DEPARTMENT OF ENERGY
Wallkill Generating Company, L.P.; Issuance of Order
July 22, 1994.
On April 25, 1991, Wallkill Generating Company, L.P. (Wallkill)
submitted for filing a power sales agreement with Orange and Rockland
Utilities, Inc. (O&R) which included markets-based rates. Wallkill also
requested waiver of various Commission regulations. In particular,
Wallkill requested that the Commission grant blanket approval under 18
CFR Part 34 of all future issuances of securities and assumptions of
liability by Wallkill.
On July 5, 1991, the Commission granted the request for blanket
approval under Part 34, 56 FERC 61,067, subject to certain conditions,
specifically the Commission allowing interested persons 30 days in
which to protest or move to intervene and to seek a hearing. However,
no notice of the opportunity to file was issued at that time.
Accordingly, take notice that:
Within thirty days of the date of this notice, any person desiring
to be heard or to protest the blanket approval of issuances of
securities or assumptions of liability by Wallkill should file a motion
to intervene or protest with the Federal Energy Regulatory Commission,
825 North Capitol Street, NE., Washington, DC 20426, in accordance with
Rules 211 and 214 of the Commission's Rules of Practice and Procedure
(18 CFR 385.211 and 385.214).
Absent a request for hearing within this period, Wallkill is
authorized to issue securities and assume obligations or liabilities as
a guarantor, indorser, surety, or otherwise in respect of any security
of another person; provided that such issuance or assumption is for
some lawful object within the corporate purposes of the applicant, and
compatible with the public interests, and is reasonably necessary or
appropriate for such purposes.
The Commission reserves the right to require a further showing that
neither public nor private interests will be adversely affected by
continued approval of Wallkill's issuances or securities or assumptions
of liability.
Notice is hereby given that the deadline for filing motions to
intervene or protests, as set forth above, is August 22, 1994.
Copies of the full text of the order are published in the FERC
Reports, and also are available from the Commission's Public Reference
Branch, Room 3308, 941 North Capitol Street, NE. Washington, DC 20426.
Lois D. Cashell,
Secretary.