01-17187. Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments  

  • Start Preamble July 3, 2001.

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection:

    a. Type of Application: Preliminary Permit.

    b. Project No.: 12050-000.

    c. Date filed: June 11, 2001.

    d. Applicant: Symbiotics, LLC.

    e. Name of Project: Pine Creek Project.

    f. Location: On Pine Creek, in Lincoln County, Wyoming. The project would be located on U.S. Forest Service Lands within the Bridger National Forest.

    g. Filed Pursuant to: Federal Power Act, 16 USC §§ 791(a)-825(r).

    h. Applicant Contact: Mr. Brent L. Smith, President, Northwest Power Services, Inc., P.O. Box 535, Rigby, ID 83442, (208) 745-8630.

    i. FERC Contact: Robert Bell, (202) 219-2806.

    j. Deadline for filing motions to intervene, protests and comments: 60 days from the issuance date of this notice.

    All documents (original and eight copies) should be filed with: David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's web site at http://www.ferc.gov under the link to the User's Guide. If you have not yet established an account, you will need to create a new account by clicking on “Login to File” and then “New User Account.”Start Printed Page 35964

    Please include the project number (P-12050-000) on any comments or motions filed.

    The Commission's Rules of Practice and Procedure require all interveners filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    k. Description of Project: The proposed project would consist of: (1) A proposed 30-foot-long, 10-foot-high earth filled dam, (2) a proposed impoundment having a surface area of 1 acre with negligible storage and normal water surface elevation of 7,400 feet msl, (3) a proposed intake structure, (4) a proposed 15,600-foot-long, 24-inch-diameter steel penstock; (5) a proposed powerhouse containing two generating units with a total installed capacity of 1.8 MW, (6) a proposed 5-mile-long 15 kV transmission line, and (7) appurtenant facilities.

    The project would have an annual generation of 9.9 GWh that would be sold to a local utility.

    l. A copy of the application is available for inspection and reproduction at the Commission's Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 208-1371. This filing may be viewed on the web at http://www.ferc.gov using the “RIMS” link, select “Docket #” from the RIMS Menu and follow the instructions (please call (202) 208-2222 for assistance). A copy is also available for inspection and reproduction at the address in item h above.

    m. Preliminary Permit—Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36.

    n. Preliminary Permit—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36.

    o. Notice of intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice.

    p. Proposed Scope of Studies under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project.

    q. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.

    r. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title “COMMENTS”, “NOTICE OF INTENT TO FILE COMPETING APPLICATION”, “COMPETING APPLICATION”, “PROTEST”, “MOTION TO INTERVENE”, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission's regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application.

    s. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency's comments must also be sent to the Applicant's representatives.

    Start Signature

    David P. Boergers,

    Secretary.

    End Signature End Preamble

    [FR Doc. 01-17187 Filed 7-9-01; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
07/10/2001
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
01-17187
Pages:
35963-35964 (2 pages)
EOCitation:
of 2001-07-03
PDF File:
01-17187.pdf