99-18714. Notice of Application Accepted for Filing and Soliciting Motions to Intervene and Protests  

  • [Federal Register Volume 64, Number 140 (Thursday, July 22, 1999)]
    [Notices]
    [Pages 39506-39507]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-18714]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    
    
    Notice of Application Accepted for Filing and Soliciting Motions 
    to Intervene and Protests
    
    July 16, 1999.
        a. Type of Application: Preliminary Permit.
        b. Project No.: P-11740-000.
        c. Date filed: May 7, 1999.
        d. Applicant: Universal Electric Power Corp.
        e. Name of Project: Enid Dam Project.
        f. Location: At the Corps of Engineer's Enid Dam, on the Yocona 
    River, near the Town of Crowder, Yolobusha County, Mississippi.
        g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
        h. Applicant Contact: Mr. Ronald Feltenberger, Universal Electric 
    Power Corp., 1145 Highbrook Street, Akron, Ohio 44301, (330) 535-7115.
        i. FERC Contact: Michael Spencer, [email protected], 
    (202) 219-2846.
        j. Deadline for filing motions to intervene and protest: 60 days 
    from the issuance date of this notice.
        All documents (original and eight copies) should be filed with: 
    David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888 
    First Street, NE, Washington, DC 20426.
        The Commission's Rules of Practice and Procedure require all 
    intervenors filing documents with the Commission to serve a copy of 
    that document on each person whose name appears on the official service 
    list for the project. Further, if an intervenor files comments or 
    documents with the Commission relating to the merits of an issue that 
    may affect the responsibilities of a particular resource agency, they 
    must also serve a copy of the document on that resource agency.
        k. Description of Project: The proposed project would utilize the 
    Corps of Engineer's Enid Dam and consist of the following: (1) a 114-
    inch-diameter, 80-foot-long steel penstock, constructed in the existing 
    outlet works; (2) a powerhouse containing four generating units with a 
    total capacity of 7.8 MW and an estimated average annual generation of 
    48.0 GWh; and (3) a 3.0-mile-long transmission line.
        l. Locations of the application: A copy of the application is 
    available for inspection and reproduction at the Commission's Public 
    Reference and Files Maintenance Branch, located at 888 First Street, 
    N.E., Room 2A, Washington, D.C. 20426, or by calling (202) 219-1371. 
    This filing may be viewed on the web at http://www.ferc.fed.us/online/
    rims.htm (Call (202) 208-2222 for assistance). A copy is also available 
    for inspection and reproduction at the address in item h above.
        Preliminary Permit--Anyone desiring to file a competing application 
    for preliminary permit for a proposed project must submit the competing 
    application itself, or a notice of intent to file such an application, 
    to the Commission on or before the specified comment date for a 
    particular application (see 18 CFR 4.36). Submission of a timely notice 
    of intent allows an interested person to file the competing preliminary 
    permit application no later than 30 days after the specified comment 
    date for the particular application. A competing preliminary permit 
    application must conform with 18 CFR 4.30(b) and 4.36.
        Preliminary Permit--Any qualified development applicant desiring to 
    file a competing development application must submit to the Commission, 
    on or before a specified comment date for the particular application, 
    either a competing development application or a notice of intent to 
    file such an application. Submission of a timely notice of intent to 
    file a development application allows an interested person to file the 
    competing application no later than 120 days after the specified 
    comment date for the particular application. A competing license 
    application must conform with 18 CFR 4.30(b) and 4.36.
        Notice of intent--A notice of intent must specify the exact name, 
    business address, and telephone number of the prospective applicant, 
    and must include an unequivocal statement of intent to submit, if such 
    an application may be filed, either a preliminary permit application or 
    a development application (specify which type of application). A notice 
    of intent must be served on the applicant(s) named in this public 
    notice.
        Proposed Scope of Studies under Permit--A preliminary permit, if 
    issued, does not authorize construction. The term of the proposed 
    preliminary permit would be 36 months. The work proposed under the 
    preliminary permit would include economic analysis, preparation of 
    preliminary engineering plans, and a study of environmental
    
    [[Page 39507]]
    
    impacts. Based on the results of these studies, the Applicant would 
    decide whether to proceed with the preparation of a development 
    application to construct and operate the project.
        Comments, Protests, or Motions to Intervene--Anyone may submit 
    comments, a protest, or a motion to intervene in accordance with the 
    requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
    .214. In determining the appropriate action to take, the Commission 
    will consider all protests or other comments filed, but only those who 
    file a motion to intervene in accordance with the Commission's Rules 
    may become a party to the proceeding. Any comments, protests, or 
    motions to intervene must be received on or before the specified 
    comment date for the particular application.
        Filing and Service of Responsive Documents--Any filings must bear 
    in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT TO 
    FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', ``PROTEST'', 
    ``MOTION TO INTERVENE'', as applicable, and the Project Number of the 
    particular application to which the filing refers. Any of the above-
    named documents must be filed by providing the original and the number 
    of copies provided by the Commission's regulations to: The Secretary, 
    Federal Energy Regulatory Commission, 888 First Street, NE., 
    Washington, DC 20426. An additional copy must be sent to Director, 
    Division of Project Review, Federal Energy Regulatory Commission, at 
    the above-mentioned address. A copy of any notice of intent, competing 
    application or motion to intervene must also be served upon each 
    representative of the Applicant specified in the particular 
    application.
        Agency Comments--Federal, state, and local agencies are invited to 
    file comments on the described application. A copy of the application 
    may be obtained by agencies directly from the Applicant. If an agency 
    does not file comments within the time specified for filing comments, 
    it will be presumed to have no comments. One copy of an agency's 
    comments must also be sent to the Applicant's representatives.
    David P. Boergers,
    Secretary.
    [FR Doc. 99-18714 Filed 7-21-99; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
07/22/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-18714
Pages:
39506-39507 (2 pages)
PDF File:
99-18714.pdf