95-17564. Commonwealth Edison Co. (Zion Nuclear Power Station, Unit 1); Exemption  

  • [Federal Register Volume 60, Number 137 (Tuesday, July 18, 1995)]
    [Notices]
    [Pages 36834-36836]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-17564]
    
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-295]
    
    
    Commonwealth Edison Co. (Zion Nuclear Power Station, Unit 1); 
    Exemption
    
    I
    
        Commonwealth Edison Company (ComEd or the licensee) is the holder 
    of Facility Operating License No. DPR-39, which authorizes operation of 
    the Zion Nuclear Power Station, Unit 1, at a steady-state reactor power 
    level not in excess of 3250 megawatts thermal. The facility is a 
    pressurized water reactor located at the licensee's site in Lake 
    County, Illinois. The license provides, among other things, that the 
    Zion Nuclear Power Station is subject to all rules, regulations, and 
    orders of the U.S. Nuclear Regulatory Commission (the Commission or 
    NRC) now or hereafter in effect.
    
    II
    
        Section III.D.1.(a) of appendix J to 10 CFR part 50 requires the 
    performance of three Type A containment integrated leakage rate tests 
    (ILRTs) at approximately equal intervals during each 10-year inservice 
    inspection period. Furthermore, the third test of each set is to be 
    conducted during the shutdown for the 10-year plant inservice 
    inspections.
    
    III
    
        In a letter dated May 12, 1995, the licensee requested relief from 
    the requirement to perform a set of three Type A tests at approximately 
    equal intervals during each 10-year inservice 
    
    [[Page 36835]]
    inspection period. The requested exemption would permit a one-time 
    interval extension of the third Type A test of the second 10-year 
    inservice inspection period by approximately 18 months and would result 
    in the interval between successive Type A leakage rate tests being 
    approximately 60 months. If the revised 10 CFR part 50 requirements are 
    approved and implemented, the next Type A test could be deferred up to 
    an additional 60 months.
        The licensee's request justified the proposed change, on the 
    following basis.
        In the Type A test conducted in the RFO in March 1988, the leakage 
    rate was below the maximum allowable. In the Type A test conducted 
    during the RFO in March 1992, after adding all required penalties 
    associated with local leakage rate tests (LLRTs), the as-found Type A 
    test result was a failure. However, the majority of the leakage in the 
    LLRTs was due to a valve in one penetration. Prior to repairing the 
    valve, a leakage rate that was double the allowed limit was measured. 
    The licensee's corrective maintenance on the valve and its post-repair 
    leakage rate testing resulted in a Type A test leakage rate that was 
    about 20 percent of the allowable limit.
        The licensee stated that there are no mechanisms which would 
    adversely affect the structural integrity of the containment or that 
    would be a factor in evaluating the extension of the test interval by 
    18 months. However, as a preventive maintenance measure, the visual 
    containment inspection currently required by 10 CFR part 50, appendix 
    J, prior to a Type A test, will be conducted during the September 1995 
    RFO to verify that there are no apparent signs of containment 
    degradation and to provide added confidence that the containment 
    structural integrity was not affected during the period since the last 
    visual inspection. Any additional risk created by the longer interval 
    between Type A testing is considered by the licensee to be negligible, 
    primarily because all Type B and Type C leakage rate testing will 
    continue to be performed in accordance with the requirements of 10 CFR 
    part 50, appendix J, Sections III.B and III.C.
        To justify granting an exemption to the requirements of 10 CFR Part 
    50, a licensee must show that the requirements of 10 CFR 50.12(a)(1) 
    are met. The licensee stated that its exemption request meets the 
    requirements of 10 CFR 50.12(a)(1), for the following reasons:
    
        (1) The requested one time exemption and the associated 
    activities are authorized by law.
        There are no prohibitions of law which preclude the activities 
    which would be authorized by the requested exemption. Similar 
    exemptions have been granted for ComEd's Zion Station and other 
    utilities. Therefore, the NRC is authorized by law to approve the 
    proposed exemption.
        (2) The requested exemption will not present undue risk to the 
    public.
        An exemption from the requirements of 10 CFR 50 Appendix J to 
    perform reactor containment leakage testing will not present undue 
    risk to the health and safety of the public. Past testing has 
    demonstrated the leak tight nature of the primary reactor 
    containment structure and systems and components penetrating the 
    primary containment and the ability to maintain total leakages, 
    including conservatisms, within required limits. A more detailed 
    discussion of the past reactor containment integrated leakage rate 
    test results is included below.
        (3) The requested exemption will not endanger the common defense 
    and security.
        The common defense and security are in no way compromised by 
    this proposed exemption since approval of the exemption would in no 
    way alter the plant in any physical manner.
    
        In addition, the licensee must show that at least one of the 
    special circumstances, as defined in 10 CFR 50.12(a)(2), is present. 
    One of the special circumstances that a licensee may show to exist is 
    that the application of the regulation in the particular circumstances 
    is not necessary to achieve the underlying purposes of the rule. The 
    purposes of the rule, as stated in section I of 10 CFR part 50, 
    appendix J, are to ensure that: 1) leakage through the primary reactor 
    containment and systems and components penetrating containment shall 
    not exceed allowable values, and 2) periodic surveillance of reactor 
    containment penetrations and isolation valves is performed so that 
    proper maintenance and repairs are made. The licensee presented the 
    following discussion to show that the requirement to perform the third 
    Type A leakage rate test during the September 1995 RFO is not necessary 
    to achieve the underlying purpose of the rule.
    
        Type A tests are intended to measure the primary reactor 
    containment overall integrated leakage rate after the containment 
    has been completed and is ready for operation, and at periodic 
    intervals. The performance of a periodic ILRT (Type A) and local 
    penetration tests (Type B and C) during containment life provides a 
    current assessment of potential leakage from the containment during 
    accident conditions. The periodic tests are performed at a pressure 
    sufficiently high to provide an accurate measurement of the leakage 
    rate. This pressure is at least 50 percent of design accident 
    pressure for the Type A tests and at least design accident pressure 
    for the Type B and C tests.
        Application of the regulation is not necessary to achieve the 
    underlying purpose of the rule because:
        (1) Prior testing has verified the ability of the reactor 
    containment to maintain leakage below the limits set forth in the 
    Technical Specifications and the regulation:
        (2) Type B & C testing, which detects the majority of 
    containment leakage, will continue to be performed as required;
        (3) The availability of the seal water and penetration 
    pressurization systems provides added confidence that leakage would 
    be maintained below the limits in the unlikely event of a LOCA; and
        (4) There is no significant impact on risk to the public 
    associated with extending the period of time between successive Type 
    A tests on Unit 1 by approximately 18 months.
    
    IV
    
        Section III.D.1.(a) of appendix J to 10 CFR part 50 states that a 
    set of three Type A leakage rate tests shall be performed at 
    approximately equal intervals during each 10-year inservice inspection 
    period.
        The licensee proposes an exemption to this section which would 
    provide a one-time interval extension for the Type A test of 
    approximately 18 months.
        The Commission has determined that, pursuant to 10 CFR 50.12(a)(1), 
    this exemption is authorized by law, will not present an undue risk to 
    the public health and safety, and is consistent with the common defense 
    and security. The Commission further determined, for the reasons 
    discussed below, that special circumstances, as provided in 10 CFR 
    50.12(a)(2)(ii), are present justifying the exemption; namely, that 
    application of the regulation in the particular circumstances is not 
    necessary to achieve the underlying purpose of the rule.
        The underlying purpose of the requirement to perform Type A 
    containment leakage rate tests at intervals during the 10-year 
    inservice inspection period, is to ensure that any potential leakage 
    pathways through the containment boundary are identified within a time 
    span that prevents significant degradation from commencing or 
    continuing without the knowledge of the licensee. The stafff has 
    reviewed the basis and supporting information provided by the licensee 
    in the exemption request and considers that the licensee has a good 
    record of ensuring a leak-tight containment. The one Type A test that 
    did not pass was shown to be due to a leaking valve. The licensee took 
    aggressive and appropriate corrective action that resulted in a final 
    as-left leakage rate that was significantly below the maximum allowable 
    value. Therefore, the containment was shown to be leak tight, the 
    licensee demonstrated that it has an effective 
    
    [[Page 36836]]
    corrective action program and the results of the Type A test were 
    confirmatory of the Type B and Type C tests rather than providing 
    information that would otherwise not have been available. The licensee 
    has stated that the visual containment inspection will be performed 
    during the September 1995 RFO although it is only required by 10 CFR 
    part 50, appendix J, to be performed in conjunction with Type A tests. 
    The staff considers that these inspections, though limited in scope, 
    provide an important added level of confidence in the continued 
    structural integrity of the containment boundary.
        The staff has also made use of the information in a draft stafff 
    report, NUREG-1493, which provides the technical justification for the 
    present Appendix J rulemaking effort which also includes a 10-year test 
    interval for Type A tests. The ILRT, or Type A test, measures overall 
    containment leakage. However, operating experience with all types of 
    containments used in this country demonstrates that essentially all 
    containment leakage can be detected by LLRT (Type B and Type C). 
    According to results given in NUREG-1493, out of 180 ILRT reports 
    covering 110 individual reactors and approximately 770 years of 
    operating history, only five ILRT failures were found which local 
    leakage rate testing could not detect. This is 3 percent of all 
    failures. This study agrees with previous staff studies which show that 
    Type B and Type C testing detect a very large percentage of containment 
    leaks. The Zion Station, Unit 1, experience has also been consistent 
    with these results.
        The Nuclear Management and Resources Council (NUMARC), now the 
    Nuclear Energy Institute (NEI), collected and provided the staff with 
    summaries of data to assist in the 10 CFR part 50, appendix J, 
    rulemaking effort. The NEI collected results of 144 ILRTs from 33 units 
    of which 23 ILRTs exceeded 1.0La. Of these, only nine were not due 
    to Type B or C leakage penalties. The NEI data also added another 
    perspective. The NEI data show that in about one-third of the cases 
    exceeding allowable leakage, the as-found leakage was less than 
    2La; in one case the leakage was found to be approximately 
    2La; in one case the as-found leakage was less than 3La; one 
    case approached 10La; and in one case the leakage was found to be 
    approximately 21La. For about half of the failed ILRTs, the as-
    found leakage was not qualified. These data show that, for those ILRTs 
    for which the leakage was quantified, the leakage values are small when 
    compared to the leakage value at which the risk to the public starts to 
    increase over the value of risk corresponding to La (approximately 
    200La, as discussed in NUREG-1493). Therefore, based on these 
    considerations, it is unlikely that an extension of 18 months for the 
    performance of the appendix J, type A tests at Zion would result in 
    significant degradation of the overall containment integrity. Thus, the 
    application of the regulation in these particular circumstances is not 
    necessary to achieve the underlying purpose of the rule.
        Based on generic and plant-specific data, the staff finds the 
    licensee's proposed one-time exemption to permit a schedular extension 
    of one cycle for the performance of the 10 CFR part 50, appendix J, 
    type A test, provided that the visual containment inspection is 
    performed, to be acceptable.
        Pursuant to 10 CFR 51.32, the Commission has determined that 
    granting this exemption will not have a significant impact on the human 
    environment (60 FR 34305).
        This exemption is effective upon issuance and shall expire at the 
    completion of the Type A test scheduled to be performed during the 
    March 1997 refueling outage.
    
        Dated at Rockville, Maryland this 12th day of July 1995.
    
        For the Nuclear Regulatory Commission.
    Jack W. Roe,
    Director, Division of Reactor Projects--III/IV, Office of Nuclear 
    Reactor Regulation.
    [FR Doc. 95-17564 Filed 7-17-95; 8:45 am]
    BILLING CODE 7590-01-M
    
    

Document Information

Published:
07/18/1995
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
95-17564
Pages:
36834-36836 (3 pages)
Docket Numbers:
Docket No. 50-295
PDF File:
95-17564.pdf