98-18960. Duke Energy Corporation; Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing  

  • [Federal Register Volume 63, Number 136 (Thursday, July 16, 1998)]
    [Notices]
    [Pages 38433-38435]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-18960]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-269, 50-270, and 50-287]
    
    
    Duke Energy Corporation; Notice of Consideration of Issuance of 
    Amendments to Facility Operating Licenses, Proposed No Significant 
    Hazards Consideration Determination, and Opportunity for a Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of amendments to Facility Operating License Nos. 
    DPR-38, DPR-47, and DPR-55, issued to Duke Energy Corporation (the 
    licensee), for operation of the Oconee Nuclear Station, Units 1, 2, and 
    3, respectively, located in Seneca, South Carolina.
        If approved, the proposed amendments would allow temporary 
    noncompliance with the Penetration Room Ventilation System air flow 
    surveillance requirements of Technical Specification (TS) 4.5.4.1.b.1 
    until modifications can be completed to support testing in accordance 
    with ANSI Standard N510-1975, as required by the TSs. These 
    modifications are scheduled to be completed on all three units by 
    August 30, 1998.
        Oconee TS 4.5.4.1.b.1 requires that every 18 months the Penetration 
    Room Ventilation System fans be demonstrated to operate at design flow 
    (+/-10 percent) when tested in accordance with ANSI Standard N510-1975. 
    ANSI Standard N510-1975 requires that a pitot tube velocity-traverse 
    method be used in accordance with Section 9 of the American Conference 
    of Government Industrial Hygienists Industrial Ventilation 
    requirements. The flow measurement method that has been used since 
    original construction uses installed orifice plates to measure the air 
    flow.
        However, during a Safety System Engineering Inspection at Oconee 
    for the Control Room Ventilation System (CRVS) and Penetration Room 
    Ventilation System (PRVS), the NRC identified a violation that 
    indicated that the PRVS fans were not tested in accordance with the TSs 
    and ANSI Standard N510-1975. This violation was included in Inspection 
    Report Nos. 50-269/98-03, 50-270/98-03, and 50-287/09-03 dated May 4, 
    1998. By letter dated June 4, 1998, the licensee denied the violation 
    based on a belief that the use of the orifice plates met the 
    requirements of the TSs and the ANSI standard. As part of the review of 
    this issue, the licensee conducted flow measurement tests using a pitot 
    tube array and attempted (unsuccessfully) to locate calibration data 
    for the orifices. The licensee was unable to develop an alternate 
    method to measure flow that was reliable.
        By letter dated July 6, 1998, the NRC informed the licensee that 
    its denial of the violation was rejected. Consequently, the licensee 
    entered TS 3.0, which required that all three units be in the hot 
    shutdown condition within 12 hours, and requested that a Notice of 
    Enforcement Discretion (NOED) be granted. The NOED was issued on July 
    8, 1998, and will be effective until the proposed amendments that were 
    submitted on July 8, 1998, are processed. Since the proposed amendments 
    are designed to complete the review process and implement the TS 
    changes, pursuant to the NRC's policy regarding exercising discretion 
    for an operating facility set out in Section VII.c of the ``General 
    Statement of Policy and Procedures for NRC Enforcement Actions'' 
    (Enforcement Policy), NUREG-1600, and be effective for the period until 
    the issuance of the related TS amendments, these circumstances require 
    that the amendments be processed under exigent circumstances.
        Before issuance of the proposed license amendments, the Commission 
    will have made findings required by the Atomic Energy Act of 1954, as 
    amended (the Act) and the Commission's regulations.
        Pursuant to 10 CFR 50.91(a)(6) for amendments to be granted under 
    exigent circumstances, the NRC staff must determine that the amendment 
    request involves no significant hazards consideration. Under the 
    Commission's regulations in 10 CFR 50.92, this means that operation of 
    the facility in accordance with the proposed amendments would not (1) 
    involve a significant increase in the probability or consequences of an 
    accident previously evaluated; or (2) create the possibility of a new 
    or different kind of accident from any accident previously evaluated; 
    or (3) involve a significant reduction in a margin of safety. As 
    required by 10 CFR 50.91(a), the licensee has provided its analysis of 
    the issue of no significant hazards consideration, which is presented 
    below:
    
        [This proposed change has been evaluated against the standards 
    in 10 CFR 50.92 and has been determined to involve no significant 
    hazards, in that operation of the facility in accordance with the 
    proposed amendments would not:]
        1. Involve a significant increase in the probability or 
    consequences of an accident previously evaluated:
        This proposed change does not increase the probability of an 
    accident evaluated in the SAR [Safety Analysis Report] because:
        This evaluation addresses the potential impact of revising 
    Technical Specification 4.5.4.1.b.1 to include a note to allow a 
    temporary noncompliance with this surveillance requirement until 
    August 30, 1998, to complete the necessary modifications to enable 
    flow testing in accordance with ANSI N510-1975.
        As described in the technical justification (Attachment 3 [of 
    the July 8, 1998, submittal]), the use of orifice plates in the 
    Oconee Units 1, 2, and 3 Penetration Room Ventilation Systems 
    (PRVSs) to measure the flow from the PRVS fans, in lieu of ANSI 
    N510-1975 requirements, does not increase the probability of an 
    accident evaluated in the SAR because this condition is not an 
    accident initiator. There is no physical change to any plant 
    structures, systems, or components (SSCs) or operating procedures. 
    Neither electrical power systems, nor important to safety mechanical 
    SSCs will be adversely affected. The PRVS has been evaluated as 
    operable for normal and accident conditions. There are no shutdown 
    margin, reactivity management, or fuel integrity concerns. There is 
    no increase in accident initiation likelihood, therefore analyzed 
    accident scenarios are not impacted.
        This proposed change does not increase the probability of a 
    malfunction of equipment important to safety evaluated in the SAR 
    because:
        As described in the technical justification, the use of orifice 
    plates which are currently used in Oconee Units 1, 2, and 3 to 
    measure the flow from the PRVS fans, in lieu of ANSI N510-1975 
    requirements, does not increase the probability of a malfunction of 
    equipment important to safety. This activity does not physically 
    change or modify any plant system, structure, or component. The PRVS 
    is QA [quality assurance] condition 1 (QA-1) and is required to 
    filter reactor building leakage which enters the East and West 
    Penetration Rooms. This activity does not change any test 
    procedures. Nothing is being done to inhibit the integrity or 
    function of the PRVS. No valve manipulations, electrical alignments, 
    or system configurations are required.
        This change does not increase the consequences of an accident 
    evaluated in the SAR because:
        This activity will not adversely affect the ability to mitigate 
    any SAR described accidents. The PRVS flow is within the system 
    design limits as measured by the orifice plates. In addition, Duke 
    [Duke Energy Corporation] has performed bounding analyses which 
    demonstrate that the carbon filter efficiency is still within the 
    Technical Specification limits at higher flow rates. Therefore, 
    Oconee Units 1, 2, and 3 will meet system design requirements for 
    the PRVS. There is no adverse impact on containment integrity, 
    radiological release pathways, fuel
    
    [[Page 38434]]
    
    design, filtration systems, main steam relief valve setpoints, or 
    radwaste systems.
        This change does not increase the consequences of a malfunction 
    of equipment important to safety evaluated in the SAR because:
        No safety related or important to safety equipment necessary to 
    place or maintain the plant in safe shutdown condition will be 
    impacted by allowing a temporary noncompliance with this 
    surveillance requirement until August 30, 1998, to complete flow 
    testing in accordance with ANSI N510-1975. As described in the 
    technical justification, the use of orifice plates which are 
    currently used in Oconee Units 1, 2, and 3 to measure the flow from 
    the PRVS fans, in lieu of ANSI N510-1975 requirements, does not 
    increase the consequences of a malfunction of equipment important to 
    safety. The PRVS flow is within the system design limits as measured 
    by the orifice plates. In addition, Duke has performed bounding 
    analyses which demonstrate that the carbon filter efficiency is 
    still within the Technical Specification limits at higher flow 
    rates. Therefore, Oconee Units 1, 2, and 3 will meet system design 
    requirements for the PRVS. There is no adverse impact on containment 
    integrity, radiological release pathways, fuel design, filtration 
    systems, main steam relief valve setpoints, or radwaste systems.
        (2) Create the possibility of a new or different kind of 
    accident from any kind of accident previously evaluated:
        This change does not create the possibility for an accident of a 
    different type than any evaluated in the SAR because:
        There is no increased risk of unit trip, or challenge to the 
    Reactor Protection System (RPS) or other safety systems. There is no 
    physical effect on the plant, i.e. none on Reactor Coolant System 
    (RCS) temperature, boron concentration, control rod manipulations, 
    core configuration changes, and no impact on nuclear 
    instrumentation. There is no increased risk of a reactivity 
    excursion. No new failure modes or credible accident scenarios are 
    postulated from this activity.
        This change does not create the possibility for a malfunction of 
    a different type than any evaluated in the SAR because:
        There is no physical change to the plant SSCs or operating 
    procedures. This change does not involve any plant changes, 
    electrical lineups, or valve manipulations. Analyses have been 
    performed which demonstrate that the PRVS can perform its intended 
    safety function relying on the orifice plates to measure flow. No 
    new equipment or components were installed. No credible new failures 
    are postulated.
        (3) Involve a significant reduction in a margin of safety.
        This change does not involve a significant reduction in the 
    margin of safety because:
        No function of any importance to safety SSC will be adversely 
    affected or degraded as a result of continued operation. No safety 
    parameters, setpoints, or design limits are changed. There is no 
    adverse impact to the nuclear fuel, cladding, RCS, or required 
    containment systems.
        Duke has concluded, based on the above, that there are no 
    significant hazards considerations involved in this amendment 
    request.
    
        The NRC staff has reviewed the licensee's analysis and, based on 
    this review, it appears that the three standards of 10 CFR 50.92(c) are 
    satisfied. Therefore, the NRC staff proposes to determine that the 
    amendment request involves no significant hazards consideration.
        The Commission is seeking public comments on this proposed 
    determination. Any comments received within 14 days after the date of 
    publication of this notice will be considered in making any final 
    determination.
        Normally, the Commission will not issue the amendments until the 
    expiration of the 14-day notice period. However, should circumstances 
    change during the notice period, such that failure to act in a timely 
    way would result, for example, in derating or shutdown of the facility, 
    the Commission may issue the license amendments before the expiration 
    of the 14-day notice period, provided that its final determination is 
    that the amendments involve no significant hazards consideration. The 
    final determination will consider all public and State comments 
    received. Should the Commission take this action, it will publish in 
    the Federal Register a notice of issuance. The Commission expects that 
    the need to take this action will occur very infrequently.
        Written comments may be submitted by mail to the Chief, Rules and 
    Directives Branch, Division of Administrative Services, Office of 
    Administration, U.S. Nuclear Regulatory Commission, Washington, DC 
    20555-0001, and should cite the publication date and page number of 
    this Federal Register notice. Written comments may also be delivered to 
    Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, 
    Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Copies of 
    written comments received may be examined at the NRC Public Document 
    Room, the Gelman Building, 2120 L Street, NW., Washington, DC.
        The filing of requests for hearing and petitions for leave to 
    intervene is discussed below.
        By August 17, 1998, the licensee may file a request for a hearing 
    with respect to issuance of the amendments to the subject facility 
    operating license and any person whose interest may be affected by this 
    proceeding and who wishes to participate as a party in the proceeding 
    must file a written request for a hearing and a petition for leave to 
    intervene.
        Requests for a hearing and a petition for leave to intervene shall 
    be filed in accordance with the Commission's ``Rules of Practice for 
    Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested persons 
    should consult a current copy of 10 CFR 2.714 which is available at the 
    Commission's Public Document Room, the Gelman Building, 2120 L Street, 
    NW., Washington, DC, and at the local public document room located at 
    the Oconee County Library, 501 West South Broad Street, Walhalla, South 
    Carolina. If a request for a hearing or petition for leave to intervene 
    is filed by the above date, the Commission or an Atomic Safety and 
    Licensing Board, designated by the Commission or by the Chairman of the 
    Atomic Safety and Licensing Board Panel, will rule on the request and/
    or petition; and the Secretary or the designated Atomic Safety and 
    Licensing Board will issue a notice of hearing or an appropriate order.
        As required by 10 CFR 2.714, a petition for leave to intervene 
    shall set forth with particularity the interest of the petitioner in 
    the proceeding, and how that interest may be affected by the results of 
    the proceeding. The petition should specifically explain the reasons 
    why intervention should be permitted with particular reference to the 
    following factors: (1) The nature of the petitioner's right under the 
    Act to be made a party to the proceeding; (2) the nature and extent of 
    the petitioner's property, financial, or other interest in the 
    proceeding; and (3) the possible effect of any order which may be 
    entered in the proceeding on the petitioner's interest. The petition 
    should also identify the specific aspect(s) of the subject matter of 
    the proceeding as to which petitioner wishes to intervene. Any person 
    who has filed a petition for leave to intervene or who has been 
    admitted as a party may amend the petition without requesting leave of 
    the Board up to 15 days prior to the first prehearing conference 
    scheduled in the proceeding, but such an amended petition must satisfy 
    the specificity requirements described above.
        Not later than 15 days prior to the first prehearing conference 
    scheduled in the proceeding, a petitioner shall file a supplement to 
    the petition to intervene which must include a list of the contentions 
    which are sought to be litigated in the matter. Each contention must 
    consist of a specific statement of the issue of law or fact to be 
    raised or controverted. In addition, the petitioner shall provide a 
    brief explanation of the bases of the contention and a concise 
    statement of the alleged facts or expert opinion which support the 
    contention
    
    [[Page 38435]]
    
    and on which the petitioner intends to rely in proving the contention 
    at the hearing. The petitioner must also provide references to those 
    specific sources and documents of which the petitioner is aware and on 
    which the petitioner intends to rely to establish those facts or expert 
    opinion. Petitioner must provide sufficient information to show that a 
    genuine dispute exists with the applicant on a material issue of law or 
    fact. Contentions shall be limited to matters within the scope of the 
    amendments under consideration. The contention must be one which, if 
    proven, would entitle the petitioner to relief. A petitioner who fails 
    to file such a supplement which satisfies these requirements with 
    respect to at least one contention will not be permitted to participate 
    as a party.
        Those permitted to intervene become parties to the proceeding, 
    subject to any limitations in the order granting leave to intervene, 
    and have the opportunity to participate fully in the conduct of the 
    hearing, including the opportunity to present evidence and cross-
    examine witnesses.
        If the amendments are issued before the expiration of the 30-day 
    hearing period, the Commission will make a final determination on the 
    issue of no significant hazards consideration. If a hearing is 
    requested, the final determination will serve to decide when the 
    hearing is held.
        If the final determination is that the amendment request involves 
    no significant hazards consideration, the Commission may issue the 
    amendment and make it immediately effective, notwithstanding the 
    request for a hearing. Any hearing held would take place after issuance 
    of the amendments.
        If the final determination is that the amendment request involves a 
    significant hazards consideration, any hearing held would take place 
    before the issuance of any amendment.
        A request for a hearing or a petition for leave to intervene must 
    be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
    Adjudications Staff, or may be delivered to the Commission's Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, 
    by the above date. A copy of the petition should also be sent to the 
    Office of the General Counsel, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555-0001, and to Mr. J. Michael McGarry, III, Winston 
    and Strawn, 1200 17th Street, NW., Washington, DC 20036, attorney for 
    the licensee.
        Nontimely filings of petitions for leave to intervene, amended 
    petitions, supplemental petitions and/or requests for hearing will not 
    be entertained absent a determination by the Commission, the presiding 
    officer or the presiding Atomic Safety and Licensing Board that the 
    petition and/or request should be granted based upon a balancing of the 
    factors specified in 10 CFR 2.714(a)(1)(l)-(v) and 2.714(d).
        For further details with respect to this action, see the 
    application for amendment dated July 8, 1998, which is available for 
    public inspection at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room, located at the Oconee County Library, 501 West South 
    Broad Street, Walhalla, South Carolina.
    
        Dated at Rockville, Maryland, this 13th day of July 1998.
    
        For the Nuclear Regulatory Commission.
    David E. LaBarge,
    Senior Project Manager Project Directorate II-2, Division of Reactor 
    Projects--I/II, Office of Nuclear Reactor Regulation.
    [FR Doc. 98-18960 Filed 7-15-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
07/16/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-18960
Pages:
38433-38435 (3 pages)
Docket Numbers:
Docket No. 50-269, 50-270, and 50-287
PDF File:
98-18960.pdf