98-18496. East Tennessee Natural Gas Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 63, Number 133 (Monday, July 13, 1998)]
[Notices]
[Page 37550]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-18496]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP98-636-000]
East Tennessee Natural Gas Company; Notice of Request Under
Blanket Authorization
July 7, 1998.
Take notice that on June 26, 1998, East Tennessee Natural Gas
Company (East Tennessee), P.O. Box 2511, Houston, Texas 77252-2511,
filed in Docket No. CP98-636-000 a request pursuant to Sections 157.205
and 157.212 of Commission's Regulations under the Natural Gas Act (18
CFR 157.205, 157.212) for authorization to operate as jurisdictional an
existing delivery point facility that was constructed under Section
311(a) of the Natural Gas Policy Act of 1978 (NGPA), under the East
Tennessee's blanket certificate issued in Docket No. CP82-412-000
pursuant to Section 7 of Natural Gas Act, all as more fully set forth
in the request on file with the Commission and open to public
inspection.
East Tennessee states that it has recently constructed a delivery
point (Rockwood Meter Station) under Section 311(a) of the NGPA for use
in the transportation of natural gas under Subpart B of Part 284 of the
Commission's regulations. Granting the requested authorization will
enable East Tennessee to fully utilize this facility for all
transportation services, pursuant to Section 311 of the NGPA and
Section 7 of the NGA and will increased the transportation options of
customers on East Tennessee's system.
East Tennessee states that delivery volumes through the existing
delivery point would not impact its peak day and annual deliveries;
that the proposed activity is not prohibited by its existing tariff;
and that it has sufficient capacity to accommodate the proposed changes
without detriment or disadvantage to its other customers.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
David P. Boergers,
Acting Secretary.
[FR Doc. 98-18496 Filed 7-10-98; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 07/13/1998
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 98-18496
- Pages:
- 37550-37550 (1 pages)
- Docket Numbers:
- Docket No. CP98-636-000
- PDF File:
-
98-18496.pdf