95-15965. Texas Utilities Electric Company (Comanche Peak Steam Electric Station, Unit 1); Exemption  

  • [Federal Register Volume 60, Number 125 (Thursday, June 29, 1995)]
    [Notices]
    [Pages 33875-33876]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-15965]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-445]
    
    
    Texas Utilities Electric Company (Comanche Peak Steam Electric 
    Station, Unit 1); Exemption
    
    I
    
        Texas Utilities Electric Company (the licensee) is the holder of 
    Facility Operating License No. NPF-87 for the Comanche Peak Steam 
    Electric Station (CPSES), Unit No. 1. The license provides, among other 
    things, that the licensee is subject to all rules, regulations, and 
    orders of the Commission now or hereafter in effect.
        The facility consists of a pressurized water reactor at the 
    licensee's site in Somervell County, Texas.
    
    II
    
        The Code of Federal Regulations, 10 CFR 50.55a(f)(4)(ii), requires 
    that inservice tests to verify operational readiness of pumps and 
    valves, whose function is required for safety, conducted during 
    successive 120-month intervals must comply with the requirements of the 
    latest edition and addenda of Section XI of the ASME Boiler and 
    Pressure Vessel Code incorporated by reference in paragraph (b) of 10 
    CFR 50.55a, twelve months prior to the start of the 120-month interval.
        NRC regulations in 10 CFR 50.12(a) provide for specific exemptions 
    from the requirements of the regulation in Part 50 if: (1) The 
    exemption is authorized by law, will not present an undue risk to the 
    public health and safety, and is consistent with the common defense and 
    security; and, (2) special circumstances are present. The regulations 
    in, 10 CFR 50.12(a)(2)(ii) provide that special circumstances are 
    present where application of the regulation in the particular 
    circumstances would not serve the underlying purpose of the rule or is 
    not necessary to achieve the underlying purpose of the rule. The 
    underlying purpose of 10 CFR 50.55a(f)(4)(ii) is to assure that 
    inservice test (IST) programs are routinely updated to conform to 
    advances in the industry in order to assure continued operability of 
    pumps and valves required for safe operation.
    
    III
    
        Pursuant to 10 CFR 50.12, the licensee requested on March 1, 1994, 
    an exemption from the requirement of 10 CFR 50.55a(f)(4)(ii) which 
    would allow the first periodic 120-month interval revision for the 
    CPSES Unit I IST plan to be based on the Unit 2 commercial operation 
    date (August 3, 1993). The first periodic interval for Unit 1 is 
    currently based on the Unit 1 commercial operation date (August 13, 
    1990). The staff had requested additional information to supplement the 
    March 1, 1994, letter. The licensee provided the requested information 
    in its letter dated August 12, 1994.
        CPSES Unit 1 and Unit 2 began commercial operation approximately 
    three years apart and are therefore on different schedules for periodic 
    IST program revisions. In order to maintain the consistency of the IST 
    program between CPSES Units 1 and 2, the licensee intends to perform 
    future 120-month program revisions for both units coincidently. The 
    licensee proposes to accomplish this by performing all future IST 
    program revisions for both units at 120-month intervals based on the 
    Unit 2 commercial operation date. This would effectively extend the 
    first test interval for Unit 1 from 120 months to approximately 156 
    months.
        At the licensee's request, the NRC staff previously granted 
    permission to use the later approved 1989 edition of American Society 
    of Mechanical Engineers Boiler and Pressure Vessel Code (ASME) Section 
    XI for the interval of inservice testing at CPSES Unit 2 and at the 
    same time granted permission to update the Unit 1 IST program to the 
    use of that same Code. Effectively, the pumps and valves at CPSES Units 
    1 and 
    
    [[Page 33876]]
    2 are being tested to the requirements of a later Code edition that 
    might otherwise not be required to be implemented until the year 2000 
    for Unit 1 and the year 2003 for Unit 2. The changes to the 1989 
    edition of ASME Section XI regarding pump and valve testing represent a 
    substantial technical improvement over the 1986 edition not usually 
    found from edition to edition. Since none of the IST test frequencies 
    are directly tied to the 120-month interval, except for safety and 
    relief valve testing, the test frequencies are unchanged and remain 
    compliant with the committed edition of the code or as modified by 
    approved relief requests. The schedule for safety and relief valves 
    must be maintained on a five- or ten-year frequency; however, this can 
    be accomplished even if both units are placed on a concurrent interval.
    IV
    
        Therefore, based on these considerations, it is unlikely that the 
    IST program for Unit 1 will not be updated such that there would be an 
    increase in the risk of failure for operational readiness of pumps and 
    valves whose function is required for the safety of Unit 1. Since the 
    Unit 1 IST was updated to the Code edition required to support the 
    commercial operation of Unit 2 on August 3, 1993, Unit 1 was 
    effectively updated per 10 CFR 50.55a(f)(4)(ii) at that time. Thus, 
    using that date as the start of the 120-month interval will achieve the 
    underlying purpose of 10 CFR 50.55a(f)(4)(ii). However, as noted above, 
    the licensee must maintain the safety and relief valve testing on a 5- 
    and 10-year frequency, in accordance with American National Standards 
    Institute (ANSI)/ASME OM-1, which is referenced in the 1989 edition of 
    ASME Section XI as applicable for testing of safety and relief valves.
        Consequently, the Commission concludes that the special 
    circumstances of 10 CFR 50.12(a)(2)(ii) exist in that application of 
    the regulation in this particular circumstance is not necessary to 
    achieve the underlying purpose of the rule.
        Further, it is advantageous for a facility with two similar units 
    to implement an IST program which is consistent between units by 
    testing each unit to the same Code edition and by scheduling 120-month 
    program updates on each unit to coincide. CPSES Units 1 and 2 are 
    similar units and the licensee has therefore attempted to capture these 
    advantages through the use of one IST program which specifies the same 
    test requirements for both units based on the same Code Edition.
        The advantages include a significant reduction in the 
    administrative effort required in preparing periodic program updates, a 
    corresponding reduction in the program review effort by the NRC staff 
    and a reduction in the potential for personnel errors in the 
    performance of testing requirements. Further, a significant unit 
    difference is eliminated by applying the same Code requirements to the 
    testing of both units. In addition, this exemption increases plant 
    safety through simplification and standardization of plant testing 
    procedures, does not present an undue risk to the public health and 
    safety, and is consistent with the common defense and security.
    
    V
    
        Accordingly, the Commission has determined that, pursuant to 10 CFR 
    50.12, this exemption is authorized by law, will not endanger life or 
    property or the common defense and security, and is otherwise in the 
    public interest and that the special circumstances required by 10 CFR 
    50.12(a)(ii) are present. Therefore, the Commission hereby grants Texas 
    Utilities Electric Company an exemption from those requirements of 10 
    CFR 50.55a(f)(4)(ii) such that the CPSES Unit 1, periodic 120-month IST 
    program interval revisions will be based on the Unit 2 commercial 
    operation date (August 3, 1993).
        Pursuant to 10 CFR 51.32, the Commission has determined that the 
    granting of this exemption will have no significant effect on the 
    quality of the human environment (60 FR 32356). This exemption is 
    effective upon issuance.
    
        Dated at Rockville, Maryland, this 21st day of June 1995.
    
        For the Nuclear Regulatory Commission.
    Elinor G. Adensam,
    Acting Director, Division of Reactor Projects III/IV, Office of Nuclear 
    Reactor Regulation.
    [FR Doc. 95-15965 Filed 6-28-95; 8:45 am]
    BILLING CODE 7590-01-M
    
    

Document Information

Published:
06/29/1995
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
95-15965
Pages:
33875-33876 (2 pages)
Docket Numbers:
Docket No. 50-445
PDF File:
95-15965.pdf