94-16066. Colorado Interstate Gas Company, et al.; Natural Gas Certificate Filings  

  • [Federal Register Volume 59, Number 126 (Friday, July 1, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-16066]
    
    
    [[Page Unknown]]
    
    [Federal Register: July 1, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP94-604-000, et al.]
    
     
    
    Colorado Interstate Gas Company, et al.; Natural Gas Certificate 
    Filings
    
    June 24, 1994.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. Colorado Interstate Gas Company
    
    [Docket No. CP94-604-000]
    
        Take notice that on June 15, 1994, Colorado Gas Interstate Gas 
    Company (CIG), Post Office Box 1087, Colorado Springs, Colorado 80944, 
    filed in Docket No. CP94-604-000 a request pursuant to 
    Sec. Sec. 157.205 and 157.211 of the Commission's Regulations under the 
    Natural Gas Act (18 CFR 157.205 and 157.211) for authorization to 
    construct a new delivery facility pursuant to CIG's blanket certificate 
    issued in Docket No. CP83-21-000 to implement an interruptible 
    transportation service for Meridan Oil, Inc. (Meridan), pursuant to 
    Section 7(c) of the Natural Gas Act, all as more fully set forth in the 
    request which is on file with the Commission and open to public 
    inspection.
        CIG proposes a new delivery facility to be located in Las Animas 
    County, Colorado. CIG states the facility will consist of a two-inch 
    meter run and facilities appurtenant thereto for the delivery of fuel 
    gas to Meridan for the start up of a compressor station. CIG indicates 
    it will transport approximately 200 Mcf per day on an interruptible 
    basis for Meridian under its Part 284 blanket certificate.
        CIG indicates its tariff does not prohibit the addition of new 
    delivery points. Further, CIG states the proposed facility will not 
    have an impact on its peak day or annual deliveries.
        Comment date: August 8, 1994, in accordance with Standard Paragraph 
    G at the end of this notice.
    
    2. NorAm Gas Transmission Company
    
    [Docket No. CP94-612-000]
    
        Take notice that on June 17, 1994, NorAm Gas Transmission Company 
    (NGT), 1600 Smith Street, Houston, Texas 77002, filed in Docket No. 
    CP94-612-000 an abbreviated application pursuant to Section 7(b) of the 
    Natural Gas Act, as amended, and Sec. Sec.  157.7 and 157.18 of the 
    Federal Energy Regulatory Commission's (Commission) regulations 
    thereunder, for permission to abandon a firm transportation service for 
    Arkansas Western Gas Company, (Arkansas Western), all as more fully set 
    forth in the application which is on file with the Commission and open 
    to public inspection.
        NGT states that it proposes to abandon a transportation service 
    originally authorized by Commission order issued October 23, 1956, in 
    Docket No. G-10591. NGT indicates that under the arrangement with 
    Arkansas Western, NGT would provide for transportation for Arkansas 
    Western from a point on Texas Gas Transmission Corporation (Texas Gas) 
    lines near Lynchburg, Mississippi, to a point near Turrell, Arkansas, 
    and exchange of gas during temporary periods of emergency. By letter 
    dated March 30, 1994, both parties have agreed to the termination of 
    the agreement. NGT indicates that no facilities are to be abandoned.
        Comment date: July 15, 1994, in accordance with Standard Paragraph 
    F at the end of this notice.
    
    3. Northwest Pipeline Corporation
    
    [Docket Nos. CP93-613-001]
    
        Take notice that on June 14, 1994, Northwest Pipeline Corporation 
    (Northwest), 295 Chipeta Way, Salt Lake City, Utah 84158, filed in 
    Docket No. CP93-613-001, pursuant to Sections 7(b) and 7(c) of the 
    Natural Gas Act, an amendment to its August 2, 1993 application in 
    Docket No. CP93-613-000. This amendment revises facilities proposed to 
    be constructed and operated to provide 102,000 Dth equivalent per day 
    of new long-term, firm transportation service to Northwest Natural Gas 
    Company (Northwest Natural) from Stanfield, Oregon to various delivery 
    points on Northwest's Grants Pass Lateral, all as more fully set forth 
    in the amendment which is on file with the Commission and open for 
    public inspection.
        Northwest says the facilities originally proposed to provide this 
    new service now have been redesigned to reflect:
        (1) elimination of 11.3 miles of 30-inch mainline loop and 
    associated cross-over taps because of the availability of additional 
    existing capacity for this project resulting from the upcoming 
    termination of a firm transportation agreement with Columbia Power 
    Associates, LP (Columbia Power).
        (2) addition of a new pipeline loop on the Grants Pass Lateral as a 
    result of correcting an error in the existing pipeline specifications 
    used in the original flow studies; and
        (3) various refinements to the scope of work originally proposed 
    for the remaining segments of the project which were identified during 
    the on-going detailed design process.
        Northwest now amends its application to request certificate 
    authority to construct and operate the following facilities:
         5,700 horsepower of additional compression, with 
    appurtenances, at one existing compressor station;
         13.2 miles of 20-inch pipeline loop, on new right-of-way 
    (deviating from the existing Grants Pass Lateral), near Gresham, 
    Oregon;
         1.3 miles of 20-inch pipeline loop on the Grants Pass 
    Lateral near Salem, Oregon;
         one new meter station and one cross-over tap to an 
    existing meter station on the new Gresham Loop; and
         upgrades of six existing meter stations on the Grants Pass 
    Lateral.
        Northwest also requests abandonment approval for certain existing 
    facilities proposed to be replaced by upgraded facilities at the 
    aforementioned six meter stations on the Grants Pass Lateral.
        Northwest says the estimated cost of the Northwest Natural 
    Expansion Project has been revised and reduced from the original $45.0 
    million estimate to $42.7 million. Northwest further says that the 
    revised estimate includes an $8.6 million cost increase for the Gresham 
    Loop attributable to a reassessment of the extensive right-of-way, 
    environmental and construction complications associated with installing 
    this loop.
        Northwest estimates that it will cost approximately $152,000 to 
    remove the metering facilities proposed to be abandoned. Northwest 
    further estimates that the total cost of the facilities proposed to be 
    abandoned is $59,204 with an estimated salvage value of $2,400.
        Northwest requests any waivers of the ``Right-of-First-Refusal; 
    Posting of Pipeline Capacity'' procedures set forth in Section 25 of 
    the General Terms and Conditions of its FERC Gas Tariff, Third Revised 
    Volume No. 1, which may be necessary to allow the capacity made 
    available by the expiration of the Columbia Power agreement to be 
    reserved and used for the Northwest Natural Expansion Project.
        Northwest proposes to finance the construction cost of this 
    expansion with short-term bank borrowings. Northwest proposes to 
    convert the short-term bank borrowings to an appropriate mix of long-
    term debt and equity which will provide an overall corporate capital 
    structure of approximately 45% long-term debt and 55% equity.
        Northwest submits that, in recognition of the benefits of the 
    proposed Northwest Natural Expansion Project to its existing system and 
    to facilitate prompt resolution of the rate issues pertinent to this 
    proceeding, it no longer requests either conditional approval of 
    alternative initial rates or preapproval of specific future rate case 
    treatment for this project.
        Northwest says the Northwest Natural Expansion Agreement is subject 
    to Northwest's open-access Rate Schedule TF-1 and will be implemented 
    under Northwest's blanket transportation certificate and Subpart G of 
    Part 284. Northwest requests approval for initial rates under the 
    Northwest Natural Expansion Agreement to be its maximum Rate Schedule 
    TF-1 rates, including applicable surcharges and fuel reimbursement in-
    kind percentages, which are in effect at the time service commences 
    under the agreement.
        Northwest avers that any issues which may be raised concerning the 
    potential rate impact of this project and the appropriate future rate 
    design for service under the Northwest Natural Expansion Agreement 
    should be deferred for consideration in the first rate proceeding where 
    Northwest files to include its expansion project costs in rates. 
    Northwest further states that in the first general rate proceeding in 
    which Northwest seeks to include the costs of the Northwest Natural 
    Expansion Project in rates, Northwest intends to revise its rolled-in 
    system rate to reflect the additional costs and billing determinants 
    resulting from this project.
        Comment date: July 15, 1994, in accordance with with the first 
    paragraph of Standard Paragraph F at the end of this notice.
    
    4. NorAm Gas Transmission Company
    
    [Docket No. CP94-617-000]
    
        Take notice that on June 20, 1994, NorAm Gas Transmission Company 
    (NGT), 1600 Smith St., Houston, Texas 77002, filed in Docket No. CP94-
    617-000 a request pursuant to Secs. 157.205, 157.211, and 157.212 of 
    the Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 
    157.211, and 157.212) for authorization to construct and operate 
    certain facilities in Louisiana under NGT's blanket certificate issued 
    in Docket No. CP82-384-000, et al., pursuant to Section 7 of the 
    Natural Gas Act, all as more fully set forth in the request that is on 
    file with the Commission and open to public inspection.
        NGT proposes to construct and operate a new 2-inch commercial tap 
    for deliveries to Arkansas Louisiana Gas Company's (ALG) new customer, 
    Winford Company, Inc., in Bienville Parish, Louisiana. The volume of 
    gas to be delivered through this tap is approximately 27,900 Mcf 
    annually and 900 Mcf on a peak day. The construction cost is estimated 
    at $2,000 and will be reimbursed by ALG.
        Comment date: August 8, 1994, in accordance with Standard Paragraph 
    G at the end of this notice.
    
    5. Columbia Gulf Transmission Co.
    
    [Docket No. CP94-620-000]
    
        Take notice that on June 21, 1994, Columbia Gulf Transmission 
    Company (Columbia Gulf), 1700 MacCorkle Avenue, S. E., Charleston, West 
    Virginia 25314-1599, filed in Docket No. CP94-620-000 a request 
    pursuant to Sec.  157.205 of the Commission's Regulations to abandon by 
    sale to Stingray Pipeline Company (Stingray) certain offshore 
    facilities in West Cameron Block 146, offshore Louisiana (Block 146) 
    under Columbia Gulf's blanket certificate issued in Docket No. CP83-
    496-000, pursuant to Section 7 of the Natural Gas Act, all as more 
    fully set forth in the request on file with the Commission and open to 
    public inspection.
        Columbia Gulf proposes to abandon 950 feet (0.18 mile) of 6-inch 
    pipeline extending from Block 146 ``A'' platform to a subsea valve on 
    National Gas Pipeline Company of America's pipeline, which Stingray 
    currently leases, in Block 146; a 6-inch riser; and a dual 4-inch meter 
    station and appurtenant facilities on the Block 146 ``A'' platform. 
    Columbia Gulf states that Stingray would acquire the facilities under 
    its blanket certificate in Docket No. CP91-1505-000 at a purchase cost 
    of $126,500. Columbia Gulf states that Elf Exploration, Inc. and 
    Phillips Petroleum Company, the sole producers/shippers on these 
    facilities have consented to the abandonment by sale to Stingray.
        Comment date: August 8, 1994, in accordance with Standard Paragraph 
    G at the end of this notice.
    
    6. Northwest Pipeline Corporation
    
    [Docket No. CP93-673-001]
    
        Take notice that on June 15, 1994, Northwest Pipeline Corporation 
    (Northwest), 295 Chipeta Way, Salt Lake City, Utah 84158, filed in 
    Docket No. CP93-673-001, pursuant to Sections 7(b) and 7(c) of the 
    Natural Gas Act, an amendment to its August 18, 1993 application in 
    Docket No. CP93-673-000. This amendment reflects the downsizing of 
    Northwest's originally proposed $228.6 million, 258,488 Dth per day 
    equivalent system Expansion II Project to a $67.7 million, 62,175 Dth 
    per day equivalent project, all as more fully set forth in the 
    amendment which is on file with the Commission and open for public 
    inspection.
        Northwest amends its application to request certificate authority 
    to construct and operate, as its primary design case, the following 
    facilities in the states of Washington, Oregon, and Idaho to implement 
    its downsized project for an additional 62,175 Dth per day of new firm 
    mainline expansion:
         19.2 miles of 24-inch loop pipeline in three segments on 
    Northwest's mainline in Idaho and Wyoming;
         12.9 miles of new 20-inch loop pipeline in three segments;
         13.2 miles of new 30-inch pipeline loop in place of the 
    20-inch loop (Gresham Loop) previously proposed in the Northwest 
    Natural Expansion Project, Docket No. CP93-613-000;
         two new customer-specific delivery laterals: 8.1 miles of 
    12-inch and 16-inch pipeline for the Weyerhaeuser Lateral and 0.2 mile 
    of 12-inch pipeline for the Springfield Lateral;
         a total of 9,120 standard sea-level horsepower of 
    additional compression at three existing compressor stations;
         modifications or upgrades of appurtenant facilities at 11 
    existing compressor stations;
         three new meter stations; and
         crossover taps to new loop lines for three existing meter 
    stations.
        Northwest also requests abandonment approval for certain existing 
    facilities proposed to be replaced by upgraded facilities at six 
    existing compressor stations and one meter station.
        Northwest says the certificate authority requested in this 
    Northwest Expansion II Project assumes Northwest has received 
    Commission approval to construct and operate the prerequisite 
    facilities proposed in the Northwest Natural Expansion Project, in 
    Docket No. CP93-613. If Northwest does not receive approval to 
    construct the Northwest Natural Expansion Project in conjunction with 
    or before the expansion project herein, Northwest alternatively 
    requests that the proposed certificate authorization reflect the 
    following changes from the primary design case facilities:
         eliminate 5,700 standard sea-level horsepower of 
    additional compression proposed at one existing compressor station;
         add a crossover tap from an existing meter station to the 
    Gresham Loop;
         install 13.2 mile 24-inch pipeline segment, instead of 
    upgrading a loop (Gresham Loop) from 20-inch to 30-inch; and
         an additional 1.3 miles of 20-inch pipeline loop on the 
    Grants Pass Lateral.
        Northwest estimates the revised total cost for this primary design 
    Northwest System Expansion II Project to be $67.7 million. Northwest 
    further estimates that it will cost approximately $105,300 to remove 
    the facilities proposed to be abandoned. Northwest estimates that the 
    total original cost of the facilities proposed to be abandoned is 
    $604,641 with an estimated salvage value of $6,000. Northwest says 
    about $10.9 million of costs for the Weyerhaeuser and Springfield 
    Utility Board Laterals will be paid for incrementally by specific 
    shippers.
        Northwest says it has requested, as part of its proposal in the 
    Northwest Expansion II Project in Docket No. CP93-673, to upgrade the 
    20-inch Gresham loop, requested in the Northwest Natural Expansion 
    Project (Docket No. CP93-613), to a 30-inch pipeline loop. Northwest 
    further says, if the Commission approves the upgrade from 20-inch to 
    30-inch and approves the construction of all facilities in both 
    projects concurrently, it will allocate to the Northwest Natural 
    Expansion Project those costs attributable to constructing a 20-inch 
    loop, and the Northwest Expansion II Project will be allocated costs 
    attributable to increasing the pipe diameter from 20-inch to 30-inch.
        Northwest indicates that the net estimated cost of the alternative 
    facility case (no prerequisite Northwest Natural Expansion Project and 
    excluding the Weyerhaeuser and Springfield Utility Board Laterals) is 
    $70.2 million.
        Northwest proposes to finance the construction cost of this 
    expansion with short-term bank borrowings. Northwest further proposes 
    to convert the short-term bank borrowings to an appropriate mix of 
    long-term debt and equity which will provide an overall corporate 
    capital structure of approximately 45% long-term debt and 55% equity.
        Northwest says it originally requested authorization in Docket No. 
    CP93-673-000 to construct facilities necessary to expand its mainline 
    and various laterals to accommodate 258,488 Dth per day of new firm 
    service under 31 long-term agreements with 26 shippers. Northwest 
    further says, as a result of a one-time contract termination/reduction 
    option provided to the expansion shippers, coupled with an open season 
    to solicit replacement shippers, 19 contracts for a total of 134,063 
    Dth per day were terminated, 8 contracts were amended to reduce 
    contract demands by a total of 62,500 Dth per day, 4 contracts did not 
    change, and one new contract was executed for 250 Dth per day.
        Northwest says it now has 13 long-term firm contracts (primary term 
    of 15 years from the in-service date and year to year thereafter) under 
    Northwest's TF-1 Rate Schedule with 12 expansion shippers for a total 
    of 62,175 Dth per day in mainline contract demand.
        Northwest submits that, in recognition of the benefits of this 
    proposed Northwest Expansion II Project to its existing system and to 
    facilitate prompt resolution of the rate issues pertinent to this 
    proceeding, it no longer requests pre-approval of specific future rate 
    case treatment for this project.
        Northwest says its Expansion II Agreements with the shippers are 
    subject to Northwest's open-access Rate Schedule TF-1 and will be 
    implemented under Northwest's blanket transportation certificate and 
    Subpart G of Part 284. Northwest requests approval for initial rates 
    for mainline service under the expansion agreements to be its maximum 
    Rate Schedule TF-1 rates, including applicable surcharges and fuel 
    reimbursement in-kind percentages, which are in effect at the time 
    service commences under the agreements.
        Northwest avers that any issues which may be raised concerning the 
    potential rate impact of this project and the appropriate future rate 
    design for service under the Expansion II Agreements should be deferred 
    for consideration in the first rate proceeding where Northwest files to 
    include its expansion project costs in rates. Northwest says it intends 
    to revise its rolled-in system rate to reflect the additional costs and 
    billing determinants resulting from this project in the first general 
    rate proceeding in which Northwest seeks to include the costs of this 
    expansion in rate base.
        In addition to using existing Rate Schedule TF-1 rolled-in rates as 
    its initial rates for the Expansion II mainline services, Northwest 
    requests approval to incrementally recover the costs of the two 
    proposed, customer-specific delivery laterals by assessing Facilities 
    Cost-of-Service charges to the applicable shippers in accordance with 
    the Facilities Reimbursement provisions of its tariff. Northwest 
    proposes to initially charge Weyerhaeuser Company and Longview 
    Cogeneration Company, affiliate and assignee of Mission Energy, 
    $115,936 per month each for service on the proposed Weyerhaeuser 
    Lateral and to initially charge Springfield Utility Board $5,140 per 
    month for service on the Springfield Utility Board Lateral.
        Comment date: July 15, 1994, in accordance with the first paragraph 
    of Standard Paragraph F at the end of this notice.
    
    Standard Paragraphs
    
        F. Any person desiring to be heard or to make any protest with 
    reference to said application should on or before the comment date, 
    file with the Federal Energy Regulatory Commission, Washington, D.C. 
    20426, a motion to intervene or a protest in accordance with the 
    requirements of the Commission's Rules of Practice and Procedure (18 
    CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act 
    (18 CFR 157.10). All protests filed with the Commission will be 
    considered by it in determining the appropriate action to be taken but 
    will not serve to make the protestants parties to the proceeding. Any 
    person wishing to become a party to a proceeding or to participate as a 
    party in any hearing therein must file a motion to intervene in 
    accordance with the Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to the jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and Procedure, a hearing will be 
    held without further notice before the Commission or its designee on 
    this application if no motion to intervene is filed within the time 
    required herein, if the Commission on its own review of the matter 
    finds that a grant of the certificate and/or permission and approval 
    for the proposed abandonment are required by the public convenience and 
    necessity. If a motion for leave to intervene is timely filed, or if 
    the Commission on its own motion believes that a formal hearing is 
    required, further notice of such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for applicant to appear or be represented at the 
    hearing.
        G. Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 94-16066 Filed 6-30-94; 8:45 am]
    BILLING CODE 6717-01-P
    
    
    

Document Information

Published:
07/01/1994
Department:
Energy Department
Entry Type:
Uncategorized Document
Document Number:
94-16066
Dates:
August 8, 1994, in accordance with Standard Paragraph G at the end of this notice.
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: July 1, 1994, Docket No. CP94-604-000, et al.