing does not exist. For 
    such pipe, without new tensile testing, yield strength would have to be 
    assumed to be 24,000 psi. The operator suggested that RSPA allow 
    operators to use appropriate evidence besides tensile tests to 
    demonstrate the yield strength of pipe.
        In response to this comment, we note, first, that the proposed 
    amendment to Sec. 195.106(b) would not affect the design pressure of 
    existing pipelines unless they are replaced, relocated, or otherwise 
    changed (see Sec. 195.100). Second, Sec. 195.106(b) currently requires 
    operators to use as yield strength either SMYS or a value based on 
    tensile testing. So the operator's apparent difficulty in verifying 
    yield strength is a problem of compliance with the current rule. Third, 
    the proposed rule would relax the burden of tensile testing only when 
    MOP does not exceed the level that corresponds to a yield strength of 
    24,000 psi. When a higher MOP is desired, operators must use the 
    tensile testing option. Finally, RSPA is not aware of any acceptable 
    evidence of the yield strength of pipe of unknown SMYS apart from 
    appropriate tensile testing. Thus, the amendments to Sec. 195.106(b), 
    as discussed above, are adopted.
    
    Section 195.204  Inspection-general.
    
        The THLPSSC voted 10 to 0 in favor of the proposed change to make 
    the language gender neutral and, except for a minor correction, no 
    objections were received from commenters. The proposed change is 
    adopted as corrected.
    
    Section 195.228  Welds; standards of acceptability.
    
        One of the comments we received on proposed amendments to 
    nondestructive testing requirements under Sec. 195.234(e) (discussed 
    infra) concerned the standards for acceptance of weld flaws 
    (Sec. 195.228(b)). A pipeline-related association asked us to 
    incorporate by reference the alternative acceptance standards for girth 
    welds that are in the Appendix to American Petroleum Institute (API) 
    Standard 1104 (17th edition). For weld acceptability, Sec. 195.228(b) 
    now references the standards in Section 6 of API Standard 1104.
        In a notice of proposed rulemaking involving our review of the gas 
    pipeline safety standards in 49 CFR part 192 (Docket PS-124; 57 FR 
    39572; August 31, 1992), RSPA proposed to allow gas operators to apply 
    the API appendix in addition to section 6 criteria. Although that 
    proposal was based on a petition by API to incorporate the appendix by 
    reference in both parts 192 and 195, we overlooked the request to 
    include such a proposal in the present rulemaking.
        In the part 192 rulemaking, RSPA's gas pipeline safety advisory 
    committee voted to support the proposed amendment. Also, all but one of 
    the public comments were in favor of allowing use of the Appendix of 
    API Standard 1104.
        The dissenting commenter was concerned that industry inspection 
    personnel may not be qualified to apply the appendix. However, this 
    commenter may not have recognized that under Secs. 192.243(b) and (c), 
    operators must ensure that nondestructive testing is performed in 
    accordance with written procedures by persons who have been properly 
    trained and qualified. Sections 195.234(b) and (c) provide similar 
    requirements for nondestructive testing of welds on hazardous liquid 
    and carbon dioxide pipelines. RSPA believes these requirements are 
    adequate to assure proper application of the appendix.
        The Appendix of API Standard 1104 applies equally to girth welds in 
    gas and liquid pipelines. This amendment is not mandatory, rather it 
    provides pipeline operators an optional operating procedure. In view of 
    the prior opportunity for public comment on use of the appendix for gas 
    pipelines, the favorable response by public commenters and RSPA's 
    advisory committee, and the fact that use of the appendix would not be 
    mandatory, we believe that a further opportunity for public comment is 
    unnecessary to allow use of the appendix under Sec. 195.228(b). We feel 
    this amendment is a logical outgrowth of the Notice and furthers our 
    efforts to make parts 192 and 195 consistent wherever possible. This 
    amendment will not have a substantial impact on the regulated 
    community.
        Thus, in accordance with 5 U.S.C. 553(b)(3)(B), we are amending 
    Sec. 195.228(b) to reference the appendix without further rulemaking 
    notice. However, should any person be adversely affected by this 
    decision or wish to change the final rule, that person may submit a 
    petition for reconsideration under RSPA's rulemaking procedures in 49 
    CFR 106.35.
        The final rule provides that the appendix may be used only for 
    girth welds to which the appendix applies. For example, as section A.1 
    of the appendix states, neither welds in pump stations nor welds used 
    to connect fittings and valves are covered by the appendix. Also, the 
    appendix applies only to girth welds between pipe of equal nominal wall 
    thickness.
    
    Section 195.234  Welds: Nondestructive testing.
    
        Section 195.234(e) requires that ``100 percent of each day's girth 
    welds installed in * * * [certain] locations must be nondestructively 
    tested 100 percent unless impracticable, in which case at least 90 
    percent must be tested.'' RSPA proposed to amend Sec. 195.234(e) to 
    clarify that ``90 percent'' pertains to the number of girth welds that 
    must be tested over their entire circumference.
        In addition, Sec. 195.234(g) requires: ``At pipeline tie-ins 100 
    percent of the girth welds must be nondestructively tested.'' RSPA 
    proposed to clarify that this standard applies to tie-ins of 
    replacement sections of pipeline.
        The THLPSSC supported the proposed amendments, although one member 
    thought part 195 should define the word ``impracticable.'' We did not 
    adopt this recommendation because the word is used in its ordinary 
    dictionary sense.
        Three operators and two pipeline-related associations commented on 
    the proposed amendments. Three commenters agreed with the proposal, one 
    suggested editing changes, and one made a related proposal discussed 
    supra under the heading, ``Sec. 195.228(b) Welds; standards of 
    acceptability.'' Although we did not adopt all the editing suggestions, 
    these comments helped us provide clarity to the final rule.
        In addition, one commenter thought the proposed amendment of 
    Sec. 195.234(g) was unnecessary because Sec. 195.200 already indicates 
    that Sec. 195.234(g) applies to replacement sections. Moreover, the 
    commenter thought adding the proposed phrase to Sec. 195.234(g) would 
    create confusion over whether Secs. 195.234(a) through (f) apply to 
    replacement sections. While these observations have theoretical merit, 
    in practice, some operators have failed to recognize that ``pipeline 
    tie-ins'' include tie-ins of replacement sections. The clarifying 
    phrase adds emphasis where it is apparently needed to assure compliance 
    with the full extent of the rule. Section 195.234(g) is, therefore, 
    adopted as proposed.
    
    Sections 195.246  Installation of pipe in a ditch and 195.248 Cover 
    over buried pipeline.
    
        Section 195.246(b) is inconsistent with Sec. 195.413(b)(3) for pipe 
    in the Gulf of Mexico and its inlets (See Sec. 195.2 Definitions) under 
    water less than 15 feet deep but at least 12 feet deep, because 
    Sec. 195.246(b) permits the pipe to be without cover or to be above the 
    seabed if properly protected. Such pipe is a ``hazard to navigation'' 
    under the definition of that term in Sec. 195.2, and must have the 
    minimum cover required by Sec. 195.413(b)(3). In addition, 
    Secs. 195.248(a) and (b) are inconsistent with Sec. 195.413(b)(3) for 
    pipe in the Gulf of Mexico and its inlets under water less than 12 feet 
    deep. Section 195.248(a) allows pipe to be less than 12 inches below 
    the seabed (i.e., a hazard to navigation). In certain instances, 
    Sec. 195.248(b) allows pipe to be without cover or less than 12 inches 
    below the seabed. Neither condition is allowed under 
    Sec. 195.413(b)(3). In light of these inconsistences, RSPA proposed in 
    the NPRM to amend Secs. 195.246(b) and 195.248(a) and (b) to correct 
    the problem.
        Ten THLPSSC members favored the proposed changes (5 members did not 
    vote). One of the members favoring the changes said it would make more 
    sense to retain the existing regulation which operators have adhered to 
    for years. In similar manner, two commenters and one pipeline-related 
    organization agreed with the proposal. One commenter and two pipeline-
    related organizations disagreed and suggested that references to a 
    depth of 15 feet in the rule be eliminated. RSPA proposed changes to 
    Secs. 195.246(b), 195.248(a) and 195.248(b) so these sections would 
    conform with Public Law 101-599 (section 1, 104 Stat. 3038 (1990)) 
    which requires burial of pipe where the subsurface is under 15 feet of 
    water as measured from mean low water. Therefore, Secs. 195.246(b), 
    195.248(a) and 195.248(b) are adopted as proposed in the NPRM.
    
    Section 195.262  Pumping equipment.
    
        Section 195.262(d) regulates the location of pumping equipment. The 
    rule prohibits the installation of pumping equipment on property not 
    under the operator's control. It also prohibits installation less than 
    50 feet from the pump station boundary. RSPA proposed to amend 
    Sec. 195.262(d) to clarify that these two restraints on location apply 
    conjunctively not alternatively.
        The THLPSSC members who voted on the proposed amendment supported 
    it in concept, but 5 members recommended further editing of the rule 
    for clarity. Although three of the five persons who commented on the 
    proposal supported it as proposed, the other two commenters thought 
    further clarifying changes were needed. In view of these comments and 
    THLPSSC views, we have modified the final rule based on identical 
    wording suggested by five THLPSSC members and one commenter.
    
    Section 195.304  Testing of components.
    
        Section 195.304(b) excludes from hydrostatic testing under part 195 
    any component that is the only item being replaced or added to a 
    pipeline system if the component or a prototype was tested at the 
    factory. RSPA proposed to amend Sec. 195.304(b) to clarify that the 
    excluded components do not include pipe.
        The THLPSSC fully supported the proposed amendment. Of the six 
    comments from the public on the proposal, a pipeline-related 
    association and two operators agreed with it, while three operators 
    suggested changes.
        An operator suggested that instead of amending Sec. 195.304(b), we 
    should revise the definition of ``component'' to exclude pipe. We did 
    not adopt this suggestion because the revision would affect every rule 
    in part 195 that uses the term ``component.'' Editing suggested by 
    another operator was not adopted because it concerned matters not 
    addressed in the NPRM.
        One operator felt pipe should be excluded from hydrostatic testing 
    under Sec. 195.304(b) to the same extent as other components. The 
    operator said that hydrostatically testing short sections of mill 
    tested pipe is duplicative, costly, and not needed for safety. Although 
    the NPRM did not propose to alter the existing requirement that 
    replacement sections of pipe of any length must be hydrostatically 
    tested to part 195 standards before operation, we do not agree with 
    this commenter's contention. Normal pipe mill tests are not duplicative 
    of part 195 tests, and are not a proven safe alternative to part 195 
    requirements. However, for short sections of replacement pipe, part 195 
    test requirements could be met anywhere, including, by prior 
    arrangement with the operator, in the pipe mill. So if an operator 
    wishes to avoid field testing of short replacement sections of pipe, it 
    only needs to assure that the mill tests of those sections were done in 
    accordance with part 195 test requirements.
    
    Section 195.406  Maximum operating pressure.
    
        The changes to Sec. 195.406 are discussed supra under Sec. 195.5.
    
    Section 195.412  Inspection of rights-of-way and crossings under 
    navigable waters.
    
        Section 195.412(a) requires an operator, at intervals not exceeding 
    3 weeks, but at least 26 times each calendar year, to inspect the 
    surface conditions on or adjacent to each pipeline right-of-way. 
    Because some surface condition activities that affect the safety and 
    operation of pipelines are more visible from aerial patrols than from 
    walking or driving the right-of-way, RSPA proposed that the section be 
    changed to clarify that aerial patrols are an optional method of 
    compliance. No comments were received regarding the change and the 
    THLPSSC voted 10 to 0 in favor of the change (5 members did not vote). 
    Accordingly, the change to Sec. 195.412(a) is adopted as proposed.
        Section (b) requires operators, at intervals not exceeding 5 years, 
    to inspect each crossing under a navigable waterway (except offshore) 
    to determine the condition of the crossing. The purpose of the 
    inspection is to look for any damage, unanticipated loading, or loss of 
    protection that could threaten the safety of the pipeline. We stated in 
    the NPRM that bored crossings are usually so deep that there is little 
    likelihood the pipeline could be affected by waterway-related events, 
    such as scouring or anchor dragging. We proposed to add an exception to 
    Sec. 195.412(b) to cover bored crossings that are too deep to be 
    subject to waterway-related damage.
        The THLPSSC voted 10 to 0 in favor of the rule (5 members did not 
    vote). However, a state pipeline agency suggested the existing 
    regulation be retained. The agency stated that a pipeline operator 
    cannot be 100 percent sure a bored crossing is so deep it cannot be 
    affected as stated. RSPA received four additional comments, three of 
    which expressed an opinion that the phrase ``too deep to anticipate 
    damage from waterway conditions or vessel traffic'' is vague and 
    inappropriate. The other commenter said the proposal is unduly 
    restrictive and should be refocused from bored crossings to a more 
    generic performance standard potentially including all crossings.
        In view of the comments received, RSPA agrees with those who opined 
    that ``too deep to anticipate damage from waterway conditions or vessel 
    traffic'' is too vague. In the absence of a recognized standard on the 
    subject, it is too speculative to judge when bored crossings are buried 
    at a sufficient depth to be safe from damage by external forces. 
    Therefore, it is in the interest of public safety that the current rule 
    requiring inspection at intervals not exceeding 5 years be retained. 
    Accordingly, the proposed change to Sec. 195.412(b) is not adopted.
    
    Section 195.416  External Corrosion Control.
    
        Section 195.416(a) states that each operator shall, at intervals 
    not exceeding 15 months, but at least once each calendar year, conduct 
    tests on each underground facility that is under cathodic protection to 
    determine whether protection is adequate. RSPA is clarifying the rule 
    to reduce any misunderstanding regarding what is meant by 
    ``underground.'' The word ``underground'' in this paragraph has meant 
    any facility that is buried or in contact with the ground. This rule 
    clarification will not change the burden on operators because RSPA 
    compliance inspectors have consistently required any facility in 
    contact with the ground to be cathodically protected.
        RSPA received two comments regarding the change to Sec. 195.416(a). 
    One commenter recommended that offshore pipelines be excluded from 
    annual testing requirements. RSPA believes there is no acceptable 
    substitute for regular testing to determine if corrosion protection of 
    all lines, both onshore and offshore, is adequate. Accordingly, ``in 
    contact with the ground or submerged'' is added to the rule to assure 
    that all underwater pipelines, both onshore and offshore, are included 
    in the definition. The other commenter suggested requiring the testing 
    of ``carrier pipes'' in casings. ``Carrier pipes'' are normally buried 
    and subject to the rule. The THLPSSC voted 10 to 0 in favor of the 
    proposed change (5 members did not vote). The revision to 
    Sec. 195.416(a) is adopted as modified.
        Section 195.416(f) requires that any pipe found to be generally 
    corroded so that the remaining wall thickness is less than the minimum 
    thickness required by the pipe specification tolerances must either be 
    replaced with coated pipe that meets the requirements of part 195 or, 
    if the area is small, must be repaired. However, the operator need not 
    replace generally corroded pipe if the operating pressure is reduced to 
    be commensurate with the limits on operating pressure specified in 
    Sec. 195.406, based on the actual remaining wall thickness.
        Section 195.416(g) states that if localized corrosion pitting is 
    found to exist to a degree where leakage might result, the pipe must be 
    replaced or repaired, or the operating pressure must be reduced 
    commensurate with the strength of the pipe based on the actual 
    remaining wall thickness in the pits.
        RSPA recognizes that paragraphs (f) and (g) do not provide guidance 
    for an operator's use in determining the strength of the actual 
    remaining wall thickness of corroded steel pipe. To provide such 
    guidance, RSPA proposed amending Sec. 195.416(h) to adopt the ASME 
    Manual B31G procedure for determining the remaining strength of 
    corroded steel pipe in existing pipelines. Application of the procedure 
    was proposed to be in accordance with the limitations set out in the 
    B31G Manual. The rule would provide guidance as to whether a corroded 
    region (not penetrating the pipe wall) may be left in service; this 
    option might require a reduction in maximum allowable operating 
    pressure, but may be more economical than replacement or repair of the 
    corroded pipe.
        Ten THLPSSC members voted for the proposal (5 members did not 
    vote).
        Comments relative to Sec. 195.416(h) were received from five 
    commenters. One commenter said the proposal to change Sec. 195.416(h) 
    is inappropriate and should be redone to be consistent with 
    Sec. 192.485. Others stated that the proposal was unnecessarily 
    restrictive because it did not allow the use of other proven industry 
    developed methods for determining the remaining strength of corroded 
    pipelines. The most noteworthy method mentioned was ``A Modified 
    Criterion for Evaluating the Remaining Strength of Corroded Pipe (with 
    RSTRENG disk)'' developed by Battelle under the Pipeline Research 
    Committee of the American Gas Association (AGA). (Project PR 3-805, 
    December 1989, AGA catalog No. L51609). Project PR 3-805 was undertaken 
    to devise a modified criterion that, while still assuring pipeline 
    integrity, would eliminate as much as possible the excessive 
    specifications embodied in the ASME B31G manual. The AGA modified 
    criterion, using a complex analysis approach, can be carried out by 
    means of a PC-based program called RSTRENG. The modified criterion can 
    also be applied via tables or curves or a long-hand equation if a 
    simplified analysis is preferred.
        The addition of the modified criterion to the rule does not 
    compromise safety because it merely accepts an established pipeline 
    industry guideline, and does not impose new requirements on the 
    operators. Accordingly, RSPA is amending Sec. 195.416(h) to include the 
    AGA/Battelle--A Modified Criterion for Evaluating the Remaining 
    Strength of Corroded Pipe (with the computer disk RSTRENG).
    
    Rulemaking Analyses
    
    Impact Assessment
    
        This final rule is not considered a significant regulatory action 
    under section 3(f) of Executive Order 12866 and, therefore, was not 
    subject to review by the Office of Management and Budget. The rule is 
    not considered significant under the regulatory policies and procedures 
    of the Department of Transportation (44 FR 11034).
        A Regulatory Evaluation has been prepared and is available in the 
    docket. RSPA estimates the proposed changes to existing rules would 
    result in an estimated savings of $1,534,000 per year for the hazardous 
    liquid pipeline industry at no cost to the industry, and with no 
    adverse effect on safety. As discussed above, these savings would come 
    largely from the use of new technology, greater flexibility in 
    constructing and operating pipelines, and the elimination of 
    unnecessary requirements.
    
    Federalism Assessment
    
        RSPA has analyzed the proposed rules under the criteria of 
    Executive Order 12612 (52 FR 41685; October 30, 1987). The regulations 
    have no substantial effects on the states, on the current federal-state 
    relationship, or on the current distribution of power and 
    responsibilities among the various levels of government. Thus, 
    preparation of a federalism assessment is not warranted.
    
    Regulatory Flexibility Act
    
        RSPA criteria for small companies or entities are those with less 
    than $1,000,000 in revenues and are independently owned and operated. 
    Few of the companies subject to this rulemaking meet these criteria. 
    Accordingly, based on the facts available concerning the impact of this 
    proposal, I certify under Section 605 of the Regulatory Flexibility Act 
    that this proposal would not have a significant economic impact on a 
    substantial number of small entities. This rule applies to intrastate 
    and interstate pipeline facilities used in the transportation of 
    hazardous liquids or carbon dioxide.
    
    Paperwork Reduction Act
    
        The documentation for the information collection requirements for 
    part 195 was submitted to the Office of Management and Budget (OMB) 
    during the original rulemaking processes. Currently, regulations in 
    part 195 are covered by OMB Control Numbers 2137-0047 (approved through 
    May 31, 1994), 2137-0578 (approved through October 31, 1994) and 2137-
    0583 (approved through May 31, 1994). There are no new information 
    collection requirements in this final rule.
    
    List of Subjects in 49 CFR Part 195
    
        Ammonia, Carbon dioxide, Incorporation by reference, Petroleum, 
    Pipeline safety, Reporting and recordkeeping requirements.
    
        In consideration of the foregoing, RSPA is amending 49 CFR part 195 
    as follows:
    
    PART 195--[AMENDED]
    
        1. The authority citation for part 195 continues to read as 
    follows:
    
        Authority: 49 app. U.S.C. 2002 and 2015; and 49 CFR 1.53.
    
        2. In Sec. 195.1, the introductory text of paragraph (b) is 
    republished, paragraph (b)(5) is revised, in paragraph (b)(6) a hyphen 
    is added between the words ``in'' and ``plant'', and paragraphs (b)(7) 
    and (b)(8) are revised to read as follows:
    
    
    Sec. 195.1  Applicability.
    
    * * * * *
        (b) This part does not apply to--
    * * * * *
        (5) Transportation of hazardous liquid or carbon dioxide in 
    offshore pipelines which are located upstream from the outlet flange of 
    each facility where hydrocarbons or carbon dioxide are produced or 
    where produced hydrocarbons or carbon dioxide are first separated, 
    dehydrated, or otherwise processed, whichever facility is farther 
    downstream;
    * * * * *
        (7) Transportation of hazardous liquid or carbon dioxide--
        (i) By vessel, aircraft, tank truck, tank car, or other non-
    pipeline mode of transportation; or
        (ii) Through facilities located on the grounds of a materials 
    transportation terminal that are used exclusively to transfer hazardous 
    liquid or carbon dioxide between non-pipeline modes of transportation 
    or between a non-pipeline mode and a pipeline, not including any device 
    and associated piping that are necessary to control pressure in the 
    pipeline under Sec. 195.406(b); and
        (8) Transportation of carbon dioxide downstream from the following 
    point, as applicable:
        (i) The inlet of a compressor used in the injection of carbon 
    dioxide for oil recovery operations, or the point where recycled carbon 
    dioxide enters the injection system, whichever is farther upstream; or
        (ii) The connection of the first branch pipeline in the production 
    field that transports carbon dioxide to injection wells or to headers 
    or manifolds from which pipelines branch to injection wells.
    * * * * *
        3. In Sec. 195.2, the introductory text is republished, definitions 
    for Corrosive product, Flammable product, In-plant piping system, 
    Petroleum, Petroleum product, and Toxic product are added in 
    alphabetical order to read as follows:
    
    
    Sec. 195.2  Definitions.
    
        As used in this part--
    * * * * *
        Corrosive product means ``corrosive material'' as defined by 
    Sec. 173.136 Class 8-Definitions of this chapter.
    * * * * *
        Flammable product means ``flammable liquid'' as defined by 
    Sec. 173.120 Class 3-Definitions of this chapter.
    * * * * *
        In-plant piping system means piping that is located on the grounds 
    of a plant and used to transfer hazardous liquid or carbon dioxide 
    between plant facilities or between plant facilities and a pipeline or 
    other mode of transportation, not including any device and associated 
    piping that are necessary to control pressure in the pipeline under 
    Sec. 195.406(b).
    * * * * *
        Petroleum means crude oil, condensate, natural gasoline, natural 
    gas liquids, and liquefied petroleum gas.
        Petroleum product means flammable, toxic, or corrosive products 
    obtained from distilling and processing of crude oil, unfinished oils, 
    natural gas liquids, blend stocks and other miscellaneous hydrocarbon 
    compounds.
    * * * * *
        Toxic product means ``poisonous material'' as defined by 
    Sec. 173.132 Class 6, Division 6.1-Definitions of this chapter.
    
    
    Secs. 195.2, 195.112, 195.212, 195.413  [Amended]
    
        4. In the list below, for each section indicated in the left 
    column, the phrase indicated in the middle column is removed and the 
    phrase indicated in the right column is added: 
    
    ----------------------------------------------------------------------------------------------------------------
                  Section                                Remove                                  Add                
    ----------------------------------------------------------------------------------------------------------------
    195.2, Gathering line...............  8 inches or less in nominal diameter  219.1 mm (8\5/8\ in) or less nominal
                                                                                 outside diameter.                  
    195.112(c)..........................  An outside diameter of 4 inches or    A nominal outside diameter of 114.3 
                                           more.                                 mm (4\1/2\ in) or more.            
    195.212(b)(3)(ii)...................  The pipe is 12 inches or less in      The pipe is 323.8 mm (12\3/4\ in) or
                                           outside diameter.                     less nominal outside diameter.     
    195.413(a)..........................  Except for gathering lines of 4-inch  Except for gathering lines of 114.3 
                                           nominal diameter or smaller.          mm (4\1/2\ in) nominal outside     
                                                                                 diameter or smaller.               
    ----------------------------------------------------------------------------------------------------------------
    
        5. In Sec. 195.3, paragraph (a) is revised to read as follows:
    
    
    Sec. 195.3  Matter incorporated by reference.
    
        (a) Any document or portion thereof incorporated by reference in 
    this part is included in this part as though it were printed in full. 
    When only a portion of a document is referenced, then this part 
    incorporates only that referenced portion of the document and the 
    remainder is not incorporated. Applicable editions are listed in 
    paragraph (c) of this section in parentheses following the title of the 
    referenced material. Earlier editions listed in previous editions of 
    this section may be used for components manufactured, designed, or 
    installed in accordance with those earlier editions at the time they 
    were listed. The user must refer to the appropriate previous edition of 
    49 CFR for a listing of the earlier editions.
    * * * * *
        6. In Sec. 195.3, paragraphs (b)(1) through (b)(5) are redesignated 
    as paragraphs (b)(2) through (b)(6) and paragraph (b)(1) is added to 
    read as follows:
    
    
    Sec. 195.3  Matter incorporated by reference.
    
    * * * * *
        (b) * * *
        (1) American Gas Association (AGA), 1515 Wilson Boulevard, 
    Arlington, VA 22209.
    * * * * *
        7. In Sec. 195.3, paragraphs (c)(2)(iii) and (c)(2)(iv) are 
    redesignated as paragraphs (c)(2)(v) and (c)(2)(vi) and paragraphs 
    (c)(2)(iii) and (c)(2)(iv) are added to read as follows:
    
    
    Sec. 195.3  Matter incorporated by reference.
    
    * * * * *
        (c) * * *
        (2) * * *
        (iii) ASME/ANSI B31.8 ``Gas Transmission and Distribution Piping 
    Systems'' (1989 with ASME/ANSI B31.8a-1990, B31.8b-1990, B31.8c-1992 
    Addenda and Special Errata issued July 6, 1990 and Special Errata 
    (Second) issued February 28, 1991).
        (iv) ASME/ANSI B31G, ``Manual for Determining the Remaining 
    Strength of Corroded Pipelines'' (1991).
    * * * * *
        8. In Sec. 195.3, paragraphs (c)(1) through (c)(4) are redesignated 
    as paragraphs (c)(2) through (c)(5) and paragraph (c)(1) is added to 
    read as follows:
    
    
    Sec. 195.3  Matter incorporated by reference.
    
    * * * * *
        (c) * * *
        (1) American Gas Association (AGA): AGA Pipeline Research 
    Committee, Project PR-3-805, ``A Modified Criterion for Evaluating the 
    Remaining Strength of Corroded Pipe'' (December 1989). The RSTRENG 
    program may be used for calculating remaining strength.
    * * * * *
        9. Section 195.5 is amended by revising paragraphs (a)(1) and 
    (a)(4) to read as follows:
    
    
    Sec. 195.5  Conversion to service subject to this part.
    
        (a) * * *
        (1) The design, construction, operation, and maintenance history of 
    the pipeline must be reviewed and, where sufficient historical records 
    are not available, appropriate tests must be performed to determine if 
    the pipeline is in satisfactory condition for safe operation. If one or 
    more of the variables necessary to verify the design pressure under 
    Sec. 195.106 or to perform the testing under paragraph (a)(4) of this 
    section is unknown, the design pressure may be verified and the maximum 
    operating pressure determined by--
        (i) Testing the pipeline in accordance with ASME B31.8, Appendix N, 
    to produce a stress equal to the yield strength; and
        (ii) Applying, to not more than 80 percent of the first pressure 
    that produces a yielding, the design factor F in Sec. 195.106(a) and 
    the appropriate factors in Sec. 195.106(e).
    * * * * *
        (4) The pipeline must be tested in accordance with subpart E of 
    this part to substantiate the maximum operating pressure permitted by 
    Sec. 195.406.
    * * * * *
        10. Section 195.50(f) is revised to read as follows:
    
    
    Sec. 195.50  Reporting accidents.
    
    * * * * *
        (f) Estimated property damage, including cost of clean-up and 
    recovery, value of lost product, and damage to the property of the 
    operator or others, or both, exceeding $50,000.
        11. Section 195.52(a)(3) is revised to read as follows:
    
    
    Sec. 195.52  Telephonic notice of certain accidents.
    
        (a) * * *
        (3) Caused estimated property damage, including cost of cleanup and 
    recovery, value of lost product, and damage to the property of the 
    operator or others, or both, exceeding $50,000;
    * * * * *
        12. Section 195.106(b) is revised to read as follows:
    
    
    Sec. 195.106  Internal design pressure.
    
    * * * * *
        (b) The yield strength to be used in determining the internal 
    design pressure under paragraph (a) of this section is the specified 
    minimum yield strength. If the specified minimum yield strength is not 
    known, the yield strength to be used in the design formula is one of 
    the following:
        (1)(i) The yield strength determined by performing all of the 
    tensile tests of API Specification 5L on randomly selected specimens 
    with the following number of tests: 
    
    ------------------------------------------------------------------------
                 Pipe size                           No. of tests           
    ------------------------------------------------------------------------
    Less than 168.3 mm (6\5/8\ in)       One test for each 200 lengths.     
     nominal outside diameter.                                              
    168.3 through 323.8 mm (6\5/8\       One test for each 100 lengths.     
     through 12\3/4\ in) nominal                                            
     outside diameter.                                                      
    Larger than 323.8 mm (12\3/4\ in)    One test for each 50 lengths.      
     nominal outside diameter.                                              
    ------------------------------------------------------------------------
    
        (ii) If the average yield-tensile ratio exceeds 0.85, the yield 
    strength shall be taken as 165,474 kPa (24,000 psi). If the average 
    yield-tensile ratio is 0.85 or less, the yield strength of the pipe is 
    taken as the lower of the following:
        (A) Eighty percent of the average yield strength determined by the 
    tensile tests.
        (B) The lowest yield strength determined by the tensile tests.
        (2) If the pipe is not tensile tested as provided in paragraph (b) 
    of this section, the yield strength shall be taken as 165,474 kPa 
    (24,000 psi).
    * * * * *
        13. In Sec. 195.106(c), the last sentence is revised to read as 
    follows:
    
    
    Sec. 195.106  Internal design pressure.
    
    * * * * *
        (c) * * * However, the nominal wall thickness may not be more than 
    1.14 times the smallest measurement taken on pipe that is less than 508 
    mm (20 in) nominal outside diameter, nor more than 1.11 times the 
    smallest measurement taken on pipe that is 508 mm (20 in) or more in 
    nominal outside diameter.
    * * * * *
        14. In Sec. 195.204, the last sentence is revised to read as 
    follows:
    
    
    Sec. 195.204  Inspection--general.
    
        * * * No person may be used to perform inspections unless that 
    person has been trained and is qualified in the phase of construction 
    to be inspected.
        15. Section 195.228(b) is revised to read as follows:
    
    
    Sec. 195.228  Welds and welding inspection: Standards of acceptability.
    
    * * * * *
        (b) The acceptability of a weld is determined according to the 
    standards in section 6 of API Standard 1104. However, if a girth weld 
    is unacceptable under those standards for a reason other than a crack, 
    and if the Appendix to API Standard 1104 applies to the weld, the 
    acceptability of the weld may be determined under that appendix.
        16. Section 195.234 is amended by revising the introductory text of 
    paragraph (e) and by revising paragraph (g) to read as follows:
    
    
    Sec. 195.234  Welds: Nondestructive testing.
    
    * * * * *
        (e) All girth welds installed each day in the following locations 
    must be nondestructively tested over their entire circumference, except 
    that when nondestructive testing is impracticable for a girth weld, it 
    need not be tested if the number of girth welds for which testing is 
    impracticable does not exceed 10 percent of the girth welds installed 
    that day:
    * * * * *
        (g) At pipeline tie-ins, including tie-ins of replacement sections, 
    100 percent of the girth welds must be nondestructively tested.
        17. Section 195.246 is amended by revising paragraph (b) to read as 
    follows:
    
    
    Sec. 195.246  Installation of pipe in a ditch.
    
    * * * * *
        (b) Except for pipe in the Gulf of Mexico and its inlets, all 
    offshore pipe in water at least 3.7 m 12-ft-deep but not more than 61 m 
    (200 ft) deep, as measured from the mean low tide, must be installed so 
    that the top of the pipe is below the natural bottom unless the pipe is 
    supported by stanchions, held in place by anchors or heavy concrete 
    coating, or protected by an equivalent means.
        18. Section 195.248 is amended by revising in the first column of 
    the table in paragraph (a) the language ``Other offshore areas under 
    water less than 12-ft-deep as measured from the mean low tide'' to read 
    ``Gulf of Mexico and its inlets and other offshore areas under water 
    less than 12-ft-deep as measured from the mean low tide'' and by 
    revising the introductory text of paragraph (b) to read as follows:
    
    
    Sec. 195.248  Cover over buried pipeline.
    
    * * * * *
        (b) Except for the Gulf of Mexico and its inlets, less cover than 
    the minimum required by paragraph (a) of this section and Sec. 195.210 
    may be used if--
    * * * * *
        19. Section 195.262(d) is revised to read as follows:
    
    
    Sec. 195.262  Pumping equipment.
    
    * * * * *
        (d) Except for offshore pipelines, pumping equipment must be 
    installed on property that is under the control of the operator and at 
    least 15.2 m (50 ft) from the boundary of the pump station.
    * * * * *
        20. The introductory text of Sec. 195.304(b) is revised to read as 
    follows:
    
    
    Sec. 195.304  Testing of components.
    
    * * * * *
        (b) A component, other than pipe, that is the only item being 
    replaced or added to the pipeline system need not be hydrostatically 
    tested under paragraph (a) of this section if the manufacturer 
    certifies that either--
    * * * * *
        21. Section 195.406 is amended by republishing the introductory 
    text of paragraph (a) and revising paragraph (a)(1) to read as follows:
    
    
    Sec. 195.406  Maximum operating pressure.
    
        (a) Except for surge pressures and other variations from normal 
    operations, no operator may operate a pipeline at a pressure that 
    exceeds any of the following:
        (1) The internal design pressure of the pipe determined in 
    accordance with Sec. 195.106. However, for steel pipe in pipelines 
    being converted under Sec. 195.5, if one or more factors of the design 
    formula (Sec. 195.106) are unknown, one of the following pressures is 
    to be used as design pressure:
        (i) Eighty percent of the first test pressure that produces yield 
    under section N5.0 of Appendix N of ASME B31.8, reduced by the 
    appropriate factors in Secs. 195.106 (a) and (e); or
        (ii) If the pipe is 323.8 mm (12\3/4\ in) or less outside diameter 
    and is not tested to yield under this paragraph, 1379 kPa (200 psig).
    * * * * *
        22. Section 195.412(a) is revised to read as follows:
    
    
    Sec. 195.412  Inspection of rights-of-way and crossings under navigable 
    waters.
    
        (a) Each operator shall, at intervals not exceeding 3 weeks, but at 
    least 26 times each calendar year, inspect the surface conditions on or 
    adjacent to each pipeline right-of-way. Methods of inspection include 
    walking, driving, flying or other appropriate means of traversing the 
    right-of-way.
    * * * * *
        23. Section 195.416 is amended by revising paragraph (a), 
    redesignating paragraph (h) as paragraph (i) and adding a new paragraph 
    (h) to read as follows:
    
    
    Sec. 195.416  External corrosion control.
    
        (a) Each operator shall, at intervals not exceeding 15 months, but 
    at least once each calendar year, conduct tests on each buried, in 
    contact with the ground, or submerged pipeline facility in its pipeline 
    system that is under cathodic protection to determine whether the 
    protection is adequate.
    * * * * *
        (h) The strength of the pipe, based on actual remaining wall 
    thickness, for paragraphs (f) and (g) of this section may be determined 
    by the procedure in ASME B31G manual for Determining the Remaining 
    Strength of Corroded Pipelines or by the procedure developed by AGA/
    Battelle--A Modified Criterion for Evaluating the Remaining Strength of 
    Corroded Pipe (with RSTRENG disk). Application of the procedure in the 
    ASME B31G manual or the AGA/Battelle Modified Criterion is applicable 
    to corroded regions (not penetrating the pipe wall) in existing steel 
    pipelines in accordance with limitations set out in the respective 
    procedures.
    * * * * *
        Issued in Washington, DC, on June 9, 1994.
    Ana Sol Gutierrez,
    Acting Administrator, Research and Special Programs Administration.
    [FR Doc. 94-15510 Filed 6-27-94; 8:45 am]
    BILLING CODE 4910-60-P
    
    
    

Document Information

Effective Date:
7/28/1994
Published:
06/28/1994
Department:
Research and Special Programs Administration
Entry Type:
Uncategorized Document
Action:
Final rule.
Document Number:
94-15510
Dates:
This regulation is effective July 28, 1994. The incorporation by reference of certain publications listed in the regulations is approved by the Director of the Federal Register as of July 28, 1994.
Pages:
0-0 (None pages)
Docket Numbers:
Federal Register: June 28, 1994, Docket PS-127, Amdt. 195-52
RINs:
2137-AC27
CFR: (33)
49 CFR 195.416(a)
49 CFR 195.106(b)
49 CFR 195.228(b)
49 CFR 195.412(b)
49 CFR 195.1(b)(5)
More ...