97-18185. Colorado Interstate Gas Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 62, Number 133 (Friday, July 11, 1997)]
[Notices]
[Page 37214]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-18185]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP97-610-000]
Colorado Interstate Gas Company; Notice of Request Under Blanket
Authorization
July 7, 1997.
Take notice that on June 27, 1997, Colorado Interstate Gas Company
(CIG), P.O. Box 1087, Colorado Springs, Colorado 80944 filed in Docket
No. CP97-610-000 a request pursuant to Sections 157.205 and 157.211 of
the Commission's Regulations under the Natural Gas Act (18 CFR 157.205
and 157.211) for authorization to construct a new meter station at an
existing delivery point in Douglas County, Colorado, under CIG's
blanket certificate issued in Docket No. CP83-21-000, pursuant to
Section 7(c) of the Natural Gas Act, all as more fully set forth in the
request that is on file with the Commission and open to public
inspection.
CIG proposes to construct a new meter station at its existing Bayou
Gulch delivery point, located near Castle Rock, in Douglas County,
Colorado where gas is delivered to UtiliCorp United Incorporated
(UtiliCorp). CIG states that the existing delivery point to UtiliCorp
is a 2 inch side tap delivery facility on its 20-inch main transmission
line that was constructed pursuant to a Prior Notice filing in Docket
No. CP84-762-000. CIG explains that currently UtiliCorp owns and
maintains the measurement equipment at the Bayou Gulch delivery point.
CIG claims that by installing CIG owned and operated measurement
facilities at this point, it will be possible to accurately measure
volumes being supplied to this no-noticed customer. CIG proposes to
install a Roots Gas Meter, a solar powered remote operating controler,
and telemetry so it will know promptly if there are problems with gas
flow at this point that serves a housing development.
CIG states that the estimated cost of the propposed facilities is
approximately $36,300. Additionally, CIG indicates that it has obtained
all required environmental clearances.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursaunt to Sec. 157.205 of the
Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the
request. If no protest is filed within the time allowed therefor, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 97-18185 Filed 7-10-97; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 07/11/1997
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 97-18185
- Pages:
- 37214-37214 (1 pages)
- Docket Numbers:
- Docket No. CP97-610-000
- PDF File:
-