94-18507. Commonwealth Edison Co.; Zion Nuclear Power Station, Units 1 and 2; Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 59, Number 145 (Friday, July 29, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-18507]
    
    
    [[Page Unknown]]
    
    [Federal Register: July 29, 1994]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
     
    
    Commonwealth Edison Co.; Zion Nuclear Power Station, Units 1 and 
    2; Environmental Assessment and Finding of No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an exemption to Facility Operating License Nos. 
    DPR-39 and DPR-48, issued to Commonwealth Edison Company (the 
    licensee), for operation of the Zion Nuclear Power Station, Units 1 and 
    2, located in Lake County, Illinois.
    
    Environmental Assessment
    
    Identification of Proposed Action
    
        The proposed action would grant an exemption from 10 CFR Part 50, 
    Appendix J, Section III.D.3, which requires that Type C tests 
    (containment isolation valve leakage rate tests) be performed during 
    each reactor shutdown for refueling, but in no case at intervals 
    greater than 2 years. This requirement applies to valves 1(2)MOV-CC685, 
    the first isolation valves outside containment in the component cooling 
    water return line from the reactor coolant pump thermal barriers. It is 
    these valves that are the subject of this exemption request. This one-
    time exemption will allow the Type C leak rate test on valves 1(2)MOV-
    CC685 to be deferred until the next refueling outages (September 1995 
    for Unit 1 and January 1995 for Unit 2).
        An amendment request to recognize the exemption was submitted by 
    the licensee in another letter, also dated June 16, 1994. Both the 
    amendment and exemption requests were preceded by a Notice of 
    Enforcement Discretion (NOED) to not enforce compliance with the 
    Technical Specification requirement to perform Type C tests of 1(2)MOV-
    CC685 in accordance with 10 CFR Part 50, Appendix J. The NOED precluded 
    Unit 2 from being shut down and allowed the startup of Unit 1.
    
    The Need for the Proposed Action
    
        The proposed exemption is needed because valves 1(2)MOV-CC685 have 
    never been tested per the requirements of 10 CFR Part 50, Appendix J, 
    Section III.D.3. Continued operation of both units until their next 
    refueling outage requires the exemption because they will not be in 
    compliance with the requirements until the tests are performed. 
    Requiring the licensee to place both units in cold shutdown to do the 
    tests would result in undue hardship without a compensating increase in 
    safety. The scope of the test preparations in significant, requiring 
    removal of the reactor coolant pumps (RCP) from service, draining the 
    component cooling water (CCW) return line from the RCP thermal 
    barriers, uncoupling the flange at the CCW outlet from the RCP thermal 
    barrier and opening test valves to provide a vent path. In addition to 
    the undesirable thermal cycling of each unit, the licensee estimates 
    each unit would be shut down for about three weeks, significant 
    planning and maintenance support would be necessary, and significant 
    radiation doses to maintenance personnel would be incurred. There would 
    not be a compensating increase in level of safety that would justify 
    the extensive amount of work and radiation exposure that would be 
    incurred by requiring the licensee to perform the Type C leak rate 
    testing of these two valves prior the units' next refueling outage. The 
    licensee is proposing performance of the tests during the next 
    refueling outage for each unit (September 1995 for Unit 1 and January 
    1995 for Unit 2) which is a time period that is outside of the 
    schedular requirements of 10 CFR Part 50, Appendix J.
    
    Environmental Impacts of the Proposed Action
    
        The Commission has completed its evaluation and determined that 
    granting the proposed exemption would not significantly increase the 
    probability or amount of expected primary containment leakage and that 
    containment integrity would, thus, be maintained. Although granting the 
    exemption would mean that the schedular requirements for Type C leak 
    rate testing in 10 CFR Part 50, Appendix J, would not be met, the 
    intent of leak rate testing (which is to (1) ensure that the leakage 
    through the primary containment, and systems and components that 
    penetrate the primary containment does not exceed the leakage rate 
    allowed by the Technical Specifications (TS) and associated basis, and 
    (2) ensure that proper maintenance and repair are being performed 
    throughout the service life of the containment boundary components) 
    would still be met due to the substantial barriers to fission product 
    release which are provided by the intact system piping and associated 
    valves. In addition, 1(2)MOV-CC9438, which are the valves outside 
    containment immediately downstream of 1(2)MOV-CC685, have been 
    satisfactorily tested in accordance with the applicable requirements of 
    10 CFR Part 50, Appendix J.
        The requested schedular exemption is a one time request of short 
    duration for valves 1(2)MOV-CC685. All other required leak rate tests 
    have been performed in accordance with the TS and 10 CFR Part 50, 
    Appendix J. To provide an additional margin of safety during the 
    upcoming operating cycles and to account for possible leakage through 
    the valves, Zion will impose an administrative limit for maximum 
    pathway leakage of 0.4La for both units. The licensee will also 
    perform periodic visual inspections of the piping from the containment 
    wall to the subject valves to provide further assurance that no 
    external leakage exists. The administrative limit for maximum pathway 
    leakage coupled with the visual inspections of the valves and their 
    associated piping provide a basis for showing that the probability of 
    exceeding the off-site does rate limits of 10 CFR Part 100 will not be 
    increased by deferring completion of the Type C leak rate testing of 
    1(2)MOV-CC685. In addition, testing has been performed on the valves 
    that provides a high degree of confidence that leakage through 1(2)MOV-
    CC685 would be well within Type C testing limits. This testing 
    consisted of pressurized air tests of the piping between 1(2)MOV-CC685 
    and 1(2)MOV-CC9483 and water leakage tests on 1(2)MOV-CC685 in the 
    accident direction. In both tests, no leakage was observed. Therefore, 
    the staff has determined that the exemption will not present an undue 
    risk to the public health and safety.
        Consequently, the probability of accidents would not be increased, 
    nor would the post-accident radiological releases be greater than 
    previously determined. Neither would the proposed exemption otherwise 
    affect radiological plant effluents. Therefore, the Commission's staff 
    concludes that there are no significant radiological environmental 
    impacts associated with the proposed exemption.
        With regard to potential nonradiological impacts, the proposed 
    exemption involves a change to surveillance and testing requirements. 
    It does not affect nonradiological plant effluents and has no other 
    environmental impact. Therefore, the Commission's staff concludes that 
    there are no significant nonradiological environmental impacts 
    associated with the proposed exemption.
    
    Alternative to the Proposed Action
    
        Since the Commission has concluded that there are no significant 
    environmental impacts associated with the proposed action, any 
    alternatives would have either no or greater environmental impact.
        The principal alternative would be to deny the requested exemption. 
    This would not reduce the environmental impacts attributed to the 
    facility and would result in a costly shut down of the units for the 
    purpose of performing the tests.
    
    Alternate Use of Resources
    
        This action does not involve the use of any resources not 
    previously considered in connection with the Nuclear Regulatory 
    Commission's Final Environmental Statement, dated December 1972, 
    related to the operation of the Zion Nuclear Power Station, Units 1 and 
    2.
    
    Agencies and Persons Consulted
    
        The NRC staff consulted with the Illinois State official regarding 
    the environmental impact of the proposed action. The State official had 
    no comments.
    
    Finding of No Significant Impact
    
        The Commission staff has determined not to prepare an environmental 
    impact statement for the proposed license exemption. Based upon the 
    foregoing environmental assessment, we conclude that the proposed 
    action will not have a significant effect on the quality of the human 
    environment.
        For further details with respect to this action, see the request 
    for exemption dated June 16, 1994, which is available for public 
    inspection at the Commission's Public Document Room, The Gelman 
    Building, 2120 L Street, NW., Washington, DC 20555, and at the local 
    public document room located at Waukegan Public Library, 128 North 
    County Street, Waukegan, Illinois 60085.
    
        Dated at Rockville, Maryland, this 25th day of July 1994.
    
        For the Nuclear Regulatory Commission.
    Robert A. Capra,
    Director, Project Directorate III-2, Division of Reactor Projects--III/
    IV, Office of Nuclear Reactor Regulation.
    [FR Doc. 94-18507 Filed 7-28-94; 8:45 am]
    BILLING CODE 7590-01-M
    
    
    

Document Information

Published:
07/29/1994
Department:
Nuclear Regulatory Commission
Entry Type:
Uncategorized Document
Document Number:
94-18507
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: July 29, 1994