[Federal Register Volume 62, Number 143 (Friday, July 25, 1997)]
[Notices]
[Page 40067]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-19572]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP97-645-000]
Ozark Gas Transmission System; Notice of Application
July 21, 1997.
Take notice that on July 16, 1997, Ozark Gas Transmission System
(Applicant), 1,000 Louisiana, Suite 5800, Houston, Texas 77002 has
filed under Section 7(c) of the Natural Gas Act (NGA), for a
certificate to construct a delivery point for Arkansas Western Gas
Company (AWG) in Township 9N, Range 26W in Franklin County, Arkansas.
Under the terms of the Consent Decree issued in Docket No. CP78-532-
000, 22 FERC para. 61,334 (1983) Applicant must obtain a certificate
from the Commission when it installs facilities to connect with any
other entity at the location where construction is proposed.
The proposed construction will allow Applicant to deliver 17,400
Dth/d to AWG. Applicant estimates the cost of this project to be
$11,900. In addition, Applicant states that the construction will be
financed from funds on hand.
Any person desiring to be heard or to make any protest with regard
to this application should on or before August 11, 1997, file with the
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426, a motion to intervene or a protest in accordance
with the requirements of the Commission's Rules of Practice and
Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
Natural Gas Act (18 CFR 157.10). All protests filed with the Commission
will be considered by it in determining the appropriate action to be
taken but will not serve to make the protestants parties to the
proceeding. Any person wishing to become a party to the proceeding or
to participate as a party in any hearing therein must file a motion to
intervene in accordance with the Commission's Rules.
Take further notice that, pursuant to the authority contained in
and subject to the jurisdiction conferred upon the Federal Energy
Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and
the Commission's Rules of Practice and Procedure, a hearing will be
held without further notice before the Commission or its designee on
this application if no motion to intervene is filed within the time
required herein, if the Commission on its own review of the matter
finds that a grant of the certificate is required by the public
convenience and necessity. If a motion for leave to intervene is timely
filed, or if the Commission on its own motion believes that a formal
hearing is required, further notice of such hearing will be duly given.
Under the procedure herein provided for, unless otherwise advised,
it will be unnecessary for Applicant to appear or be represented at the
hearing.
Lois D. Cashell,
Secretary.
[FR Doc. 97-19572 Filed 7-24-97; 8:45 am]
BILLING CODE 6717-01-M