-
Start Preamble
AGENCY:
Occupational Safety and Health Administration (OSHA), U.S. Department of Labor.
ACTION:
Final rule; delay of effective date.
SUMMARY:
By this document the Occupational Safety and Health Start Printed Page 37138Administration (OSHA) revises the effective date of the new final rule for steel erection, Subpart R of 29 CFR Part 1926, which was published on January 18, 2001. The original effective date was to be July 18, 2001. Since publication of the standard, however, employers have contacted OSHA with a wide range of questions regarding whether, and how, the standard will be applied to projects that are in various stages of completion as of July 18, 2001. Specifically, employers have expressed concerns about their ability to comply with the new standard by that date, particularly with regard to provisions that address construction safety design aspects of structural components. To address these problems, and to allow additional time for the Agency to explain the new standard to the affected industry, the effective date of the standard is changed to January 18, 2002.
DATES:
The effective date of the amendments to 29 CFR part 1926 published on January 18, 2001 at 66 FR 5196 is delayed from July 18, 2001 until January 18, 2002.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Office of Public Affairs, Room N-3647, Occupational Safety and Health Administration, U.S. Department of Labor, 200 Constitution Ave., N.W., Washington, DC 20210; telephone: (202) 693-1999.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
I. Background
On January 18, 2001 (66 FR 5196) OSHA published a final safety standard for steel erection, with an effective date of July 18, 2001. A number of provisions in the final rule address the safety of certain structural components. These provisions (“component requirements”) contain requirements for these components to help ensure that the structure can be erected safely. For example, there are provisions that prohibit shear connectors on members before they are erected (§ 1926.754(c)(1)(i)); require all columns to be anchored by a minimum of 4 anchor bolts, which must meet specified strength requirements (§ 1926.755(a)) (there is a comparable requirement for systems-engineered metal buildings, § 1926.758(b)); set requirements for double connections (§ 1926.756(c)(1)) (there is a comparable requirement for systems-engineered metal buildings § 1926.758(e)); require column splices to be at a specified height and meet a strength requirement (§ 1926.756(d)); require perimeter columns to have holes or other devices for perimeter safety cables (§ 1926.756(e)); in some instances require a vertical stabilizer plate to stabilize steel joists (§ 1926.757(a)(1)(i)); require certain joists to be strong enough to allow one employee to release the hoisting cable without the need for erection bridging (§ 1926.757(a)(3)), and require certain joists to be fabricated to allow for field bolting during erection (§ 1926.757(a)(8)(i)).
On January 20, 2001, Andrew H. Card, Jr., the Assistant to the President and Chief of Staff, issued a memorandum entitled “Regulatory Review Plan” (66 FR 7702). The memorandum directed that, with respect to regulations published in the Federal Register that had not yet taken effect, agencies were to temporarily postpone the effective date of the regulations for 60 days, subject to certain exceptions.
Since publication of the standard, a number of employers in the steel erection industry have asked whether the final rule will be applied to projects in various stages of completion as of the effective date. For example, they have asked if and how the standard will apply to a steel erection project when: (1) The project was designed before July 18, 2001; (2) the structural components were fabricated before that date and do not meet the requirements in the final rule, and (3) the steel erection work for the project began before that date and construction is continuing afterwards.
II. New Effective Date
These questions have highlighted a need to give the industry additional time to comply with the final rule. As explained below, we believe that changing the effective date to January 18, 2002 will give the industry sufficient time to adjust to the new requirements.
Based on information available to the Agency, we understand that, while the design of structural components can be changed, some time is necessary to make changes needed to conform to the final rule's requirements. Components are typically fabricated 2 or 3 months prior to being erected. Not only would it be very costly to have to re-fabricate components that were already-made, such re-fabrication would cause serious delays to the project, affecting all the trades involved. The new effective date will give an additional 6 months to facilitate these changes. The additional 6 months should ensure that re-fabrication of already made components will be unnecessary. In addition, there will be additional time for the Agency to conduct outreach activities on the new standard, in order to inform employers and employees of the requirements of the standard.
III. How The New Effective Date Will Be Applied to Component Requirements
There are two situations that could cause significant confusion under the new standard: (1) Components used in steel erection projects that were designed before the final rule was published (January 18, 2001), and for which a building permit was obtained prior to that date; and (2) components used in steel erection projects in which the steel erection work has begun before the final rule becomes effective (originally July 18, 2001, now to be January 18, 2002). We will apply the component requirements of the final rule to these situations as follows:
Building Permits Obtained Before January 18, 2001
It is easier to alter a structural design before the building permit has been obtained, since changes prior to that point do not need as many reviews and approvals as are needed afterwards. Therefore, where a building permit was obtained before the final rule was published (January 18, 2001), the component requirements referred to above will not apply to the project.
Steel Erection Work Begins Before January 18, 2002
It would be difficult, costly and confusing to begin to comply with the new component requirements to a project in which steel erection work has started under the previous steel erection standard. (For example, the column splice height on a lower floor affects the column splice height on successive floors. The new standard makes significant changes in this area.) Since the final rule was published on January 18, 2001, employers have been on notice that the new standard's stated effective date was July 18, 2001, and they have been expected to make plans to meet the new requirements. However, on May 14, 2001, the Department published its Semi-Annual Regulatory Agenda (66 FR 25679), in which the effective date of the final rule was listed as September 16, 2001. Since that publication, affected employers have expressed confusion as to when the final rule would actually go into effect.
As of January 18, 2002, some steel erection projects will be partly completed. Since some employers may have been expecting the rule to go into effect on September 16, 2001 (rather than July 18, 2001), we will use that date to determine whether projects partially completed on January 18, 2002 will be subject to the component provisions in the final rule. In sum, the Start Printed Page 37139component requirements of the final rule will not be applied to those projects if the steel erection had begun on or before September 16, 2001.
IV. Further Guidance on Section 1926.757(a)(3)
The Steel Joist Institute (SJI) has asked the Agency to delay implementation of § 1926.757(a)(3) for two years. That provision requires that, “where steel joists at or near columns span 60 feet (18.3m) or less, the joist shall be designed with sufficient strength to allow one employee to release the hoisting cable without the need for erection bridging.” SJI has informed OSHA that they have encountered unanticipated problems in developing some of the longer joists that will meet this requirement. OSHA intends to address this issue separately.
Paperwork Reduction Act
The information requirements of the steel erection standard have been approved under OMB Control Number 1218-0237. The present regulatory action delays the effective date of that standard and imposes no additional paperwork burdens.
Regulatory Flexibility Certification
Pursuant to the Regulatory Flexibility Act (5 U.S.C. 601), the Acting Assistant Secretary certifies that the delay in the effective date of the steel erection standard will not have a significant adverse impact on a substantial number of small entities.
Executive Order 12866
The delay in the effective date of the steel erection standard is not a significant regulatory action for the purposes of Executive Order 12866.
Exemption from Notice and Comment
To the extent that 5 U.S.C. 553 applies to this action, the Secretary finds that good cause exists to exempt this action from notice and comment, and to make it effective immediately upon publication today in the Federal Register. 5 U.S.C. 553(b)(B), 553 (d)(3).
As discussed above, prior official statements may have left the regulated community uncertain about when it would need to comply with the steel erection rule. In the last several weeks, OSHA has received a significant number of inquiries manifesting this uncertainty. The rule is currently scheduled to take effect on July 18, and the regulated community has an immediate need to know its obligations under the standard. In addition, the additional time needed for notice and comment would add further uncertainty about compliance obligations during that period. Accordingly, the Agency has determined that there is good cause to dispense with notice and comment and to make this delay effective immediately.
In summary, given the imminence of the effective date of the steel erection standard, seeking prior public comment on this delay is unnecessary and impracticable, as well as contrary to the public interest in the orderly promulgation and implementation of regulations.
Authority
This document was prepared under the direction of R. Davis Layne, Acting Assistant Secretary for Occupational Safety and Health. It is issued under Section 107 of the Contract Work Hours and Safety Standards Act (Construction Safety Act) (40 U.S.C. 333), Sections 6 and 8 of the Occupational Safety and Health Act (29 U.S.C. 655, 657), and 5 U.S.C. 553.
Start SignatureIssued at Washington, DC, this 13th day of July, 2001.
R. Davis Layne,
Acting Assistant Secretary of Labor.
[FR Doc. 01-17944 Filed 7-16-01; 8:45 am]
BILLING CODE 4510-26-P
Document Information
- Effective Date:
- 1/18/2001
- Published:
- 07/17/2001
- Department:
- Occupational Safety and Health Administration
- Entry Type:
- Rule
- Action:
- Final rule; delay of effective date.
- Document Number:
- 01-17944
- Dates:
- The effective date of the amendments to 29 CFR part 1926 published on January 18, 2001 at 66 FR 5196 is delayed from July 18, 2001 until January 18, 2002.
- Pages:
- 37137-37139 (3 pages)
- RINs:
- 1218-AA65: Steel Erection (Part 1926) (Safety Protection for Ironworkers)
- RIN Links:
- https://www.federalregister.gov/regulations/1218-AA65/steel-erection-part-1926-safety-protection-for-ironworkers-
- PDF File:
- 01-17944.pdf
- CFR: (1)
- 29 CFR 1926