99-14452. NASA Structured Approach for Profit or Fee Objective  

  • [Federal Register Volume 64, Number 109 (Tuesday, June 8, 1999)]
    [Proposed Rules]
    [Pages 30468-30472]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-14452]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
    
    48 CFR Part 1815
    
    
    NASA Structured Approach for Profit or Fee Objective
    
    AGENCY: National Aeronautics and Space Administration.
    
    ACTION: Proposed rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: This proposed NASA FAR Supplement (NFS) revision modifies the 
    agency's structured approach for developing a profit or fee objective. 
    This change eliminates the element of cost approach currently 
    prescribed for establishing profit and fee objectives and focuses on 
    performance risk analysis which requires the evaluation of specific 
    technical, management and cost risk factors; provides a new method for 
    determining contract type risk and introduces a working capital 
    adjustment provision; and retains with modification the Other 
    Considerations factor contained in the structured approach currently 
    prescribed. The new form for developing the profit/fee objectives, NASA 
    Form 634, is provided for information at the end of the proposed rule 
    as an attachment to the preamble. An electronic version is also 
    available at http://ec.msfc.nasa.gov/hq/library/NF634-2.xlc.
    
    DATES: Comments should be submitted on or before August 9, 1999.
    
    ADDRESSES: Interested parties should submit written comments to Donna 
    Fortunat, NASA Headquarters, Office of Procurement, Analysis Division 
    (Code HC), Washington, DC 20546. Comments may also be submitted by e-
    mail to donna.fortunat@hq.nasa.gov.
    
    FOR FURTHER INFORMATION CONTACT: Donna Fortunat, NASA Headquarters, 
    Code HC, Washington, DC 20546, telephone: (202) 358-0426; email: 
    donna.fortunat@hq.nasa.gov.
    
    SUPPLEMENTARY INFORMATION:
    
    Background
    
        FAR 15.404-4(b)(1)(i) requires agencies to use a structured 
    approach for determining profit or fee prenegotiation objectives. This 
    proposed revision to the NASA structured approach method uses a 
    performance risk method for calculating profit and fee objectives 
    instead of the currently used cost element approach. The revised 
    approach is expected to provide more appropriate emphasis on the nature 
    of the goods and services being acquired and on the risks inherent in 
    delivering those goods and services and thereby prove to be more 
    effective in motivating and rewarding contractor performance. In 
    addition, the revised policy provides a common framework for NASA and 
    industry to evaluate potential risk and profitability in a way that is 
    relevant to both parties. FAR 15.404-4(b)(2) permits agencies to use 
    another agency's structured approach and the changes in this revised 
    policy represent an Agency adaptation of DoD's alternate structured 
    approach.
    
    Impact
    
    Regulatory Flexibility Act
    
        An initial Regulatory Flexibility Analysis has not been prepared 
    because the proposed change is not expected to have a significant 
    economic impact on a substantial number of small entities within the 
    meaning of the Regulatory Flexibility Act, 5 U.S.C. 601 et seq. Most 
    small entities receive contracts based on competition and are not 
    subject to the structured fee process.
    
    Paperwork Reduction Act
    
        The Paperwork Reduction Act does not apply because the changes to 
    the NFS do not impose any recordkeeping or information collection 
    requirements, or collections of information from offerors, contractors, 
    or members of the public that require the approval of the Office of 
    Management and Budget under 44 U.S.C. 3501, et seq.
    
    List of Subjects in CFR Part 1815
    
        Government Procurement
    
    Tom Luedtke,
    Acting Associate Administrator for Procurement.
    
        Accordingly, 48 CFR Part 1815 is proposed to be amended as follows:
    
    PART 1815--CONTRACTING BY NEGOTIATION
    
        1. The authority citation for 48 CFR Part 1815 continues to read as 
    follows:
    
        Authority: 42 U.S.C. 2473(c)(1).
    
        2. Sections 1815.404-4, 1815.404-470, and 1815.404-471 are revised 
    and sections 1815.404-471-1, 1815.404-471-2, 1815.404-471-3, 1815.404-
    471-4, and 1815.404-471-5 are added to read as follows:
    
    
    1815.404-4  Profit. (NASA supplements paragraphs (b) and (c))
    
        (b)(1)(i)(a) The NASA structured approach for determining profit or 
    fee objectives, described in 1815.404-471 shall be used to determine 
    profit or fee objectives in the negotiation of contracts greater than 
    or equal to $100,000 that use cost analysis and are:
        (1) Awarded on the basis of other than full and open competition 
    (see FAR 6.3);
        (2) Awarded under NASA Research Announcements (NRAs) and 
    Announcements of Opportunity (AO's); or
        (3) Awarded under the Small Business Innovative Research (SBIR) or 
    the Small Business Technology Transfer Research (STTR) programs.
        (b) The rate calculated for the basic contract may be used on all 
    actions under the contract, provided that conditions affecting profit 
    or fee do not change.
        (c) Although specific agreement on the applied weights or values 
    for individual profit or fee factors shall not be attempted, the 
    contracting officer may encourage the contractor to--
        (1) Present the details of its proposed profit amounts in the 
    structured approach format or similar structured approach; and
        (2) Use the structured approach method in developing profit or fee 
    objectives for negotiated subcontracts.
        (ii) The use of the NASA structured approach for profit or fee is 
    not required for:
        (a) Architect-engineer contracts;
        (b) Management contracts for operation and/or maintenance of 
    Government facilities;
        (c) Construction contracts;
        (d) Contracts primarily requiring delivery of materials supplied by 
    subcontractors;
        (e) Termination settlements; and
        (f) Contracts having unusual pricing situations when the 
    procurement officer determines in writing that the structured approach 
    is unsuitable.
        (c)(2) Contracting officers shall document the profit or fee 
    analysis in the contract file.
    
    
    1815.404-470  NASA Form 634.
    
        NASA Form (NF) 634 shall be used in performing the analysis 
    necessary to develop profit or fee objectives.
    
    
    1815.404-471  NASA structured approach for profit or fee objective.
    
    
    1815.404-471-1  General.
    
        (a) The structured approach for determining profit or fee 
    objectives (NF 634) focuses on three profit factors:
        (1) Performance risk;
        (2) Contract type risk including working capital investment; and
        (3) Other Considerations which may be considered by the contracting 
    officer to account for special circumstances
    
    [[Page 30469]]
    
    that are not adequately addressed in the performance risk and contract 
    type risk factors.
        (b) The contracting officer assigns values to each profit or fee 
    factor; the value multiplied by the base results in the profit/fee 
    objective for that factor. Each factor has a normal value and a 
    designated range of values. The normal value is representative of 
    average conditions on the prospective contract when compared to all 
    goods and services acquired by NASA. The designated range provides 
    values based on above normal or below normal conditions. In the 
    negotiation documentation, the contracting officer need not explain 
    assignment of the normal value, but must address conditions that 
    justify assignment of other than the normal value.
    
    
    1815.404-471-2  Performance Risk
    
        (a) Risk Factors. Performance risk addresses the contractor's 
    degree of risk in fulfilling the contract requirements. It consists of 
    three risk factors:
        (1) Technical--the technical uncertainties of performance;
        (2) Management--the degree of management effort necessary to ensure 
    that contract requirements are met; and
        (3) Cost control--the contractor's efforts to reduce and control 
    costs.
        (b) Risk factor weighting, values and calculations. A weighting and 
    value is assigned to each of the risk factors to determine a profit/fee 
    objective.
        (c) Values. The normal value is 6 percent and the designated range 
    is 4 percent to 8 percent.
        (d) Evaluation criteria for technical risk factor.
        (1) In determining the appropriate value for the technical risk 
    factor, the contracting officer shall review the contract requirements 
    and focus on the critical performance elements in the statement of work 
    or specifications. Contracting officers shall consider the--
        (i) Technology being applied or developed by the contractor;
        (ii) Technical complexity;
        (iii) Program maturity;
        (iv) Performance specifications and tolerances;
        (v) Delivery schedule; and
        (vi) Extent of a warranty or guarantee.
        (2) Above normal conditions indicating substantial technical risk.
        (i) The contracting officer may assign a higher than normal value 
    in those cases where there is a substantial technical risk, such as 
    when--
        (A) The contractor is either developing or applying advanced 
    technologies;
        (B) Items are being manufactured using specifications with 
    stringent tolerance limits;
        (C) The efforts require highly skilled personnel or require the use 
    of state-of-the-art machinery;
        (D) The services or analytical efforts are extremely important to 
    the government and must be performed to exacting standards;
        (E) The contractor's independent development and investment has 
    reduced the Government's risk or cost;
        (F) The contractor has accepted an accelerated delivery schedule to 
    meet the Government's requirements; or
        (G) The contractor has assumed additional risk through warranty 
    provisions.
        (ii) The contracting officer may assign a value significantly above 
    normal. A maximum value may be assigned when the effort involves--
        (A) Extremely complex, vital efforts to overcome difficult 
    technical obstacles that require personnel with exceptional abilities, 
    experience, and professional credentials;
        (B) Development or initial production of a new item, particularly 
    if performance or quality specifications are tight; or
        (C) A high degree of development or production concurrency.
        (3) Below normal conditions indicating lower than normal technical 
    risk.
        (i) The contracting officer may assign a lower than normal value in 
    those cases where the technical risk is low, such as when the--
        (A) Acquisition is for off-the-shelf items;
        (B) Requirements are relatively simple;
        (C) Technology is not complex;
        (D) Efforts do not require highly skilled personnel;
        (E) Efforts are routine; or
        (F) Acquisition is a follow-on effort or a repetitive type 
    acquisition.
        (ii) The contracting officer may assign a value significantly below 
    normal. A minimum value may be justified when the effort involves--
        (A) Routine services;
        (B) Production of simple items;
        (C) Rote entry or routine integration of Government-furnished 
    information; or
        (D) Simple operations with Government-furnished property.
        (e) Evaluation criteria for management risk factor.
        (1) In determining the appropriate value for the management risk 
    factor, the contracting officer shall review the contract requirements 
    and focus on the critical performance elements in the statement of work 
    or specifications. Contracting officers shall--
        (i) Assess the contractor's management and internal control systems 
    using contracting office information and reviews made by contract 
    administration offices;
        (ii) Assess the management involvement expected on the prospective 
    contract action; and
        (iii) Consider the degree of cost mix as an indication of the types 
    of resources applied and value added by the contractor.
        (2) Above normal conditions indicating substantial management risk.
        (i) The contracting officer may assign a higher than normal value 
    when the management effort is intense, such as when--
        (A) The contractor's value added is both considerable and 
    reasonably difficult; or
        (B) The effort involves a high degree of integration and 
    coordination.
        (ii) The contracting officer may justify a maximum value when the 
    effort--
        (A) Requires large-scale integration of the most complex nature;
        (B) Involves major international activities with significant 
    management coordination; or
        (C) Has critically important milestones.
        (3) Below normal conditions indicating lower than normal management 
    risk.
        (i) The contracting officer may assign a lower than normal value 
    when the management effort is minimal, such as when--
        (A) The program is mature and many end item deliveries have been 
    made;
        (B) The contractor adds minimum value to an item;
        (C) The efforts are routine and require minimal supervision;
        (D) The contractor fails to provide an adequate analysis of 
    subcontractor costs; or
        (E) The contractor does not cooperate in the evaluation and 
    negotiation of the proposal.
        (ii) The contracting officer may assign a value significantly below 
    normal. A minimum value may be assigned when--
        (A) Reviews performed by the field administration offices disclose 
    unsatisfactory management and internal control systems (e.g., quality 
    assurance, property control, safety, security); or
        (B) The effort requires an unusually low degree of management 
    involvement.
        (f) Evaluation criteria for cost control risk factor.
        (1) In determining the appropriate value for the cost control risk 
    factor, the contracting officer shall--
        (i) Evaluate the expected reliability of the contractor's cost 
    estimates (including the contractor's cost estimating system);
    
    [[Page 30470]]
    
        (ii) Evaluate the contractor's cost reduction initiatives (e.g., 
    competition advocacy programs);
        (iii) Assess the adequacy of the contractor's management approach 
    to controlling cost and schedule; and
        (iv) Evaluate any other factors that affect the contractor's 
    ability to meet the cost targets (e.g., foreign currency exchange rates 
    and inflation rates).
        (2) Above normal conditions indicating substantial cost control 
    risk.
        (i) The contracting officer may assign a value higher than normal 
    value if the contractor can demonstrate a highly effective cost control 
    program, such as when--
        (A) The contractor provides fully documented and reliable cost 
    estimates;
        (B) The contractor has an aggressive cost reduction program that 
    has demonstrable benefits;
        (C) The contractor uses a high degree of subcontract competition; 
    or
        (D) The contractor has a proven record of cost tracking and 
    control.
        (3) Below normal conditions indicating lower than normal cost 
    control risk.
        (i) The contracting officer may assign a lower than normal value in 
    those cases where the contractor demonstrates minimal concern for cost 
    control, such as when--
        (A) The contractor's cost estimating system is marginal;
        (B) The contractor has made minimal effort to initiate cost 
    reduction programs;
        (C) The contractor's cost proposal is inadequate; or
        (D) The contractor has a record of cost overruns or the indication 
    of unreliable cost estimates and lack of cost control.
    
    
    1815.404-471-3  Contract type risk and working capital adjustment.
    
        (a) Risk factors. The contract type risk factor focuses on the 
    degree of cost risk accepted by the contractor under varying contract 
    types. The working capital adjustment is an adjustment added to the 
    profit objective for contract type risk. It applies to fixed-price type 
    contracts that provide for progress payments. Though it uses a formula 
    approach, it is not intended to be an exact calculation of the cost of 
    working capital. Its purpose is to give general recognition to the 
    contractor's cost of working capital under varying contract 
    circumstances, financing policies, and the economic environment. This 
    adjustment is limited to 4 percent.
        (b) Risk factor values and calculations. A risk value is assigned 
    to calculate the profit or fee objective for contract type. A contract 
    length factor is assigned and applied to costs financed when a working 
    capital adjustment is appropriate. This calculation is only performed 
    when the prospective contract is a fixed-price contract containing 
    provisions for progress payments.
        (c) Values: Normal and designated ranges.
    
    ----------------------------------------------------------------------------------------------------------------
                                                               Normal value
                      Contract type                     Note     (percent)          Designated range (percent)
    ----------------------------------------------------------------------------------------------------------------
    Firm-fixed-price, no financing..................      (1)          5     4 to 6.
    Firm-fixed-price with performance-based payments      (6)          4     2.5 to 5.5.
    Firm-fixed-price with progress payments.........      (2)          4     3 to 5.
    Fixed-price-incentive, no financing.............      (1)          3     2 to 4.
    Fixed-price-incentive, with performance-based         (6)          2     .5 to 3.5.
     payments.
    Fixed-price, redeterminable.....................      (3)          0     0.
    Fixed-price-incentive, with progress payments...      (2)          2     1 to 3.
    Cost-plus-incentive-fee.........................      (4)          1     0 to 2.
    Cost-plus-award fee.............................      (4)           .75  .5 to 1.5.
    Cost-plus-fixed fee.............................      (4)           .5   0 to 1.
    Time-and-materials..............................      (5)           .5   0 to 1.
    Labor-hour......................................      (5)           .5   0 to 1.
    Firm-fixed-price, level-of-effort, term.........      (5)           .5   0 to 1.
    ----------------------------------------------------------------------------------------------------------------
    
        (1) ``No financing,'' means that the contract either does not 
    provide progress or performance based payments, or provides them only 
    on a limited basis. Do not compute a working capital adjustment.
        (2) When progress payments are present, compute a working capital 
    adjustment.
        (3) For purposes of assigning profit values, treat a fixed-price 
    redeterminable contract as if it were a fixed-price-incentive contract 
    with below normal provisions.
        (4) Cost-plus contracts shall not receive the working capital 
    adjustment.
        (5) These types of contracts are considered cost-plus-fixed-fee 
    contracts for the purposes of assigning profit values. Do not compute 
    the working capital adjustment. However, higher than normal values may 
    be assigned within the designated range to the extent that portions of 
    cost are fixed.
        (6) When performance-based payments are used, do not compute a 
    working capital adjustment.
        (d) Evaluation criteria. (1) General. The contracting officer shall 
    consider elements that affect contract type risk such as--
        (i) Length of contract;
        (ii) Adequacy of cost projection data;
        (iii) Economic environment;
        (iv) Nature and extent of subcontracted activity;
        (v) Protection provided to the contractor under contract provisions 
    (e.g., economic price adjustment clauses);
        (vi) The ceilings and share lines contained in the incentive 
    provisions; and
        (vii) The rate, frequency, and risk to the contractor of 
    performance-based payments, if provided.
        (2) Mandatory. The contracting officer shall assess the extent to 
    which costs have been incurred prior to definitization of the contract. 
    When costs have been incurred prior to definitization, generally regard 
    the contract type risk to be in the low end of the designated range. If 
    a substantial portion of the costs have been incurred prior to 
    definitization, the contracting officer may assign a value as low as 0 
    percent regardless of contract type.
        (3) Above normal conditions. The contracting officer may assign a 
    higher than normal value when there is substantial contract type risk. 
    Conditions indicating higher than normal contract type risk are--
        (i) Efforts where there is minimal cost history;
        (ii) Long-term contracts without provisions protecting the 
    contractor, particularly when there is considerable economic 
    uncertainty;
        (iii) Incentive provisions that place a high degree of risk on the 
    contractor;
        (iv) Performance-based payments totaling less than the maximum
    
    [[Page 30471]]
    
    allowable amount(s) specified at FAR 32.1004(b)(2); or
        (v) An aggressive performance-based payment schedule that increases 
    risk.
        (4) Below normal conditions. The contracting officer may assign a 
    lower than normal value when the contract type risk is low. Conditions 
    indicating lower than normal contract type risk are:
        (i) Very mature product line with extensive cost history;
        (ii) Relatively short-term contracts;
        (iii) Contractual provisions that substantially reduce the 
    contractor's risk, e.g. economic price adjustment provisions;
        (iv) Incentive provisions that place a low amount of risk on the 
    contractor; and
        (v) A performance-based payment schedule that is routine with 
    minimal risk.
        (e) Costs financed. (1) Costs financed equal the total costs 
    multiplied by the percent of costs financed by the contractor.
        (2) Total costs may be reduced as appropriate when--
        (i) The contractor has little cash investment (e.g., subcontractor 
    progress payments are liquidated late in the period of performance); or
        (ii) Some costs are covered by special funding arrangements, such 
    as advance payments.
        (3) The portion financed by the contractor is generally the portion 
    not covered by progress payments, i.e., 100 percent minus the customary 
    progress payments rate. (For example, if a contractor receives progress 
    payments at 75 percent, the portion financed by the contractor is 25 
    percent. On contracts that provide progress payments to small business, 
    use the customary progress payment rate for large businesses.)
        (f) Contract length factor. (1) This is the period of time that the 
    contractor has a working capital investment in the contract. It--
        (i) Is based on the time necessary for the contractor to complete 
    the substantive portion of the work;
        (ii) Is not necessarily the period of time between contract award 
    and final delivery, as periods of minimal effort should be excluded;
        (iii) Should not include periods of performance contained in option 
    provisions when calculating the objective for the base period; and
        (iv) Should not, for multiyear contracts, include periods of 
    performance beyond that required to complete the initial year's 
    requirements.
        (2) The contracting officer--
        (i) Should use the following to select the contract length factor:
    
    ------------------------------------------------------------------------
                                                                  Contract
         Period to perform substantive portion (in months)         length
                                                                   factor
    ------------------------------------------------------------------------
    21 or less................................................           .40
    22 to 27..................................................           .65
    28 to 33..................................................           .90
    34 to 39..................................................          1.15
    40 to 45..................................................          1.40
    46 to 51..................................................          1.65
    52 to 57..................................................          1.90
    58 to 63..................................................          2.15
    64 to 69..................................................          2.40
    70 to 75..................................................          2.65
    76 or more................................................          2.90
    ------------------------------------------------------------------------
    
        (ii) Should develop a weighted average contract length when the 
    contract has multiple deliveries; and
        (iii) May use sampling techniques provided they produce a 
    representative result.
        (3) Example: A prospective contract has a performance period of 40 
    months with end items being delivered in the 34th, 36th, 38th and 40th 
    months of the contract. The average period is 37 months and the 
    contract length factor is 1.15.
    
    
    1815.404-471-4  Other Considerations.
    
        (a) Other Considerations may be included by the contracting officer 
    to account for special circumstances, such as contractor efficiencies 
    or unusual acceptance of contractual or program risks that are not 
    adequately addressed in the structured approach calculations described 
    in 1815.404-471-2 or 1815.404-4713. The total adjustment resulting from 
    Other Considerations may be positive or negative but in no case should 
    the total adjustment exceed +/-5 percent.
        (b) The contracting officer shall analyze and verify information 
    provided by the contractor that demonstrates that the special 
    circumstances being recognized under this section--
        (1) Provide substantial benefits to the Government under the 
    contract and/or overall program;
        (2) Have not been recognized in the structured approach 
    calculations; and
        (3) Represent unusual and innovative actions or acceptance of risk 
    by the contractor.
        (c) Examples of special circumstances include, but are not limited 
    to the following:
        (1) Consistent demonstration by the contractor of excellent past 
    performance within the last three years, with a special emphasis on 
    excellence in safety, may merit an upward adjustment of as much as 1 
    percent. Similarly, an assessment of poor past performance, especially 
    in the area of safety, may merit a downward adjustment of as much -1 
    percent. This consideration is especially important when negotiating 
    modifications or changes to an ongoing contract.
        (2) Extraordinary steps to achieve the Government's socio-economic 
    goals, environmental goals, and public policy goals established by law 
    or regulation that are sufficiently unique or unusual may merit an 
    upward adjustment of as much as .5 percent. Similarly, for non-
    participation in or violation of Federal programs, the contracting 
    officer may adjust the objective by as much as -.5 percent. However, 
    this consideration does not apply to the utilization of small 
    disadvantaged businesses. Incentives for use of these firms may only be 
    structured according to FAR 19.1203 and 19.1204(c).
        (3) Consideration of up to 2 percent should be given when contract 
    performance requires the expenditure of significant corporate capital 
    resources. Conversely, unusual requests for use of government 
    facilities and property may merit a downward adjustment of as much as 
    -2 percent.
        (4) Cost efficiencies arising from innovative product design, 
    process improvements, or integration of a life cycle cost approach for 
    the design and development of systems that minimize maintenance and 
    operations costs, that have not been recognized in Performance Risk or 
    Contract Type Risk, may merit an upward adjustment. This factor is 
    intended to recognize and reward improvements resulting from better 
    ideas and management that will benefit the Government in the contract 
    and/or program.
        (5) A negative consideration may be appropriate when the contractor 
    is expected to obtain spin-off benefits as a direct result of the 
    contract, for example, products with commercial application.
    
    
    1815.404-471-5  Facilities capital cost of money.
    
        (a) When facilities capital cost of money is included as an item of 
    cost in the contractor's proposal, it shall not be included in the cost 
    base for calculating profit/fee. In addition, a reduction in the 
    profit/fee objective shall be made in the amount equal to the 
    facilities capital cost of money allowed in accordance with FAR 31.205-
    10(a)(2).
        (b) CAS 417, cost of money as an element of the cost of capital 
    assets under construction, should not appear in contract proposals. 
    These costs are included in the initial value of a facility for 
    purposes of calculating depreciation under CAS 414.
    
    BILLING CODE 7510-01-P
    
    [[Page 30472]]
    
    Attachment: NASA FORM 634
    
        Note: This form will not appear in the CFR, but is provided for 
    information as an attachment to the preamble.
    [GRAPHIC] [TIFF OMITTED] TP08JN99.000
    
    
    [FR Doc. 99-14452 Filed 6-7-99; 8:45 am]
    BILLING CODE 7510-01-C
    
    
    

Document Information

Published:
06/08/1999
Department:
National Aeronautics and Space Administration
Entry Type:
Proposed Rule
Action:
Proposed rule.
Document Number:
99-14452
Dates:
Comments should be submitted on or before August 9, 1999.
Pages:
30468-30472 (5 pages)
PDF File:
99-14452.pdf
CFR: (1)
48 CFR 1815