  • Start Preamble

    AGENCY:

    Defense Acquisition Regulations System, Department of Defense (DoD).

    ACTION:

    Interim rule with request for comments.

    SUMMARY:

    DoD is issuing an interim rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to implement section 819 of the National Defense Authorization Act for Fiscal Year 2010. Section 819 places limitations on certain types of line items and contract options that may be included in contracts initially awarded pursuant to competitive solicitations. When the prohibition applies, it limits the dollar value, period of performance, and time for exercise of such contract line items or contract options.

    DATES:

    Effective Date: June 8, 2010.

    Comment Date: Comments on the interim rule should be submitted in writing to the address shown below on or before August 9, 2010, to be considered in the formation of the final rule.

    ADDRESSES:

    Submit comments identified by DFARS Case 2009-D034, using any of the following methods:

    Federal eRulemaking Portal: http://www.regulations.gov. Follow the instructions for submitting comments.

    E-mail: dfars@osd.mil. Include DFARS Case 2009-D034 in the subject line of the message.

    Fax: 703-602-0350.

    Mail: Defense Acquisition Regulations System, Attn: Ms. Meredith Murphy, OUSD(AT&L)DPAP(DARS), Room 3B855, 3060 Defense Pentagon, Washington, DC 20301-3060.

    Comments received generally will be posted without change to http://www.regulations.gov,, including any personal information provided.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Ms. Meredith Murphy, 703-602-1302.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    A. Background

    This DFARS case implements section 819 of the National Defense Authorization Act for Fiscal Year 2010 (Pub. L. 111-84, enacted October 28, 2009). Section 819 is entitled “Contract Authority for Advanced Component Development or Prototype Units.”

    Section 819 is intended to prevent a contract for new technology that is initially awarded as a result of competition from becoming a noncompetitive effort for the development of advanced components or the procurement of prototype units. To do so, section 819 places limitations on the (a) Dollar value, (b) period of performance, and (c) time for exercise of contract line items or contract options for advanced component development or procurement of prototype items. Specifically, the contract line item or contract option must be limited to the minimal amount of initial or additional prototype items that will allow for timely competitive solicitation and award of a follow-on development or production contract for those items. The term of the contract line item or contract option cannot be for a period longer than 12 months, and the dollar value of the work to be performed pursuant to the contract line item or contract option may not exceed the lesser of the amount that is three times the dollar value of the work previously performed under the contract or $20 million.

    Because the coverage is most likely to apply to major systems acquisitions, it has been added as a new DFARS subsection 234.005-1, entitled “Competition.” However, because the language applies to the exercise and content of certain contract options, a reference to 234.005-1 has been added to DFARS 217.202, entitled “Use of Options.”

    This is not a significant regulatory action and, therefore, is not subject to review under section 6(b) of Executive Order 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

    B. Regulatory Flexibility Act

    DoD does not expect that this interim rule will have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because the rule does not impose any additional requirements on small businesses. Therefore, an Initial Regulatory Flexibility Analysis has not been performed. DoD invites comments from small business concerns and other interested parties on the expected impact of this rule on small entities.

    DoD will also consider comments from small entities concerning the existing regulations in subparts affected by this rule in accordance with 5 U.S.C. 610. Interested parties must submit such comments separately and should cite 5 U.S.C. 610 (DFARS Case 2009-D034) in correspondence.

    C. Paperwork Reduction Act

    The Paperwork Reduction Act does not apply because the interim rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C., et seq.

    D. Determination To Issue an Interim Rule

    A determination has been made under the authority of the Secretary of Defense (DoD) that urgent and compelling circumstances exist to promulgate this interim rule without prior opportunity for public comments. This action is necessary because section 819 of the National Defense Authorization Act for Fiscal Year 2010 became effective upon enactment on October 28, 2009. Section 819 places limitations on certain types of line items and contract options that may be included in contracts initially awarded pursuant to competitive solicitations. In order to prevent a contract for new technology that is initially awarded as a result of competition from becoming a noncompetitive effort for the development of advanced components or procurement of prototype units, it is necessary to publish this rule as an interim rule prior to affording the public an opportunity to comment. However, pursuant to 41 U.S.C. 418b and FAR 1.501-3, DoD will consider public comments received in response to this interim rule in the formation of the final rule.

    Start List of Subjects Start Printed Page 32639

    List of Subjects in 48 CFR Parts 217 and 234

    • Government procurement
    End List of Subjects Start Signature

    Ynette R. Shelkin,

    Editor, Defense Acquisition Regulations System.

    End Signature Start Amendment Part

    Therefore, 48 CFR parts 217 and 234 are amended as follows:

    End Amendment Part Start Amendment Part

    1. The authority citation for 48 CFR parts 217 and 234 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 41 U.S.C. 421 and 48 CFR chapter 1.

    End Authority Start Part

    PART 217—SPECIAL CONTRACTING METHODS

    End Part Start Amendment Part

    2. Section 217.202 is revised as follows:

    End Amendment Part
    Use of options.

    (1) See PGI 217.202 for guidance on the use of options.

    (2) See 234.005-1 for limitations on the use of contract options for the provision of advanced component development or prototype of technology developed under the contract or the delivery of initial or additional prototype items.

    Start Part

    PART 234—MAJOR SYSTEM ACQUISITION

    End Part Start Amendment Part

    3. Section 234.005-1 is added to read as follows:

    End Amendment Part
    Competition.

    (1) A contract that is initially awarded from the competitive selection of a proposal resulting from a general solicitation may contain a contract line item or contract option for the provision of advanced component development or prototype of technology developed under the contract or the delivery of initial or additional prototype items if the item or a prototype thereof is created as the result of work performed under the contract only when it adheres to the following limitations:

    (i) The contract line item or contract option shall be limited to the minimal amount of initial or additional prototype items that will allow for timely competitive solicitation and award of a follow-on development or production contract for those items.

    (ii) The term of the contract line item or contract option shall be for not more than 12 months.

    (iii) The dollar value of the work to be performed pursuant to the contract line item or contract option shall not exceed the lesser of—

    (A) The amount that is three times the dollar value of the work previously performed under the contract; or

    (B) $20 million.

    (2) A contract line item or contract option may not be exercised under this authority after September 30, 2014.

    End Supplemental Information

    [FR Doc. 2010-13524 Filed 6-7-10; 8:45 am]

    BILLING CODE 5001-08-P

Document Information

Comments Received:
0 Comments
Published:
06/08/2010
Department:
Defense Acquisition Regulations System
Entry Type:
Rule
Action:
Interim rule with request for comments.
Document Number:
2010-13524
Pages:
32638-32639 (2 pages)
Topics:
Government procurement
PDF File:
2010-13524.pdf
CFR: (2)
48 CFR 217.202
48 CFR 234.005-1