Sea Robin Pipeline Company; Notice of Application
June 26, 1998.
Take notice that on June 19, 1998, Sea Robin Pipeline Company (Sea
Robin), Post Office Box 2563, Birmingham, Alabama 35202-2563, filed in
Docket No. CP98-628-000, an application pursuant to Section 7(b) of the
Natural Gas Act and Sections 157.5 through 157.13 and 157.18 of the
Commission's Regulations, to abandon two compressor units and
appurtenant facilities, one of which is located in Vermillion Parish,
Louisiana, and the other located offshore Louisiana, all as more fully
set forth in the application which is on file with the Commission and
open to public inspection.
Specifically, Sea Robin proposes to abandon: (1) one of three
10,830 horsepower reciprocating compressor units and appurtenant
facilities at its Erath Compressor Station (Erath); and
[[Page 36218]]
(2) one of three 12,350 horsepower turbine engine compressor units and
appurtenant facilities at its Vermillion 149 Compressor Station
(Vermillion 149).
Sea Robin states that the remaining compressor units at Erath and
Vermillion 149 will be sufficient to compress the quantities of gas
available on its system, and that the proposed abandonment of the two
units will have no affect on its firm obligations, nor will it result
in any termination or deterioration of service to its customers.
Any person desiring to be heard or to make any protest with
reference to said application should on or before July 17, 1998, file
with the Federal Energy Regulatory Commission, 888 First Street, N.E.,
Washington, D.C. 20426, a motion to intervene or a protest in
accordance with the requirements of the Commission's Rules of Practice
and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
Natural Gas Act (18 CFR 157.10). All protests filed with the Commission
will be considered by it in determining the appropriate action to be
taken but will not serve to make protestants parties to the proceeding.
Any person wishing to become a party to a proceeding or to participate
as a party in any hearing therein must file a motion to intervene in
accordance with the Commission's Rules.
Take further notice that, pursuant to the authority contained in
and subject to the jurisdiction conferred upon the Federal Energy
Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and
the Commission's Rules of Practice and Procedure, a hearing will be
held without further notice before the Commission or its designee on
this application if no motion to intervene is filed within the time
required herein, if the Commission on its on review of the matter finds
that permission and approval for the proposed abandonment are required
by the public convenience and necessity. If a motion for leave to
intervene is timely filed, or if the Commission on its own motion
believes that a formal hearing is required, further notice of such
hearing will be duly given.
Under the procedure herein provided for, unless otherwise advised,
it will be unnecessary for Sea Robin to appear or be represented at the
hearing.
Linwood A. Watson, Jr.,
Acting Secretary.