96-19031. Decommissioning of Nuclear Power Reactors  

  • [Federal Register Volume 61, Number 146 (Monday, July 29, 1996)]
    [Rules and Regulations]
    [Pages 39278-39304]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-19031]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    10 CFR Parts 2, 50, and 51
    
    RIN 3150-AE96
    
    
    Decommissioning of Nuclear Power Reactors
    
    AGENCY: Nuclear Regulatory Commission.
    
    ACTION: Final rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Nuclear Regulatory Commission is amending its regulations 
    on the decommissioning procedures that lead to the termination of an 
    operating license for nuclear power reactors. The final amendments 
    clarify ambiguities in the current rule and codify procedures that 
    reduce the regulatory burden, provide greater flexibility, and allow 
    for greater public participation in the decommissioning process. Some 
    minor amendments pertain to non-power reactors and are for purposes of 
    clarification and procedural simplification. The Commission believes 
    that the final amendments will enhance efficiency and uniformity in the 
    regulatory process of decommissioning nuclear power plants.
    
    EFFECTIVE DATE: August 28, 1996.
    
    FOR FURTHER INFORMATION CONTACT: Dr. Carl Feldman, Office of Nuclear 
    Regulatory Research, U.S. Nuclear Regulatory Commission, Washington, DC 
    20555-0001, telephone (301) 415-6194; or S. Singh Bajwa, Office of 
    Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555-0001, telephone (301) 415-1013.
    
    SUPPLEMENTARY INFORMATION:
    
    Background
    
        On June 27, 1988 (53 FR 24018), the Commission promulgated 
    decommissioning regulations. On July 20, 1995 (60 FR 37374), the 
    Commission issued proposed amendments to these regulations. A 
    discussion of the current requirements and proposed amendments follows.
    
    Current Requirements
    
        Within 2 years after a licensee permanently ceases operation of a 
    nuclear reactor facility, it must submit a detailed decommissioning 
    plan to the NRC for approval, along with a supplemental environmental 
    report that addresses environmental issues that have not already been 
    considered. Based on these submittals, the NRC reviews the licensee's 
    planned activities, prepares a Safety Evaluation Report (SER) and an 
    environmental assessment (EA), and either makes a negative declaration 
    of impact (the usual case) or prepares an environmental impact 
    statement (EIS). Upon NRC approval of the decommissioning plan, the 
    Commission issues an order permitting the licensee to decommission its 
    facility in accordance with the approved plan. As part of the approval 
    process, the opportunity for a hearing under subpart G of 10 CFR part 
    2, is made available to the public. Once the decommissioning process is 
    completed and the NRC is satisfied that the facility has been 
    radioactively decontaminated to an unrestricted release level, the NRC 
    terminates the license.
        If the licensee chooses to place the reactor in storage and 
    dismantle it at a later time, the initial decommissioning plan 
    submittal need not be as detailed as a plan for prompt dismantlement. 
    However, before the licensee can begin dismantlement, a detailed plan 
    and environmental report must be submitted and approved by the 
    Commission.
        Before the decommissioning plan is approved, the licensee cannot 
    perform major decommissioning activities. If a licensee desires a 
    reduction in requirements because of the permanent cessation of 
    operation, it must obtain a license amendment for possession-only 
    status. This is usually granted after the licensee indicates that the 
    reactor has permanently ceased operations and fuel has been permanently 
    removed from the reactor vessel.
        A licensee is required to provide assurance that at any time during 
    the life of the facility, through termination of the license, adequate 
    funds will be available to complete decommissioning. For operating 
    reactors, the amount of decommissioning funding required is generically 
    prescribed in 10 CFR 50.75. Five years before license expiration or 
    cessation of operations, a preliminary decommissioning plan containing 
    a site-specific decommissioning cost estimate must be submitted and the 
    financial assurance mechanism must be appropriately adjusted. Finally, 
    the decommissioning plan, submitted within 2 years after permanent 
    cessation of operations, must provide a site-specific cost estimate for 
    decommissioning and a correspondingly adjusted financial assurance 
    mechanism. For delayed dismantlement of a power reactor facility, an 
    updated decommissioning plan must be submitted with the estimated cost 
    of decommissioning and the licensee must appropriately adjust the 
    financial assurance mechanism. Before approval of the decommissioning 
    plan, licensee use of these funds would be determined on a case-
    specific basis for premature closure, when accrual of required 
    decommissioning funds may be incomplete.
    
    Proposed Amendments
    
        The degree of regulatory oversight required for a nuclear power 
    reactor during its decommissioning stage is considerably less than that 
    required for the facility during its operating stage. During the 
    operating stage of the reactor, fuel in the reactor core undergoes a 
    controlled nuclear fission reaction that generates a high neutron flux 
    and large
    
    [[Page 39279]]
    
    amounts of heat. Safe control of the nuclear reaction involves the use 
    and operation of many complex systems. First, the nuclear reaction must 
    be carefully controlled through neutron absorbing mechanisms. Second, 
    the heat generated must be removed so that the fuel and its supporting 
    structure do not overheat. Third, the confining structure and ancillary 
    systems must be maintained and degradation caused by radiation and 
    mechanical and thermal stress ameliorated. Fourth, the radioactivity 
    resulting from the nuclear reaction in the form of direct radiation 
    (especially near the high neutron flux areas around the reactor 
    vessel), contaminated materials and effluents (air and water) must be 
    minimized and controlled. Finally, proper operating procedures must be 
    established and maintained with appropriately trained staff to ensure 
    that the reactor system is properly operated and maintained, and that 
    operating personnel minimize their exposure to radiation when 
    performing their duties. Moreover, emergency response procedures must 
    be established and maintained to protect the public in the event of an 
    accident.
        During the decommissioning stage of a nuclear power reactor, the 
    nuclear fission reaction is stopped and the fuel (spent fuel 
    assemblies) is permanently removed and placed in the spent fuel pool 
    until transferred offsite for storage or disposal. While the spent fuel 
    is still highly radioactive and generates heat caused by radioactive 
    decay, no neutron flux is generated and the fuel slowly cools as its 
    energetic decay products diminish. The spent fuel pool, which contains 
    circulating water, removes the decay heat and filters out any small 
    radioactive contaminants escaping the spent fuel assemblies. The spent 
    fuel pool system is relatively simple to operate and maintain compared 
    to an operating power reactor. The remainder of the facility contains 
    radioactive contamination and is highly contaminated in the area of the 
    reactor vessel. However, because the spent fuel is stored in a 
    configuration that precludes the nuclear fission reaction, no 
    generation of new radioactivity can occur. Safety concerns for a spent 
    fuel pool are greatly reduced regarding both control of the nuclear 
    fission process and the resultant generation of large amounts of heat, 
    high neutron flux and related materials degradation, and the stresses 
    imposed on the reactor system. Contaminated areas of the facility must 
    still be controlled to minimize radiation exposure to personnel and 
    control the spread of radioactive material. This situation is now 
    similar to a contaminated materials facility and does not require the 
    oversight that an operating reactor would require.
        Based on the preceding discussion, it should be noted that during 
    the operating stage of the reactor a nuclear reaction must be sustained 
    that has the potential during an accident to generate significant 
    amounts of energy and radiation whose consequences can be severe. 
    Moreover, the nature of maintaining and controlling a nuclear reaction 
    and the complexity of systems and operations requirements necessary to 
    prevent and mitigate adverse consequences requires considerable 
    oversight by the NRC. During the decommissioning stage of the reactor, 
    the potential for consequences that could result from an inadvertent 
    nuclear reaction are highly unlikely. The systems required for 
    maintaining the spent fuel in the spent fuel pool as well as the 
    operations required to contain the remaining residual contamination in 
    the facility and spent fuel pool are relatively simple. Consequently, 
    the activities performed by the licensee during decommissioning do not 
    have a significant potential to impact public health and safety and 
    these require considerably less oversight by the NRC than during power 
    operations.
        The amendments proposed in July 20, 1995 (60 FR 37374), were 
    intended to provide licensees with simplicity and flexibility in 
    implementing the decommissioning process, especially with regard to 
    premature closure. The proposed amendments were intended to clarify 
    ambiguities in the current regulations, codify procedures and 
    terminology that have been used in a number of specific cases, and 
    increase opportunities for the public to become informed about the 
    licensee's decommissioning activities. The amendments were designed to 
    establish a level of NRC oversight commensurate with the level of 
    safety concerns expected during decommissioning activities.
        A. Initial activities. The decommissioning process outlined in the 
    proposed amendments was similar in approach to that in the current 
    decommissioning rule, but included flexibility in the type of actions 
    that can be undertaken without NRC approval. Once a licensee 
    permanently ceases operation of the power reactor, no major 
    decommissioning activities (as defined in the proposed rule) could be 
    undertaken until the public and the NRC were provided information by 
    the licensee. Information required from the licensee in a Post-Shutdown 
    Decommissioning Activities Report (PSDAR) consisted of the licensee's 
    proposed decommissioning activities and schedule through license 
    termination, an assessment of whether such proposed activities are 
    bounded by existing analyses of environmental impacts, and a general 
    decommissioning cost estimate for the proposed activities. The PSDAR 
    would be made available to the public for comment.
        Ninety days after the PSDAR submittal to the NRC and approximately 
    30 days after a public information meeting is held in the vicinity of 
    the reactor site, the licensee could perform major decommissioning 
    activities if NRC does not offer an objection. Before undertaking these 
    activities, the licensee must provide certifications to the NRC that 
    operations have permanently ceased and fuel has been permanently 
    removed from the reactor vessel (elements not formally addressed in the 
    current rule). Once these certifications have been provided to the NRC, 
    the licensee could no longer operate the reactor.
        Part 50 technical requirements would also be amended to properly 
    cover the transition of the facility from operating to permanent 
    shutdown status (which also is not explicitly covered in the current 
    rule). Thus, a licensee who has permanently ceased operations and 
    removed fuel from the reactor vessel would no longer need to obtain a 
    license amendment to proceed with certain decommissioning activities 
    within established regulatory constraints.
        B. Major decommissioning activities. A major change from the 
    current rule is that power reactor licensees would no longer be 
    required to have an approved decommissioning plan before being 
    permitted to perform major decommissioning activities. Under the 
    proposed rule, licensees would be allowed to perform activities that 
    meet the criteria proposed in Sec. 50.59. Section 50.59 would be 
    amended to include additional criteria to ensure that concerns specific 
    to decommissioning are considered by the licensee. Based on NRC 
    experience with licensee decommissioning activities, the Commission 
    recognized that the Sec. 50.59 process used by the licensee during 
    reactor operations encompassed routine activities that are similar to 
    those undertaken during the decommissioning process. The Commission 
    concluded that the Sec. 50.59 process could be used by the licensee to 
    perform major decommissioning activities if licensing conditions and 
    the level of NRC oversight required during reactor operations are 
    continued, commensurate with the status of the facility being 
    decommissioned. These
    
    [[Page 39280]]
    
    objectives were considered in the proposed rule as follows.
        (1) The proposed rule would clarify, modify, and extend certain 
    licensing conditions to decommissioning activities.
        (2) Aside from changes to part 50, the final safety analysis report 
    (FSAR), which is a licensing basis document for performing activities 
    under Sec. 50.59, would need to be updated to cover decommissioning 
    activities.
        (3) A PSDAR would be submitted to the NRC that would contain a 
    schedule of planned decommissioning activities and provide a mechanism 
    for timely NRC oversight. The licensee would provide written 
    notification to the NRC before performing any decommissioning activity 
    that is inconsistent with or makes significant schedule changes from 
    the PSDAR.
        C. License termination. A licensee wishing to terminate its license 
    would submit a license termination plan for approval similar to the 
    approach that is currently required for a decommissioning plan. 
    However, the plan would be less detailed than the decommissioning plan 
    required by the current rule, because it would not need to provide a 
    dismantlement plan, and could be as simple as a final site survey plan. 
    The approval process for the termination plan, as in the current rule, 
    would provide for a hearing opportunity under 10 CFR part 2. The 
    proposed rule recognized that, if the spent fuel is either offsite or 
    in an independent spent fuel storage facility (ISFSI), that is covered 
    under a part 72 license, the remaining facility licensed under part 50 
    is similar to a materials facility and a less formal hearing, under 
    subpart L rather than subpart G of part 2, is more appropriate. As in 
    the current rule, a supplemental environmental report would be required 
    from the licensee that considers environmental impacts that are not 
    already covered in existing EISs. An additional requirement, proposed 
    for the purpose of keeping the public informed, is that a public 
    meeting be held, after the licensee submits the license termination 
    plan to the NRC, similar to the one held after the PSDAR submittal.
        D. Financial assurance. The proposed rule would continue the same 
    degree of financial assurance as the current rule, but provide more 
    flexibility by allowing licensee's limited early use of decommissioning 
    funds. This provision was presented in a draft policy statement 
    entitled ``Use of Decommissioning Trust Funds Before Decommissioning 
    Plan Approval'' (59 FR 5216; February 3, 1994) that was published by 
    the Commission for comment and incorporated into the proposed rule. 
    Currently, licensee use of these funds is determined on a case-specific 
    basis for prematurely shutdown plants. However, the proposed rule 
    eliminated the requirement for a decommissioning plan and instead 
    required a PSDAR submittal, which requires a decommissioning cost 
    estimate. The proposed rule permitted some small percentage (3%) of the 
    generically prescribed decommissioning funds to be available to the 
    licensee for planning purposes (``paper studies'') before permanent 
    cessation of power reactor operations. Moreover, to permit the licensee 
    to accomplish major decommissioning activities promptly, an additional 
    generic funding amount would be made available (20%) before a site-
    specific cost estimate, which must be submitted to the NRC within 2 
    years after permanent cessation of operations (as in the current rule). 
    The remainder of the funds would be made available after submittal of 
    the site-specific cost estimate, as in the current rule. When the 
    licensee submits the license termination plan, the same financial 
    considerations as those in Sec. 50.82(c) of the current rule would be 
    required to provide assurance that the licensee has adequate funds to 
    complete decommissioning and terminate the license.
        E. License extension. The proposed rule clarified that a license 
    that has expired is not terminated until the Commission terminates it 
    and further clarifies what conditions prevail under such circumstances.
        F. Grandfathering. The proposed rule applied to power reactor 
    licensees who do not have an approved decommissioning plan on the 
    effective date of the final rule. Licensees that already have an 
    approved plan could, at their option, follow the provisions of the 
    proposed rule.
        G. Non-power reactors. There were some minor clarifications and 
    procedural simplifications in the proposed rule for the non-power 
    reactor decommissioning process. Otherwise, the current rule remained 
    essentially unchanged.
    
    Response to Comments
    
        Thirty-four comment letters were received on the proposed rule from 
    power reactor licensees, contractors, Government agencies, Agreement 
    States, citizens groups, and individuals. The comment letters have been 
    categorized into two groups representing commenters generally in favor 
    of the proposed rule and those generally not in favor of the proposed 
    rule. The commenters in favor of the rule (24) consisted of power 
    reactor licensees, contractors, Government agencies, and an Agreement 
    State. The commenters not in favor of the rule (10) consisted of 
    citizens groups, individuals, and an Agreement State. The comments have 
    been summarized and addressed through issue categories based on the 
    proposed rule.
        Issue 1--Proposed Rule Approach.
        Comments. Commenters in support of the proposed rule were, to 
    varying degrees, supportive of the proposed rule. There were a few 
    commenters in this group who fully supported the proposed rule because 
    it would facilitate efficient decommissioning of power plants by 
    reducing regulatory burden, clarifying the applicability of regulations 
    originally intended for operating reactors, allowing a phased approach 
    to decommissioning, and allowing early partial use of the 
    decommissioning trust fund. A few commenters supported the use of 
    lessons learned from ongoing decommissioning projects, expanding public 
    participation, and providing the rationale behind less formal NRC 
    policies and practices in a way that satisfies the requirements of the 
    Atomic Energy Act (AEA), Administrative Procedure Act (APA), and 
    National Environmental Policy Act (NEPA).
        While many commenters were generally supportive of the general 
    concept of the proposed rule, they indicated that the proposed rule did 
    not go far enough in reducing unnecessary regulatory burden. They noted 
    that the existing NRC requirements regarding operating reactors were 
    more than adequate to encompass decommissioning activities and, if 
    anything, should be relaxed rather than expanded. These recommended 
    relaxations pertained to such items as a more liberal attitude toward 
    collection and use of decommissioning trust funds, elimination of 
    unnecessary criteria concerning the use of the proposed Sec. 50.59, 
    elimination of proposed mandatory public meetings, elimination of the 
    proposed Post-Shutdown Decommissioning Activities Report (PSDAR) 
    submittal, and elimination of the proposed license termination plan or 
    eliminating its inclusion into the license by amendment, including 
    elimination of the accompanying proposed Subpart L or G hearing 
    opportunity.
        Commenters not in favor of the proposed rule were not supportive of 
    the proposed rule to varying degrees. Many of these commenters were 
    strongly opposed to the proposed rule and indicated that it allowed 
    nuclear power generators to have discretionary
    
    [[Page 39281]]
    
    powers to regulate themselves; that NRC was abdicating its 
    responsibility for protecting the health and safety of workers and the 
    public; that, in allowing the decommissioning plan to be included in 
    the Final Safety Analysis Report (FSAR) it could be revised without 
    license amendment, thereby excluding the public from the process; and 
    that major component removal should not be allowed before the 
    decommissioning plan is approved by the NRC. These commenters expressed 
    a variety of views indicating that the existing rule should be left 
    alone or that the current rule should be left basically in place but 
    made more efficient through better implementation and should include 
    greater opportunities for public participation. Finally, a few 
    commenters indicated that significantly greater public participation 
    and oversight are necessary than that prescribed in the proposed rule.
        Response. The proposed rule was developed to allow more flexibility 
    in dealing with premature closures, the decommissioning process in 
    general, and the experience gained from recent decommissioning 
    activities such as those at Fort St. Vrain, Shoreham, and Rancho Seco, 
    as well as early component removal at Yankee Rowe and Trojan. The 
    justification and intent of the final rule is unchanged. The NRC's 
    primary concern, as the licensee transitions to decommissioning, is 
    that the licensee will have sufficient funds to complete 
    decommissioning and that the activities undertaken by the licensee will 
    protect the public and the environment. The intent of this final rule 
    is to streamline some of the decommissioning requirements for power 
    reactor licensees, especially in approval of the decommissioning plan 
    before major decommissioning activities can be undertaken and in early 
    use of decommissioning trust funds.
        Specific issues addressed in the final rule are discussed in 
    greater detail below.
        Issue 2--PSDAR, FSAR, and update requirements.
        Comments. Commenters in favor of the rule had various comments 
    concerning the PSDAR, its required update, and the proposed update to 
    the FSAR. Several commenters indicated that the PSDAR requirement 
    should be eliminated because it is more stringent than requirements 
    imposed on operating reactors, that the PSDAR should only require 
    information (detailed schedule) pertaining to the current phase of 
    decommissioning because dismantlement and site restoration may not 
    occur for many years, that the word ``synopsis'' should be used to make 
    it clear that the PSDAR is a high-level summary, and that there should 
    be consistency in the criteria for assessing environmental impacts 
    between the PSDAR and the proposed Sec. 50.59 requirements. A few 
    comments suggested making the reporting requirements more efficient by 
    combining them and updating the PSDAR and FSAR together, requiring 
    updates no more than once every 36 months, or using a single PSDAR for 
    multi-reactor sites. Several comments suggested that the updating 
    requirement for the PSDAR be eliminated because Sec. 50.59 already 
    requires annual reporting requirements, that the term ``significant'' 
    used in the proposed Sec. 50.82(a)(6) should be tied to the Sec. 50.59 
    safety evaluation, and that the extent of deviation in the PSDAR 
    schedule that is permissible without notice to the NRC should be 
    clarified. Finally, there was a comment that the final rule should make 
    it clear that, if prompt decommissioning (dismantlement) is being 
    pursued by the licensee, the PSDAR and license termination plan should 
    be permitted to be the same document.
        Commenters not in favor of the rule did not specifically address 
    Issue 2. However, those commenters believed that the current rule 
    requirements should be followed and that an approved decommissioning 
    plan should be required before a licensee is permitted to perform major 
    decommissioning activities.
        Response. The purpose of the PSDAR is to provide a general overview 
    for the public and the NRC of the licensee's proposed decommissioning 
    activities until 2 years before termination of the license. The PSDAR 
    is part of the mechanism for informing and being responsive to the 
    public prior to any significant decommissioning activities taking 
    place. It also serves to inform and alert the NRC staff to the schedule 
    of licensee activities for inspection planning purposes and for 
    decisions regarding NRC oversight activities. Because the final rule 
    eliminates the need for an approved decommissioning plan before major 
    decommissioning activities can be performed, the requirement to submit 
    a PSDAR is less stringent than existing requirements for power reactor 
    licensees.
        The information required to be in the PSDAR is less detailed than 
    the information required in the FSAR. Therefore, the PSDAR should not 
    be combined with the FSAR because the two documents have different 
    purposes. The final rule requires a written notification if activities 
    are anticipated that would be inconsistent with the PSDAR activities 
    previously described. The licensee's consideration of such 
    inconsistency would include any milestone scheduling changes of 
    dismantlement tasks and significant increases in decommissioning costs 
    from those described in the PSDAR. The final rule will explicitly 
    include the requirement that activities that would result in 
    significant increases to decommissioning costs from those presented in 
    the PSDAR must be a consideration in the notification requirements of 
    Sec. 50.82(a)(7). It is intended that regulatory guidance addressing 
    the PSDAR Standard Format and Content will be issued soon after the 
    final rule is published.
        Currently, FSAR updates are required annually or 6 months after a 
    refueling outage provided the interval between updates does not exceed 
    24 months. Because the FSAR is the basis for the use of Sec. 50.59, the 
    updates will need to be timely, so the final rule specifies a 24-month 
    FSAR update for decommissioning activities for those nuclear power 
    reactor licensees that have submitted the certifications of permanent 
    cessation of operation and permanent removal of the fuel from the 
    reactor vessel.
        If prompt decommissioning is desired by the licensee, the licensee 
    could elect early submittal of the PSDAR, before cessation of 
    operation, and then use of Sec. 50.59 would be permitted at cessation 
    of operation, provided the certification of permanent fuel removal from 
    the reactor vessel has been received and the public meeting had been 
    held in advance. Although the PSDAR and license termination plan serve 
    different purposes, and a formal approval process is required of the 
    latter, the PSDAR and license termination plan can be combined. If a 
    licensee chooses to combine the PSDAR and the license termination plan, 
    the requirements for both would apply to the combined document, 
    including the requisite waiting period, public meeting, and approval by 
    amendment of the license termination plan. The procedure for approval 
    of a license termination plan is similar to that currently required for 
    approval of a decommissioning plan. For a multi-reactor site, the PSDAR 
    could address the activities for all the reactors at the site if 
    decommissioning of each will be undertaken at the same time.
        Issue 3--Ninety-Day Time Period Prior to Undertaking Major 
    Decommissioning Activities.
        Comment. Several commenters noted that the proposed 90-day waiting 
    period before major decommissioning activities could be undertaken did 
    not address a
    
    [[Page 39282]]
    
    health and safety concern and that there are potentially high costs 
    associated with such a delay because licensees could do a lot of 
    dismantlement during this time that would be more efficient and cost 
    advantageous. These commenters emphasized that all activities could be 
    carried out under Sec. 50.59 and the current licensing basis. They 
    further stated that, if the 90-day hold is retained, clarification is 
    needed regarding the NRC's opportunity to interpose an objection to 
    proceeding with major decommissioning and that the NRC review should be 
    based on areas of significant safety. Finally, one commenter expressed 
    a concern that the 90-day waiting period would not allow enough time 
    for public participation, including consideration of comments received 
    from the public after NRC notices the licensee's PSDAR submittal and 
    during a public meeting.
        Commenters not in favor of the rule did not specifically address 
    Issue 3. However, those commenters believed that the current rule 
    requirements should be followed and that an approved decommissioning 
    plan should be required before a licensee is permitted to perform major 
    decommissioning activities.
        Response. The commenters have correctly noted that the 90-day 
    waiting period does not just address a health and safety issue. The NRC 
    has chosen a 90-day waiting period prior to allowing major 
    decommissioning activities to occur as the minimal time necessary for 
    the NRC to evaluate the licensee's proposed activities and to conduct a 
    public meeting. The public meeting is informational and may be chaired 
    by a local official, with a presentation of the regulatory process for 
    decommissioning by the NRC, presentation of planned decommissioning 
    activities by the licensee, and participation by State representatives. 
    A question and answer period would follow the presentations. By 
    submitting the PSDAR before cessation of operation, a licensee could 
    reduce the need for a waiting period (see the response to Issue 2 for 
    an additional discussion on ways that the waiting period may be 
    reduced).
        Issue 4--Proposed Rule Modifications to Sec. 50.59.
        Comment. Many commenters approved of some form of the proposed 
    modifications to Sec. 50.59. Many of these commenters noted that 
    Sec. 50.59(e) in the proposed rule is more stringent than the existing 
    requirements for operating reactors. These commenters believed that the 
    existing Sec. 50.59 criteria are adequate. Several commenters stated 
    that the four proposed constraints contained in Sec. 50.59(e) are 
    somewhat redundant to the proposed requirements in Sec. 50.82; the 
    PSDAR content plus update and the 90-day waiting period envelopes 
    issues addressed by these criteria. These commenters believed that if 
    Sec. 50.59(e) criteria were kept they should be in a regulatory guide 
    and not in a rule. Comments specific to the four criteria and why they 
    should be eliminated follow.
        Section 50.59(e)(1)(i) concerning foreclosure of the site for 
    unrestricted release. It was noted that any event that detracts from 
    this effort would be accidental in nature, and that the proposed rule 
    provided no explanation of the types of activities that could result in 
    foreclosing the site for unrestricted use.
        Section 50.59(e)(1)(ii) concerning significantly increasing 
    decommissioning costs. It was noted that cost estimate information is 
    required prior to and through the decommissioning process, making this 
    requirement unnecessary. Moreover, it was asserted that there is no 
    logical correlation between the cost of a decommissioning activity and 
    whether a license amendment should be required for that activity and 
    that costs have never been a consideration in determining whether a 
    proposed activity is consistent with the licensing basis for a plant. 
    It was also noted that other regulatory bodies such as Public Utility 
    Commissions and the Federal Energy Regulatory Commission, as well as 
    economic pressure, will force a licensee to perform decommissioning 
    cost effectively. It was recognized that actions taken by a licensee 
    may diminish the decommissioning fund and it was suggested that the 
    wording be changed to deal with actions that would ``significantly 
    inhibit the ability to fund decommissioning costs which would prevent 
    successful decommissioning.''
        Section 50.59(e)(1)(iii) concerned environmental impacts not 
    previously reviewed. It was noted that compliance with the operating 
    license, technical specifications, and Sec. 50.59 regarding unreviewed 
    safety questions adequately preclude having significant adverse 
    environmental impact that have not been reviewed. Moreover, the 
    requirement is redundant to the requirement concerning unreviewed 
    environmental impacts required in the content of the PSDAR specified in 
    Sec. 50.82.
        Section 50.59(e)(1)(iv) concerned violating the terms of the 
    existing license. It was noted that this requirement is redundant with 
    language in Sec. 50.59(a) that allows licensees to proceed with an 
    activity so long as it does not violate technical specifications or 
    constitute an unreviewed safety question as defined by 
    Sec. 50.59(a)(2). Also, it was noted that a license amendment is 
    required for changes in technical specifications under the current 
    Sec. 50.59(c).
        Most commenters who opposed the use of proposed Sec. 50.59 were not 
    in favor of the rule. One commenter stated that the analysis of the 
    dismantlement activities proposed under Sec. 50.59 to determine whether 
    or not the activity generates any unreviewed safety issue should be 
    provided to the NRC, rather than rely on an NRC audit as existing 
    regulations provide. This analysis would also provide this information 
    to the public for examination. Several of the commenters indicated that 
    an after-the-fact review of Sec. 50.59 activities would provide 
    insufficient regulatory protection. Finally, a commenter stated that 
    the presence of an NRC inspector is essential during decommissioning 
    activities.
        Response. The Commission concluded that the proposed 
    Sec. 50.59(e)(1)(iv) is redundant and should be eliminated from the 
    final rule. The Commission reconsidered the need for the remaining 
    Sec. 50.59(e)(1) requirements and determined that placing them in 
    Sec. 50.82 would be more appropriate. The Commission also concluded 
    that the requirement ensuring that no major decommissioning activities 
    occur that would significantly increase decommissioning cost could be 
    overly burdensome. Instead, an appropriate constraint would be to 
    prohibit any decommissioning activities that result in there no longer 
    being reasonable assurance that adequate funds will be available for 
    decommissioning. However, the NRC needs to be aware of changes in 
    decommissioning activities that would result in significantly 
    increasing decommissioning costs and would require written notification 
    of such intended actions. The other paragraphs in Sec. 50.59(e) were 
    placed in Sec. 50.82(a) to ensure that they will be considered as 
    overall constraints on the licensee's decommissioning activities, 
    rather than separately for each contemplated activity as proposed in 
    Sec. 50.59(e).
        The purpose of retaining these requirements is to ensure that no 
    decommissioning activities can occur that result in: (1) Eliminating 
    the potential for unrestricted release, (2) significant environmental 
    impacts not previously considered in EISs, and (3) there no longer 
    being reasonable assurance that adequate funds will be available for 
    decommissioning. The basis for this final rule permitting the
    
    [[Page 39283]]
    
    use of Sec. 50.59 activities to perform decommissioning activities is 
    that environmental impacts have already been considered and that such 
    consideration was for an unrestricted release condition where the 
    licensee has sufficient funds to complete decommissioning (see final 
    generic environmental impact statement (FGEIS), NUREG-0586).1 The 
    major considerations of licensee decommissioning activities that could 
    significantly affect the environment are at the license termination 
    stage when the licensee submits a license termination plan for 
    approval.
    ---------------------------------------------------------------------------
    
        \1\ NUREG-0586, ``Final Generic Environmental Impact Statement 
    on Decommissioning of Nuclear Facilities,'' USNRC, August 1988. 
    Copies are available for inspection or copying for a fee from the 
    NRC Public Document Room 2120 L Street NW. (Lower Level), 
    Washington, DC; the PDR's mailing address is Mail Stop LL-6, 
    Washington, DC 20555-0001; telephone (202) 634-3273; fax (202) 634-
    3343.
    ---------------------------------------------------------------------------
    
        If a licensee contemplates decommissioning activities that would 
    violate these requirements, the licensee may not use the Sec. 50.59 
    process delineated in this rule to perform the activities. The licensee 
    would then be required to obtain a license amendment to perform the 
    activities.
        The final rule prohibits licensees from performing any 
    decommissioning activities that foreclose release of the site for 
    possible unrestricted use, result in significant environmental impacts 
    not previously reviewed, or result in there no longer being reasonable 
    assurance that adequate funds will be available for decommissioning 
    (Sec. 50.82(a)(6)). Prior to the licensee's use of the Sec. 50.59 
    process to perform major decommissioning activities, the PSDAR 
    submittal and public information process must be completed. The 
    licensee is required to include a discussion that provides the reasons 
    for concluding that the environmental impacts that might occur during 
    decommissioning activities have already been considered in site-
    specific or generic environmental impact statements, and to estimate 
    the amount of funds necessary to complete decommissioning (see 
    Sec. 50.82(a)(4)).
        The licensee is also required to submit a site-specific cost 
    estimate within 2 years after permanent cessation of operations. Use of 
    decommissioning trust funds are subject to the requirements (in 
    Sec. 50.82(a)(8)) that adequate funds will be available to ultimately 
    release the site and terminate the license. Moreover, the final rule 
    requires the licensee to notify the NRC in writing before performing 
    any decommissioning activity inconsistent with, or making any 
    significant schedule change from, those actions and schedules described 
    in the PSDAR and states that this notification include consideration of 
    significant increases in decommissioning costs (Sec. 50.82(a)(7)).
        The NRC intends to maintain an active inspection program to provide 
    the requisite level of oversight of licensee activities during 
    decommissioning. The PSDAR and any written notification of changes 
    required of a licensee will be used to schedule NRC inspection 
    resources for significant decommissioning activities.
        In addition to continuing requirements that the licensee must 
    comply with, such as 10 CFR part 20, regarding protection of workers 
    and the public from radiation, and appendix B to 10 CFR part 50 
    regarding quality assurance, the final rule explicitly extends certain 
    technical requirements to cover decommissioning activities (e.g., 
    Secs. 50.36, 50.36a, 50.36b, and Appendix I regarding technical 
    specifications for surveillance requirements, administrative controls, 
    control of effluents, and conditions to protect the environment). Thus, 
    there will be a licensing basis appropriate to the activities 
    undertaken using the Sec. 50.59 process during decommissioning. By 
    maintaining certain requirements throughout the decommissioning 
    process, licensees will be able to use the existing Sec. 50.59 process 
    to perform decommissioning activities and thus provide comparable 
    assurance that protection of the public health, safety, and the 
    environment will not be compromised.
        Issue 5--Environmental Impact Considerations During the Initial 
    Phase of Decommissioning.
        Comments. Many commenters in favor of the rule fully supported the 
    environmental impact considerations delineated in the proposed rule for 
    the PSDAR submittal, with no mandatory ER or subsequent EA requirement. 
    A few commenters suggested that no environmental impacts for 
    decommissioning need be addressed further because the FGEIS for the 
    1988 decommissioning rule (NUREG-0586, August 1988) \1\ and subsequent 
    environmental assessments (for various actual power reactor 
    decommissioning situations) demonstrate that decontamination and 
    dismantlement do not significantly affect the human environment and 
    have beneficial effects in restoring the site to an environmentally 
    acceptable condition. A few commenters suggested that decommissioning 
    should be considered a categorical exclusion as defined in 10 CFR 
    51.22.
        Most of the commenters who were not in favor of the rule believed 
    that the NRC should define decommissioning as a major Federal action 
    requiring an EA or EIS. They further indicated that a generic 
    environmental impact statement cannot substitute for a site-specific EA 
    because the FGEIS does not consider all possibilities. A few of these 
    commenters further stated that the proposed environmental impact 
    consideration process is NRC's attempt to streamline the process for 
    utilities and deregulate NRC current requirements. A few commenters 
    stated that the process outlined in the proposed rule abdicates NRC's 
    responsibility to protect the health and safety of the workers, the 
    public, the environment, and it also undermines citizen's due process.
        Response. While the FGEIS (NUREG-O586) \1\ for the 1988 
    decommissioning rule concluded that only minor negative environmental 
    impacts would result from decommissioning in addition to substantial 
    positive environmental impacts, it did not address site-specific 
    situations that could differ from the assumptions used in the FGEIS 
    analysis. However, it is expected that any site impacts will be minor. 
    Any site impact should be bounded by the impacts evaluated by previous 
    applicable GEISs as well as any site-specific EIS. To account for site-
    specific situations that may occur outside these environmental impact 
    considerations, the final rule prohibits major decommissioning 
    activities that could result in significant environmental impacts not 
    previously reviewed. The review process for the PSDAR and the approval 
    process for the license termination plan requires licensees to review 
    the existing documents and address any discrepancies in their 
    submittals.
        The environmental assessment conducted for this rulemaking relied 
    on the FGEIS for the decommissioning rule (NUREG-0586, August 1988) \1\ 
    and determined that, insofar as the rule would allow major 
    decommissioning activities (dismantlement) to proceed without an 
    environmental assessment, application of the rule will not have a 
    significant impact on the environment. Although not required by NEPA, 
    NRC has required in this final rule that licensees indicate in the 
    PSDAR the reasons for concluding that the planned activities are 
    bounded by the FGEIS and previous site-specific environmental impact 
    statements. This requirement is consistent with one of the primary 
    goals of the PSDAR process, which is to promote public knowledge and 
    provide an opportunity to hear public views on decommissioning 
    activities before licensees commence decommissioning.
    
    [[Page 39284]]
    
        At the license termination stage, the Commission must make 
    decisions on the licensee-proposed actions described in the license 
    termination plan. The Commission must consider:
        (1) The licensee's plan for assuring that adequate funds will be 
    available for final site release,
        (2) Radiation release criteria for license termination, and
        (3) The adequacy of the final survey required to verify that these 
    release criteria have been met.
        Therefore, the NRC has determined that submittal of the license 
    termination plan should be treated as a license amendment. In addition, 
    under 10 CFR part 51, an environmental assessment or impact statement 
    would be required at the time the license is amended. Following 
    resolution of another ongoing NRC rulemaking activity that is 
    considering adoption of radiological release criteria, a categorical 
    exclusion may be adopted that would eliminate the requirement for an 
    environmental assessment or impact analysis, except in the case of a 
    restricted release of a site.
        Issue 6--Public Participation.
        Comment. Most commenters supporting the rule commented on the 
    public participation aspects of the proposed rule. They believed that 
    the participatory role given to the public was appropriate, excessive, 
    or in need of further clarification. Several questioned the need for 
    expanded public participation on matters of public health and safety 
    because the NRC regulatory framework already provides for such 
    participation (e.g., license amendment process). These commenters also 
    noted that the purpose of the public meeting following the PSDAR 
    submittal was not properly explained and that the final rule should 
    clearly state that the meeting is intended for exchange of information 
    only. Many commenters indicated that the NRC should limit the scope of 
    these meetings and hearings to issues that are related to health and 
    safety during the decommissioning process. These commenters also 
    indicated that the supplementary information should include a clear 
    statement of the purpose and participation guidelines for these 
    meetings and clearly identify NRC's role at these meetings (which 
    should be significant). A comment stated that it is essential that 
    adequate mechanisms be developed for addressing issues of concern 
    raised by members of the public and that, absent such closure, the 
    meeting would only compound frustrations felt by the interested public. 
    Finally, there was a comment that the 90-day waiting period (after the 
    submittal of the PSDAR to the NRC) before allowing licensees to 
    undertake major decommissioning activities may not allow enough time 
    for adequate public participation.
        Most commenters who did not favor the rule believed that the public 
    participatory role proposed was inadequate. These commenters stated 
    that NRC should retain the possession-only license amendment (POLA) and 
    decommissioning plan approval required in the current rule to truly 
    enhance public participation. Public meetings were considered helpful, 
    but no substitute for an adjudicatory hearing that includes the rights 
    to discovery, to present evidence, and to cross examine. Along these 
    lines, a commenter stated that a meeting does not afford citizens the 
    level of institutional accountability necessary, given the dangers of 
    environmental-toxic contamination inherent in reactor decommissioning 
    activities and that citizens must have a substantive role in the 
    decommissioning process in order to clarify, negotiate, and protect 
    their community's interest. A few commenters suggested that site-
    specific advisory boards (SSABs) should be established early in the 
    decommissioning process and that meaningful public involvement should 
    be required at every stage of the decommissioning process, not only at 
    the final termination stage.
        Response. As discussed previously, initial decommissioning 
    activities (dismantlement) are not significantly different from routine 
    operational activities such as replacement or refurbishment. Because of 
    the framework of regulatory provisions embodied in the licensing basis 
    for the facility, these activities do not present significant safety 
    issues for which an NRC decision would be warranted. Therefore, it is 
    appropriate that the licensee be permitted to conduct these activities 
    without the need for a license amendment. However, the information 
    meetings will be beneficial in keeping the public informed of the 
    licensee's decommissioning activities. Although the primary purpose of 
    these meetings is to inform the public of the licensee's planned 
    activities, the NRC will consider public health and safety comments 
    raised by the public during the 90-day period before the licensee 
    undertakes decommissioning activities.
        A more formal public participation process is appropriate at the 
    termination stage of decommissioning because the final disposition of 
    the site is determined at that time. Under the current rule, the 
    Commission issues an order permitting the reactor to be decommissioned, 
    based on the approved decommissioning plan, which amends the license. 
    NRC administrative procedures, in subpart G of 10 CFR part 2, now 
    provide an opportunity for persons to request a hearing regarding the 
    NRC's decision. A similar procedure will be followed in the final rule 
    for the license termination plan once the licensee has permanently 
    removed fuel from the site. However, the hearing will be less formal 
    because it will follow the procedures in Subpart L of 10 CFR part 2. 
    The role of the SSABs will be evaluated when the rulemaking regarding 
    radiological release criteria for license termination is finalized.
        Issue 7--Establishment and Use of the Decommissioning Trust Fund.
        Most of the commenters on this issue were in favor of the rule. 
    These commenters requested greater flexibility in what costs can be 
    included in the fund, such as disposal costs of radioactive waste from 
    plant operations, and greater flexibility in the use of the trust funds 
    prior to and during decommissioning. Specific comments that reflect the 
    full range of comments on financial issues are:
        Comment a. The proposed Sec. 50.82(a)(7) proposes to regulate a 
    licensee's use of, and rate of withdrawal from, the decommissioning 
    trust fund. While NRC oversight is warranted to ensure that 
    decommissioning activities can be funded, regulating the rate of 
    withdrawal from the trust fund may unnecessarily impede the efficiency 
    of a licensee's decommissioning activities. Because the NRC's generic 
    estimates of decommissioning costs are substantially lower than most 
    recent site-specific cost estimates, licensees would be constrained to 
    withdraw small fractions of an unrealistically low estimate.
        Response. Limiting initial withdrawals to 23 percent of the generic 
    cost estimate (using the Sec. 50.75 requirements), until the licensee 
    has submitted a site-specific decommissioning cost estimate, preserves 
    the integrity of the decommissioning trust accounts. The final rule 
    permits licensees to withdraw up to 3 percent of the generic formula 
    amount for planning at any time during the decommissioning planning 
    process, including planning that occurs while a plant is still 
    operating. This amount should be ample based on current planning costs 
    for licensees recently undergoing decommissioning. Likewise, allowing 
    withdrawals of 20 percent of the generic amount for decommissioning 
    activities would allow funding of certain activities before receipt of 
    a site-specific cost estimate. This amount is consistent with costs of 
    large component removal activities undertaken or contemplated by
    
    [[Page 39285]]
    
    licensees of shutdown plants (e.g., Yankee-Rowe and Trojan). Once the 
    NRC has received the site-specific decommissioning cost estimate, a 
    licensee would have access to the balance of trust fund monies for the 
    remaining decommissioning activities. Because the timing of the 
    submittal of a site-specific cost estimate is within the control of the 
    licensee, the Commission believes that unwarranted restraints on access 
    to funds are not imposed by the final rule.
        Comment b. The scope of decommissioning-related activities that 
    licensees may collect funds for should include disposal of low-level 
    waste generated during operations, maintenance and storage of spent 
    fuel after cessation of operations, costs to maintain an independent 
    spent fuel storage installation, and non-radioactive demolition or 
    ``greenfield.'' State Public Service Commissions and the Federal Energy 
    Regulatory Commission have authorized funding for these activities in 
    some cases because it is in the best interests of the utilities' 
    customers. The NRC regulation should not require segregation of these 
    funds in separate accounts; restrictions on the withdrawal of trust 
    funds in the proposed rule could lead utilities to create separate 
    trust accounts for each nuclear facility funding component (e.g., 
    decommissioning, spent fuel management, and greenfield). Finally, the 
    rule should allow for the prudent and economic use, at the utility's 
    discretion, of decommissioning trust funds during the years of normal 
    plant operation even before end of life.
        Response. The NRC's authority is limited to assuring that licensees 
    adequately decommission their facilities with respect to cleanup and 
    removal of radioactive material prior to license termination. 
    Radiological activities that go beyond the scope of decommissioning, as 
    defined in Sec. 50.2, such as waste generated during operations or 
    demolition costs for ``greenfield'' restoration, are not appropriate 
    costs for inclusion in the decommissioning cost estimate. Funds for 
    interim spent fuel storage and maintenance are addressed in 
    Sec. 50.54(bb).
        The final rule does not prohibit licensees from having separate 
    sub-accounts for other activities in the decommissioning trust fund if 
    minimum amounts specified in the rule are maintained for radiological 
    decommissioning.
        Comment c. Section 50.82(a)(7)(ii) of the proposed rule specifies 
    that a site-specific decommissioning cost estimate must be submitted to 
    the NRC prior to the licensee being permitted to use any funding in 
    excess of previously stipulated amounts. This could be interpreted to 
    mean that the NRC must approve the additional expenditures. If this 
    paragraph is retained, the intent of this ``permitting'' should be made 
    clear. Expenditures made in accordance with the PSDAR and the 
    decommissioning cost estimate should not require any additional NRC 
    authorization.
        Response. The NRC's intent in the proposed rule was not to use a 
    formal approval mechanism for decommissioning expenditures once the 
    licensee submits its site-specific decommissioning cost estimate. The 
    final rule has been modified as suggested by the commenter.
        Comment d. More guidance should be provided regarding what 
    constitutes a decommissioning ``planning'' expenditure. Changes in the 
    proposed rule regarding expenditure of funds from the NRC Draft Policy 
    Statement on use of decommissioning funds before decommissioning plan 
    approval (59 FR 5216; February 3, 1994), should be more fully 
    explained.
        Response. The term ``planning'' used in Sec. 50.82(a)(8)(ii) 
    specifically means ``paper'' studies, not equipment removal. 
    Percentages are used in the final rule rather than specific dollar 
    amounts, as used in the Draft Policy Statement, to better allow for 
    inflation of costs in the future. Other changes to the Draft Policy 
    Statement are based on the response to comments, developed prior to 
    this rulemaking activity, and presented in the section on the 
    ``Resolution of Comments on the Draft Policy Statement.''
        Comment e. If a plant shuts down early, not only will there be 
    insufficient funds to pay for planned decommissioning (because not all 
    payments will have been made), but the actual cost of decommissioning 
    can be 2 to 3 times higher than planned. The NRC should require 
    external funds in the amount necessary to complete decommissioning 
    upfront. Moreover, the NRC does not have a procedure in place for 
    ``replacing'' a reactor licensee that goes bankrupt. Finally, the NRC 
    should specifically allow the total financial approach to be made along 
    the lines of industry self-insurance.
        Response. The revised regulations preserve the integrity of the 
    decommissioning funds by tying the rate of expenditure to specific 
    parts of the decommissioning process. At the same time they allow broad 
    flexibility once a licensee submits its site-specific decommissioning 
    cost estimate.
        The issue of bankruptcy, as well as the requirement for power 
    reactor licensees to have the total amount of decommissioning funds 
    upfront, was considered during the development of the current rule and 
    found to be adequately addressed in current requirements. Bankruptcy 
    does not necessarily mean that a power reactor licensee will liquidate. 
    To date, the NRC's experience with bankrupt power reactor licensees has 
    been that they file under Chapter 11 of the Bankruptcy Code for 
    reorganization, not liquidation (e.g., Public Service Company of New 
    Hampshire, El Paso Electric Company, and Cajun Electric Cooperative). 
    In these cases, bankrupt licensees have continued to provide adequate 
    funds for safe operation and decommissioning, even as bondholders and 
    stockholders suffered losses that were often severe. Because electric 
    utilities typically provide an essential service in an exclusive 
    franchise area, the NRC staff believes that, even in the unlikely case 
    of a power reactor licensee liquidating, its service territory and 
    obligations, including those for decommissioning, would revert to 
    another entity without direct NRC intervention. However, the NRC 
    believes that with electric utility deregulation becoming more likely, 
    it may need to require additional decommissioning funding assurance for 
    those licensees that are no longer able to collect full decommissioning 
    costs in rates or set their own rates. Thus, the NRC proposed a 
    rulemaking plan to, in part, evaluate these developments in SECY-95-223 
    (September 1, 1995).
        Issue 8--Court decision.
        Comment. Most commenters who were in favor of the rule indicated 
    that the proposed rule did not conflict with the recent court decision 
    regarding the Yankee Rowe decommissioning (Citizens Awareness Network, 
    Inc. v. NRC, 59 F.3d 284 (1st Cir. 1995)). Most of the commenters who 
    were not in favor of the rule believed that the proposed rule violated 
    the court's decision, or the spirit of the decision, regarding Yankee 
    Rowe.
        Response. A significant basis for the court's decision was that it 
    perceived that the Commission had not adequately provided the reasoning 
    for the NRC decision to allow decommissioning activities before NRC 
    approval of a licensee-submitted decommissioning plan (59 F.3d at 291-
    292), a decision that the court considered to be a modification of the 
    Commission's decommissioning regulations. The court noted that the 
    Commission had failed to provide either a rulemaking proceeding or a 
    hearing to address what the court perceived to be NRC approvals of 
    licensee decommissioning activities (59 F.3d at 291-92, 294-95). By 
    initiation of
    
    [[Page 39286]]
    
    a notice of proposed rulemaking and solicitation of comment (July 20, 
    1995; 60 FR 37374), the Commission addressed the reasoning underlying 
    the proposed decommissioning process and allowed public review and 
    comment on that reasoning.
        The final rule includes a public notice and meeting process, 
    prompted by the licensee's submission of a report describing planned 
    decommissioning activities, to hear public views before the licensee 
    undertakes major decommissioning activities. This process specifically 
    provides that licensees may not begin major decommissioning activities 
    until after they have submitted a PSDAR. The PSDAR will be made 
    available to the public for written comment and a public meeting will 
    be held to hear public views. Finally, the licensee is required to 
    submit a license termination plan before release of the site. The final 
    rule specifies that the license termination plan be approved by the NRC 
    through the license amendment process. This process provides the public 
    with hearing opportunities and ensures that any hearing on that plan 
    must be completed prior to release of the site. This procedural 
    framework assures that those citizens living near the site, potentially 
    for years or decades after the facility is shut down, will be provided 
    with information regarding the licensee's planned decommissioning 
    activities, have an opportunity to ask questions regarding those 
    activities at a public meeting early in the process, and have timely 
    input into the decision to release the site.
        In its decision, the court also specifically addressed a concern 
    about decommissioning activities taking place prior to any NEPA 
    analysis (59 F.3d at 292-93). The final rule addresses this issue in 
    several respects. First, the final rule explicitly prohibits the 
    licensee from performing any major decommissioning activity that 
    results in significant environmental impacts not previously reviewed or 
    forecloses possible unrestricted release of the site.
        Also, when the licensee submits the PSDAR, the licensee must 
    specifically include a section discussing how the planned activities 
    fit within the envelope of environmental effects included in either the 
    FGEIS (NUREG-0586, August 1988) \1\ or the facility's site-specific 
    environmental impact statement. Moreover, the licensee must provide 
    written notification if the intended decommissioning activities are 
    inconsistent with the PSDAR. This requirement helps ensure that, after 
    submittal and public comment on the PSDAR, any changes to the planned 
    decommissioning activities continue to be enveloped by the assessment 
    of environmental impacts in prior environmental reviews. Any activities 
    not meeting the environmental criteria would require the licensee to 
    file an application for amendment to the license and a supplement to 
    its environmental report under 10 CFR part 51. Finally, the rule 
    requires a formal license termination plan by the licensee. The 
    activities in the licensee's plan which do not meet the environmental 
    criteria must be approved by the NRC by a license amendment that 
    follows NRC procedures for amendments, including applicable hearing 
    rights (under either subpart L or subpart G of 10 CFR part 2, as 
    specified in the rule) and the preparation of environmental 
    assessments.
        The court perceived that the agency ``approval'' of the expenditure 
    of funds from the decommissioning funds may be a basis for triggering 
    both NEPA reviews and hearing rights (59 F3d at 292-95). The final rule 
    addresses this issue by providing generic guidance as to what 
    expenditures can be made out of the decommissioning fund for 
    decommissioning activities before submittal of a site-specific cost 
    estimate. The revised regulations use generic criteria for expenditures 
    from the decommissioning funds and do not require prior NRC approval of 
    site-specific expenditures meeting the generic criteria (see 
    Sec. 50.82(a)(7)). These new provisions specifically require licensees 
    to maintain sufficient funds for release of the site and termination of 
    the license. The licensee will have to also include an updated, site-
    specific analysis of remaining costs in the license termination plan 
    submittal.
        In publishing this final rule, the Commission has explained the 
    rationale for the new decommissioning process, and has concluded that 
    nothing in the court decision dictates that the Commission take a 
    specific approach to this issue or otherwise raises questions 
    concerning the validity of the approach adopted in this rulemaking.
        Issue 9--Definitions.
        Comment. Regarding the definitions in Sec. 50.2, a few commenters 
    indicated that the definition of decommissioning should include the 
    concept of restricted release to accommodate the proposed rulemaking on 
    acceptable residual radioactive criteria for decommissioning. Several 
    commenters noted that the definitions of ``major radioactive 
    components'' and ``major decommissioning activities'' were unnecessary 
    because the use of the existing Sec. 50.59 process does not require 
    these considerations and is adequate to deal with decommissioning 
    activities. However, if a definition of ``major radioactive 
    components'' must be kept, the definition should only be relevant to 
    any components, that when dismantled for shipment, contain greater than 
    class C waste. During decommissioning activities, these waste disposals 
    have the greatest significance regarding environmental impacts and 
    adequate funding and are unrelated to the physical size of components.
        Response. When the residual radiation criteria rule is final, the 
    definition of decommissioning in Sec. 50.2 will address use of the 
    restricted release. It is necessary to have definitions of ``major 
    radioactive components'' and ``major decommissioning activities'' to 
    clarify what decommissioning activities may not occur before the end of 
    the 90-day waiting period. However, the definition of ``major 
    radioactive components'' in the final rule has been clarified so that 
    large components, other than those named, are not prohibited Sec. 50.59 
    activities if they contain small amounts of radioactivity. 
    Dismantlement of these components is considered part of routine 
    operating nuclear power reactor activities.
        Issue 10--Modifications to Specific Technical Requirements.
        Comment. Most of the commenters addressing this issue were in favor 
    of the rule and indicated that there should be additional elimination 
    or modification of requirements beyond those presented in the proposed 
    rule. There was a spectrum of views on this issue: if a risk analysis 
    were performed, it would demonstrate that the proposed rule would 
    impose unnecessary burden on NRC licensees and NRC resources without 
    commensurate benefit to health and safety; appropriate technical 
    specifications for decommissioning would be for those activities for 
    which there is a significant hazard; the final rule should include a 
    discussion of the logic (i.e., philosophy) in making conforming 
    revisions to part 50, especially with respect to provisions that did 
    not change (e.g., Secs. 50.55a, 50.63, 50.72, and 50.73 applicability); 
    the study and survey by the NRC concerning additional amendments for 
    non-applicability should be completed before this rule is finalized 
    (one commenter); and that the proposed rule appears geared to 
    permanently shut down reactors with fuel onsite and does not 
    differentiate among the aspects that apply once fuel is removed from 
    the site, and the rule should consider such situations. Finally, one 
    commenter requested that environmental qualifications remain in place 
    for equipment important to safety
    
    [[Page 39287]]
    
    pertaining to spent fuel management and storage.
        Response. This rulemaking is primarily directed toward the 
    procedural process for decommissioning, with particular emphasis on 
    premature closure situations. The modifications to technical 
    requirements in the final rule are based on a consequence analysis that 
    either leads to elimination of the requirement or extends its 
    applicability to decommissioning.
        The modifications to the technical requirements in the final rule 
    are incomplete, as noted in the proposed rule, and as the information 
    base continues to develop, additional rulemaking actions to modify 
    other requirements will be conducted. In the interim, licensees that no 
    longer have fuel onsite may continue to request exemption for specific 
    requirements on a case-by-case basis. The information base will address 
    the storage of high-density packaging of hot spent fuel in the spent 
    fuel pool with special consideration given to potential radiological 
    consequences that could occur from loss of coolant in the pool. 
    Consideration for amending rule requirements is also being given to 
    situations in which the fuel is in dry storage at an Independent Spent 
    Fuel Storage Installation (ISFSI).
        Comments on specific amendments were:
        Comment: Part 26. The final rule should explicitly state that the 
    fitness for duty program does not apply to a permanently shut down and 
    defueled facility. If it must apply, then it should apply to persons 
    with unescorted access to the fuel storage building or buildings 
    containing equipment necessary for the safe storage and handling of 
    spent fuel.
        Response. Consideration of this issue is ongoing and may result in 
    future rulemaking. However, until a decision is made, part 26 continues 
    to be applicable.
        Comment: Section 50.36. Criteria are needed to ensure that 
    technical specifications are appropriate for the conditions of a plant 
    in a defueled state. The four criteria specified in Sec. 50.59(e) would 
    be appropriate additional guidance.
        Response. Consideration will be given at a later time to the 
    development of additional guidance in the form of standardized 
    technical specifications for decommissioning. However, licensees may 
    apply for modification of their technical specifications on a case-by-
    case basis.
        Comment: Section 50.36 (c)(6) and (e). These requirements, which 
    appear to imply that a new set of technical specifications will be 
    developed for the plant decommissioning phase, are redundant and should 
    be eliminated because Sec. 50.51(b)(2), the requirement to conduct 
    activities in accordance with the specific part 50 license for the 
    facility, is sufficient to ensure effectiveness of the technical 
    specifications.
        Response. As a reactor facility transitions from operational to 
    decommissioning status, numerous changes to technical specifications 
    are expected. The regulatory experience with revisions to the technical 
    specifications during this transition period has entailed case-specific 
    evaluations of individual licensee requests. This has resulted in some 
    inconsistency and variability of expectations among shutdown reactor 
    facility license requirements. This revision provides the basis for 
    developing a consistent framework for the development of ``standardized 
    technical specifications for decommissioning,'' as well as addresses 
    the uncertainty regarding the applicability of the existing regulation 
    to permanently shutdown reactors. Section 50.51 specifically addresses 
    the continued effectiveness of expired licenses and limitation of 
    licensee actions during any continued effectiveness period. As such, 
    Sec. 50.51 does not, nor is it intended to, provide specific license 
    conditions and requirements. Section 50.36 addresses this issue.
        Comment: Section 50.36a(a)(1). This requirement should be clarified 
    and revised because radioactive waste systems will have to be removed 
    prior to license termination, and the present wording appears to 
    require that these systems be used and maintained. Moreover, temporary 
    systems are typically used for effluent treatment and the rule should 
    be modified to describe only those systems that are appropriate.
        Response. Section 50.36a(a)(1) is intended to ensure that operating 
    procedures for any waste treatment systems used to control effluents be 
    maintained and used to existing release criteria, and not that the 
    systems be used and maintained when no longer necessary. However, in 
    response to the comment, Sec. 50.36a(a)(1) has been modified from the 
    proposed rule so that systems that are no longer necessary can be 
    eliminated from compliance requirements.
        Comment: Section 50.47. A defueled plant that has ceased operation 
    warrants a material reduction in the scope of its offsite emergency 
    planning requirements because the credibility of any offsite 
    consequences are reduced. Beyond the spent fuel pool, there is not 
    sufficient source term to justify emergency plans. This also pertains 
    to appendix E to part 50 and the requirements in Sec. 50.54(t) 
    concerning periodic review (frequency and scope) of the licensee's 
    emergency preparedness program.
        Response. Consideration of the potential radiological consequences 
    of hot, high-density packaged fuel in the spent fuel pool is still 
    ongoing. Modifications to this requirement, if made, will be developed 
    at a later time.
        Comment: Section 50.48. While some commenters agreed with the 
    concept of a fire protection plan through the end of decommissioning, 
    one found the proposed language overly restrictive, vague, and 
    ambiguous. This commenter stated that once the permanently removed 
    spent fuel is certified to no longer be a fire protection concern, an 
    industrial fire protection program could be adequate in most cases. 
    Several other commenters noted that there are other ongoing NRC 
    activities to improve current fire protection regulations, and if 
    actions are taken now, they should only be based on ``significant 
    hazards'' considerations.
        Response. These modified requirements have been coordinated with 
    ongoing NRC activities regarding the improvement of fire protection 
    regulations. Also, see the response to Sec. 50.47 regarding spent fuel 
    considerations. As presently configured, fire protection regulations 
    apply only to operating reactor facilities. The need for an ongoing 
    fire protection program, albeit a modified one, remains after the 
    facility has ceased reactor operations. The final rule provides a 
    performance-based program that can readily be modified during the 
    decommissioning process to address residual hazards.
        Comment: Section 50.49. Electric equipment required for protection 
    of spent fuel outside the reactor does not meet the definition of 
    equipment defined by Sec. 50.49(b). The discussion in the final rule 
    should be corrected to note that the environmental qualifications 
    regulations apply to selected safety and non-safety related equipment 
    as described in Sec. 50.49(b).
        Response. No modifications to the proposed rule are necessary. 
    However, the environmental qualifications regulations apply to selected 
    safety and non-safety related equipment as described in Sec. 50.49(b).
        Comment : Section 50.51. Section 50.51(b) should be deleted because 
    it is redundant. If it is kept, the requirements on the continuation of 
    a license should be clarified to affirm that other operating reactors 
    would be unaffected
    
    [[Page 39288]]
    
    when the operating license of one reactor has been terminated at a 
    multi-reactor site. Section 50.51(b)(1) should be clarified to indicate 
    that, at sites that have an intervening reuse but do not require 
    decontamination to unrestricted release, decontamination would not need 
    to occur until the end of the reuse period.
        Response. Section 50.51(b) is not redundant and will not be 
    deleted. This section in the final rule has been modified to clarify 
    that an expired license for a nuclear reactor facility that has 
    permanently ceased operations is not terminated until the Commission 
    terminates it. This provision further clarifies what conditions prevail 
    under such circumstances. At a multi-reactor site, each reactor is 
    individually licensed and actions are applied accordingly. The final 
    rule addressing the radiological criteria for decommissioning will 
    address the issue of restricted release options. Under the proposed 
    rule, such restrictions would have to ensure that members of the 
    public, in the event the restrictions fail, would not receive a dose in 
    excess of 100 mrem per year. Unless the facility remained under 
    license, individuals having access to the facility would be considered 
    members of the public.
        Comment: Section 50.54(g). The antitrust law requirements for a 
    reactor that has permanently ceased operations and permanently defueled 
    should be reevaluated for applicability.
        Response. Section 50.54(g) simply provides that the issuance of an 
    NRC license does not relieve the licensee from compliance with the 
    antitrust laws specified in Section 105 of the Atomic Energy Act, and 
    that the NRC may take appropriate action, including suspension or 
    revocation of the license, if a court finds the licensee to have 
    violated any provisions of such antitrust laws. This subsection of the 
    regulation is sufficiently flexible that there is no reason to modify 
    or delete it with respect to a facility that has ceased operations or 
    is permanently defueled.
        Comment: Paragraphs (k), (l), and (m) of Sec. 50.54. The 
    requirement for licensed operators should be eliminated or reduced 
    because reactivity changes can only occur during the initial stages of 
    decommissioning in connection with repositioning fuel assemblies in the 
    spent fuel pool. With reference to Sec. 50.54(i), the scope of the 
    operator requalification program and limitations on a licensee's 
    freedom to modify it should be reduced at facilities undergoing 
    decommissioning.
        Response. Consideration of these issues is ongoing and may result 
    in future rulemaking.
        Comment: Section 50.54(w). Onsite property damage insurance for a 
    facility undergoing decommissioning should be eliminated or 
    substantially modified.
        Response. Consideration of the potential radiological consequences 
    of hot, high-density packaged fuel in the spent fuel pool is still 
    ongoing. Modifications to this requirement, if made, will be developed 
    at a later time.
        Comment: Section 50.55a. Pertaining to codes and standards 
    requirements, it should be noted that Secs. 50.55a (a), (f), and (g), 
    inservice testing requirements, do not apply to permanently defueled 
    reactors because the plant is not operating and there is no need to 
    apply the regulation.
        Response. No change is necessary because these requirements provide 
    assurance that relevant portions of the facility are maintained 
    functional or operational to adequate standards so they are 
    operationally capable.
        Comment: Section 50.63. The requirements on the loss of all ac 
    power should not apply to decommissioning because the potential for 
    significant radiological consequences is very low (there is a low 
    probability of incident and long recovery time).
        Response. Consideration of the potential radiological consequences 
    of hot, high-density packaged fuel in the spent fuel pool is still 
    ongoing. Modifications to this requirement, if made, will be developed 
    at a later time.
        Comment: Section 50.65. Monitoring maintenance for a permanently 
    shutdown and defueled facility on any of its structures, systems, or 
    components (SSC) to levels required by the current maintenance rule is 
    unnecessary. Permanently shutdown and defueled facilities can no longer 
    experience the levels of mechanical stresses associated with an 
    operating plant. Therefore, the industry interprets the proposed rule 
    to mean that the maintenance program only applies to the safe storage 
    of fuel. The relative risks from a shutdown plant allow requirements in 
    existing technical specifications and other administrative programs to 
    provide adequate assurance for safe fuel storage.
        Response. The maintenance rule, Sec. 50.65, requires that the 
    performance or condition of all structures, systems, and components 
    (SSCs) described in Sec. 50.65(b) be included in the scope of the rule. 
    Under the current rule, licensees are permitted flexibility in the 
    goals that are established and the monitoring that is performed for 
    these SSCs. The NRC agrees that the stresses on most SSCs in an 
    operating plant are greater than those associated with a shutdown and 
    defueled plant. The final rule allows the scope to be limited to those 
    SSCs associated with the storage, control, and maintenance of spent 
    fuel in a safe condition in a manner that provides reasonable assurance 
    that the SSCs are capable of performing their intended function.
        Comment: Section 50.72. The immediate notification requirements for 
    operating nuclear power reactors should not apply to permanently 
    defueled reactors or, if applicable, should be significantly modified. 
    Regarding Sec. 50.72(a)(i), there should be no requirement to use the 
    Emergency Notification System or Emergency Response Data Systems.
        Response. The NRC did not adopt this comment. Notification 
    requirements for events such as abnormal releases and overexposures are 
    examples of required reports that are necessary.
        Comment: Section 50.111. Criminal penalties should not be imposed 
    for decommissioning activities because they are not so important to 
    public health and safety that licensees need be subject to them. 
    Decommissioning activities for reactor licensees should not be treated 
    any differently than for other radioactive material licensees.
        Response. The Commission believes that certain actions are 
    essential in initiating the decommissioning process (e.g., certifying 
    to permanent cessation of operation and permanent removal of fuel from 
    the reactor vessel, and submitting a PSDAR) and should, therefore, be 
    treated as substantive with respect to the criminal penalty provisions 
    of the Atomic Energy Act. Decommissioning actions, when initiated 
    improperly, have a potential for significant consequences regarding 
    health, safety, and the environment. Willful violations of, attempted 
    violations of, or conspiracy to violate, Sec. 50.82 would, therefore, 
    be a matter of significant concern to the NRC. Thus, the NRC is 
    retaining the addition of Sec. 50.82 to the list of regulations to 
    which criminal sanctions apply.
        Comment: Section 140.11. Concerning Price Anderson financial 
    protection, permanently shutdown and defueled facility licensees should 
    be permitted to withdraw from the secondary financial protection layer, 
    and single units should be given a reduction in the primary level of 
    coverage (e.g., $100,000,000).
        Response. Consideration of the potential radiological consequences 
    of hot, high-density packaged fuel in the spent fuel pool is still 
    ongoing. Modifications to this requirement, if made, will be developed 
    at a later time, as will considerations of fuel stored in an ISFSI.
        Issue 10--Termination of License Requirements.
    
    [[Page 39289]]
    
        Most of the commenters in favor of the rule supported the 
    decommissioning requirements for termination of the license in the 
    proposed rule. However, several of these commenters stated that 
    approval of the license termination plan should not require an 
    amendment or opportunity for a hearing. They believe that if the plan 
    is made available for public comment, existing regulations provide 
    ample opportunity for public participation and the AEA does not require 
    a hearing. Another commenter noted that once the spent fuel is off the 
    site, the hazard is reduced so there is no safety, technical, or legal 
    basis for NRC approval of a detailed decommissioning plan or PSDAR. A 
    commenter pointed out that the use of the proposed Sec. 50.59, which 
    includes the four criteria (Sec. 50.59(e)), addresses the unique 
    circumstances associated with the decommissioning activities. If some 
    activities do not satisfy the requirements of Sec. 50.59 and a license 
    amendment is required, interested parties would have an opportunity to 
    request a hearing. The approval of the plan by amendment and the 
    opportunity for a hearing are not for reasons of health and safety; 
    moreover, any interested party could always petition for a hearing 
    under Sec. 2.206. Another commenter made similar comments and went even 
    further in stating that if standards for radioactive release are clear, 
    meeting the objective of terminating the license should be easily 
    demonstrated without the need for approval of a plan or license 
    amendment; and that the plan should be available to the NRC for 
    information only.
        Response. The requirement for submittal of a termination plan is 
    retained in the final rule because the NRC must make decisions, 
    required in the current rule on the decommissioning plan, regarding (1) 
    the licensee's plan for assuring that adequate funds will be available 
    for final site release; (2) radiation release criteria for license 
    termination, and (3) adequacy of the final survey required to verify 
    that these release criteria have been met. A public meeting is 
    considered necessary at the license termination stage to inform the 
    public about the licensee's proposed termination activities and to 
    provide an opportunity for public comment on those proposed activities. 
    The NRC has also made the determination that license termination is an 
    action of sufficient significance as to warrant an opportunity for a 
    public hearing on NRC's decision regarding the licensee's proposed 
    termination activities.
        Specific comments concerning the license termination plan were 
    provided by several commenters.
        Comment a. The timing of the license termination plan is not 
    explicit in the proposed rule, Sec. 50.82(a)(8), and it is not clear 
    whether the rule permits dismantlement activities before submittal or 
    approval of the license termination plan.
        Response. The final rule permits dismantlement activities 90 days 
    after PSDAR submittal unless the NRC interposes an objection. The 
    license termination plan must be submitted within 2 years of the 
    licensee's expected date of license termination (the date specified in 
    the PSDAR or supplement).
        Comment b. The NRC does not explain or support the need for the 
    elements of the plan, discussed in proposed Sec. 50.82(a)(8)(ii) (A)-
    (G). The current rule, under Sec. 50.82(d), simply requires updated, 
    detailed plans before the start of decommissioning.
        Response. The final rule permits major decommissioning activities 
    (dismantlement) to be performed using the Sec. 50.59 process. Because a 
    decommissioning plan is no longer required, the requirements for the 
    license termination plan are less complex than those that are currently 
    required for a decommissioning plan. The license termination plan 
    provides documentation on the remaining activities necessary to 
    terminate the license and includes consideration of remediation aspects 
    that could involve license termination under either unrestricted or 
    restricted release conditions (once the rulemaking on acceptable 
    residual release criteria is final). The site characterization, 
    description of the remaining dismantlement activities and plans for 
    site remediation are necessary for the NRC to be sure that the licensee 
    will have adequate funds to complete decommissioning and that the 
    appropriate actions will be completed by the licensee to ensure that 
    the public health and safety will be protected. The language of 
    Sec. 50.82(8)(a)(ii) (B) and (F) in the proposed rule, now 
    Sec. 50.82(a)(9)(ii) (B) and (F) in the final rule, has been changed to 
    more clearly reflect the intent of these requirements. Thus, element 
    (A) now requires identification of remaining dismantlement activities, 
    and element (F) now requires an updated site-specific estimate of 
    remaining decommissioning costs.
        Comment c. One commenter questioned how multiple sites will be 
    addressed. Another commenter stated that a single license termination 
    plan should be encouraged for multi-reactor sites.
        Response. Reactors at a multi-reactor site are individually 
    licensed and licensing actions are applied to the individual licenses. 
    A licensee would not be prohibited from submitting a single license 
    termination plan for the multi-reactor site, but the NRC would address 
    terminating each license separately.
        Issue 11--License Termination: Additional comments.
        Comment. A commenter stated that the need for a hearing when the 
    licensee submits the license termination plan for approval should be 
    reconsidered. If the licensee meets the requirements of the termination 
    plan and applicable regulations, there would be no issues to 
    adjudicate. Another commenter stated that, concerning the subpart L 
    proceedings, the NRC should issue a clear statement of policy to 
    eliminate the potential for significant litigation. Several commenters 
    stated that if subpart L is to be used for hearings, it appears 
    necessary to change the title of subpart L to include Part 50 
    licensees. Finally, a commenter stated that the applicability of 
    Subpart L hearings should be incorporated into Sec. 2.700 as well as 
    Sec. 2.1201.
        Response. With respect to the termination plan, the Commission 
    recognizes that ongoing rulemaking proceedings may result in 
    establishing criteria for the restricted release of sites. Even if a 
    hearing is not legally mandated at the termination stage as argued by 
    some commenters, the Commission views it as appropriate to use the 
    amendment process for approval of termination plans, including the 
    associated opportunity for a hearing, to allow public participation on 
    the specific actions required for license termination. In particular, 
    the Commission has determined that, if a hearing is requested on the 
    termination plan, the hearing must be completed before release of the 
    site. This action will help ensure meaningful public input on any 
    proposal for restricted release of the site. Given that a lengthy 
    period (up to 60 years) may pass between the PSDAR stage and the 
    termination stage, and given that final release criteria are still 
    being developed that may include restricted release of a site, the 
    Commission views a license amendment process as appropriate, along with 
    the associated opportunity for a hearing, whether or not such hearings 
    are mandated by legislation. Finally, the changes proposed by the 
    commenters concerning the change of title of subpart L to include part 
    50 licensees and the incorporation of
    
    [[Page 39290]]
    
    subpart L applicability into Secs. 2.700 and 2.1201 are unnecessary 
    because the rule already addresses these considerations.
        Comment. Many commenters expressed confusion on when a subpart L or 
    subpart G hearing would be appropriate. One commenter noted that once 
    fuel is out of the reactor vessel and in dry storage, there is no 
    difference between storage on or off site and that reference to the 
    subpart G hearing should be deleted. Another commenter wanted a 
    clarification of what is meant by removing fuel from the site (i.e., 
    under a part 72 license). Another commenter suggested that the wording 
    to Sec. 2.1201(a)(3) be clarified concerning permanent removal of fuel 
    from the site to an authorized facility. One commenter inquired as to 
    whether a license could be terminated if the licensee removed the fuel 
    to an onsite ISFSI.
        Response. The final rule clearly indicates that once the fuel is 
    removed from the licensed part 50 facility the power reactor facility 
    can be treated as a materials facility where a subpart L hearing is 
    appropriate. If fuel remains at the facility, a subpart G hearing is 
    appropriate. If the fuel is in an ISFSI, that part of the affected site 
    is regulated under a part 72 license and would no longer be regulated 
    under the part 50 license. The wording in Sec. 2.1201(a)(3) has been 
    changed to ``removal of fuel from the part 50 facility,'' rather than 
    ``from the site,'' and means either removal offsite to an authorized 
    facility or to an onsite facility (ISFSI) not under the part 50 
    license.
        Comment. Many commenters did not see the need for an environmental 
    review at the license termination stage, and one suggested that it be 
    considered a categorical exclusion. Another commenter stated that if 
    there were to be an environmental review, its scope should be 
    restricted to whether the licensee's controls and methods for 
    mitigation of radiation will meet the standards adopted in Sec. 20.1405 
    of the proposed residual radiation criteria rule.
        Response. At the license termination stage, an environmental 
    assessment or impact statement will be required when the license is 
    amended. Following resolution of another ongoing NRC rulemaking 
    activity that is considering adoption of radiological release criteria, 
    a categorical exclusion may be adopted that would eliminate the 
    requirement for an environmental assessment or impact analysis, except 
    in the case of a restricted release of a site.
        Comment. A few comments addressed proposed changes to Sec. 51.53 
    concerning requirements for environmental impact considerations. One 
    commenter stated that the first sentence of the first paragraph of 
    Sec. 51.53(b) should be deleted to be consistent with the concept that 
    ``a license amendment authorizing decommissioning activities'' is no 
    longer required. Revised wording should begin with ``each applicant for 
    a license amendment approving a license termination plan or 
    decommissioning plan.'' Another commenter stated that Sec. 51.53 should 
    be revised to reflect the fact that the proposed rule, if adopted, 
    would not require an amendment that authorizes the conduct of 
    decommissioning activities, because neither the existing nor the 
    proposed decommissioning process requires a license amendment to 
    approve a decommissioning plan. Therefore the first paragraph of this 
    section should be reworded as ``[E]ach applicant for license 
    termination upon submittal of the license termination plan under 
    Sec. 50.82 of this chapter either for unrestricted use or based on 
    continuing use restrictions applicable to the site, * * * shall submit 
    * * *'' A similar change was stated to be needed in Sec. 51.95 for the 
    same reasons. Finally, a commenter noted that Sec. 51.53(b) as well as 
    Sec. 51.95(b) refer to ``applicants * * * for a utilization facility,'' 
    which does not seem to be an element of the proposed rule and should be 
    deleted; also, Sec. 51.95(b) does not mention approval of a license 
    amendment for license termination or a decommissioning plan, which is 
    an omission and should be consistent with Sec. 51.53(b).
        Response. No change was made to this section because the non-power 
    reactor facilities are still required to submit a decommissioning plan. 
    For non-power reactors, the current rule remains essentially unchanged 
    and requires submittal of a decommissioning plan that is approved 
    through license amendment. The non-power reactor licensee must also 
    submit an appropriate supplemental environmental report and the NRC 
    must do an EA as part of the decommissioning plan approval process.
        Comment. Most of the commenters who were not in favor of the rule 
    supported the license termination phase requirements but believe that 
    these requirements were not timely and should be implemented in some 
    manner at the initiation phase of decommissioning.
        Response. During the initial phase of decommissioning, the 
    requirements in the final rule are designed to provide oversight 
    commensurate with the level of safety concerns experienced in 
    decommissioning, while providing additional opportunity for public 
    comment on the licensee's proposed activities. The final rule 
    requirements are based on NRC's experience with licensees' use of the 
    Sec. 50.59 process during operations and consideration of the types of 
    activities that licensees would undertake during the decommissioning 
    process. Where appropriate, licensing requirements are continued 
    through decommissioning and the NRC is informed of each licensee's 
    planned decommissioning activities. (Additional discussion can be found 
    in the response to Comment 5).
        Issue 12--Regulatory Guides.
        Comment. Several commenters requested regulatory guidance in the 
    form of regulatory guides. These requests pertained to a standard 
    format and content for the PSDAR and license termination plan as well 
    as to transition guidance for licensees who are shut down and choose to 
    adopt the new process. Additional guidance was also requested for a 
    regulatory guide that dealt with the decommissioning process, such as a 
    revision to Regulatory Guide 1.86, ``Termination of Operating Licenses 
    for Nuclear Reactors,'' that would include such topics as the objective 
    and implementation aspects of public meeting and hearings, guidance on 
    issues the NRC would consider in not giving negative consent approval 
    to the PSDAR after the 90-day waiting period, guidance on 
    interpretation and development of technical rule requirements, and 
    guidance, on the particulars of ``grandfathering.'' Additionally, 
    several commenters requested additional financial guidance, through a 
    regulatory guide, on the development and use of the decommissioning 
    trust fund.
        Response. The NRC intends to issue regulatory guidance on the 
    initial phase of decommissioning. Guidance on the standard format and 
    content of the PSDAR will be issued after the final rule is published. 
    Other guidance on the license termination phase is also being 
    developed.
        Issue 13--Elimination of the Possession-only License Amendment 
    (POLA).
        Comment. Generally, commenters in favor of the rule agreed with 
    eliminating the POLA. Objections to POLA elimination from other 
    commenters were that distinct categories between reactor operation and 
    cessation of operation should be maintained and that eliminating the 
    POLA process would eliminate a hearing opportunity prior to reactor 
    decommissioning. Reflecting the views of many commenters against POLA 
    elimination, a State commenter said that by deleting
    
    [[Page 39291]]
    
    the POLA the NRC would eliminate the amendment process that expressly 
    provides for State consultation (Sec. 50.91(b)) and that no subpart G 
    hearing process would occur that would allow for discovery by parties 
    to the proceeding and provide a mechanism for intervention. The State 
    commenter held that the proposed rule delays the need for amendment to 
    the license termination stage when it is too late; it is needed before 
    major decommissioning activities are undertaken. Moreover, at the 
    license termination stage, only a subpart L hearing is proposed (no 
    discovery). Finally, a few commenters asked why non-power reactors, 
    which are less hazardous facilities (smaller and less contaminated), 
    can still request a POLA and still require decommissioning plan 
    approval while power reactors no longer have this option or 
    requirement.
        Response. If fuel is removed from the licensed part 50 facility, 
    the activities undertaken during decommissioning are more like the 
    kinds of activities undertaken at a typical materials facility where 
    the subpart L process applies. The final rule requires that certain 
    procedures be satisfied before a licensee can perform major 
    decommissioning activities. These procedures include requiring a PSDAR 
    submittal, conducting a public meeting, and allowing a specified time 
    period for NRC review of the licensee's intended actions. Other final 
    rule requirements prohibit the licensee from performing any major 
    decommissioning activity that could result in significant environmental 
    impacts not previously reviewed or foreclose the release of the site 
    for unrestricted use. Written notification to the NRC is required for 
    licensee decommissioning activities that are inconsistent with those 
    described in the PSDAR, including significant changes in 
    decommissioning costs. Finally, the final rule extends certain 
    regulatory requirements to decommissioning. Thus, licensee activities 
    that would require approval under a POLA are no longer necessary. The 
    affected State(s) will be notified about the public information meeting 
    as well as consulted on the licensee's planned decommissioning 
    activities by the NRC prior to the public meeting. The final rule 
    requires that a copy of the PSDAR and any written notification of 
    inconsistent PSDAR activities be sent to the affected State(s). In 
    response to the comment concerning why non-power reactors are still 
    given the option of submitting a POLA and still require a 
    decommissioning plan, it is noted that such reactors are required to 
    immediately dismantle, except for extenuating circumstances, and are 
    not permitted a storage period (because there is no significant health, 
    safety or environmental reason for delay--see FGEIS, NUREG 0586).\1\
        Issue 14--``Grandfathering'' Considerations.
        Comment. There were several commenters who were concerned that the 
    proposed rule did not significantly address nor provide necessary 
    guidance for ``grandfathering'' issues. Specific comments in this area 
    were that recognition should be given to those plants whose 
    decommissioning plans have been approved on a case-by-case basis; that 
    if existing facilities are grandfathered from any part of the proposed 
    rule, it should clearly identify this; that the proposed rule does not 
    adequately implement the grandfathering option because the current 
    Sec. 50.82 would disappear from the rule and no explicit provisions 
    would exist to rely on. It is suggested that the NRC keep the old 
    provision as well as an applicable alternative and; that for 
    grandfathering, an implementation provision should be added to the rule 
    in a fashion similar to Sec. 20.1008. Several commenters also noted 
    that guidance needs to be given to those licensees who are in various 
    aspects of decommissioning based on the current rule requirements and 
    wish to switch to the proposed rule requirements.
        Response. The Commission has reconsidered the issue of 
    ``grandfathering'' and modified the language in the final rule to 
    provide more specific guidance for nuclear power reactor licensees 
    whose facilities are currently at certain stages of decommissioning. 
    The Commission has decided to eliminate the provision in the proposed 
    rule that would give those licensees that have an NRC approved 
    decommissioning plan, before the date when a final rule became 
    effective, the option of either complying with the final rule 
    requirements or continuing with the requirements of the currently 
    existing rule. All licensees will be required to comply with the 
    decommissioning procedures specified in the provisions of the final 
    rule, when it becomes effective. The final rule addresses the process 
    for converting from the existing rule requirements to those in the 
    final rule for those nuclear power reactor licensees whose facilities 
    are already at certain stages of decommissioning.
        For power reactor licensees who, before the effective date of this 
    final rule, either submitted a decommissioning plan for approval or 
    possess an approved plan, the plan will be considered as the PSDAR 
    submittal and the licensee will be required to perform decommissioning 
    in conformance with these final rule requirements. However, for power 
    reactor licensees who are involved in subpart G hearings of 10 CFR part 
    2, conversion to the new rule will not be permitted until the hearing 
    process is completed. The public meeting and 90-day hold on 
    decommissioning activities required in Sec. 50.82(a) (4)(ii) and (5) 
    will not apply. Those licensees will be subject to any orders arising 
    from these subpart G hearings, absent any orders from the Commission.
        For nuclear power reactor facility licensees whose licenses have 
    been modified, before the effective date of this rule, to allow 
    possession but not operation of the facility, the certifications 
    required in Sec. 50.82(a)(1) will be considered to have been submitted.
        With regard to extending current rule requirements for 
    ``grandfathering'' considerations, no current rule requirements need be 
    retained because the ``grandfathering'' provision in the proposed rule 
    has been eliminated in the final rule. The final rule covers conversion 
    from the existing requirements for approval of a submitted or approved 
    decommissioning plan, as described above, and is specific to existing 
    licensee decommissioning plan situations.
        Issue 15--Miscellaneous Comments.
        Comment. Several commenters stated that the backfit rule, 
    Sec. 50.109, should apply to decommissioning because a proper reading 
    of the intent of that rule should cover rulemaking dealing with 
    decommissioning. Otherwise, additional requirements could be imposed 
    without a benefit cost analysis.
        Response. The Commission has concluded that the provisions 
    addressed in this rulemaking do not involve a backfit because they 
    address only reactors that have permanently ceased operations and 
    Sec. 50.109 only applies to design, construction and operation of a 
    facility. These regulations are primarily procedural in nature and, to 
    the extent they address nonprocedural matters, they are a codification 
    of existing process.
        Comment. A few commenters noted that the regulatory analysis for 
    the proposed rule did not evaluate the alternatives to the proposed new 
    regulatory requirements and existing requirements do not require a 
    license termination plan or a license amendment to approve a license 
    termination plan. The regulatory
    
    [[Page 39292]]
    
    analysis does not accomplish the objective of ensuring that all 
    regulatory burdens are needed, justified, and minimal.
        Response. The regulatory analysis did evaluate the alternatives to 
    the proposed new regulatory requirements. The license termination plan 
    is not a new requirement because, under the existing rule, licensees 
    are required to submit a proposed decommissioning plan for approval 
    within 2 years of permanent shutdown. Currently, licensees who plan to 
    delay decommissioning by including a period of storage must submit a 
    final decommissioning plan for approval before starting 
    decommissioning. Current NRC policy is to approve the decommissioning 
    plan by license amendment. Because the proposed rule would permit the 
    licensee use of the Sec. 50.59 process to perform major dismantlement 
    activities, the license termination plan is less complex than a 
    decommissioning plan and covers the remainder of activities requiring 
    completion to terminate the license, other than dismantlement 
    activities. The changes adopted in the rulemaking primarily provide 
    additional flexibility to licensees that reduces burden without 
    reducing safety by allowing licensees to undertake the majority of 
    decommissioning activities without first obtaining NRC approval.
        Comment. Several commenters wanted the option of entombment to be 
    allowed because restricted release will be allowed when the residual 
    radiation criteria rule is final. Aside from the difficulty of 
    disposal, the money not spent on LLW burial is substantial. The 
    interest on this money would be more than adequate to provide for the 
    maintenance and surveillance required for the entombment option. The 
    public, including local communities, may be interested in not 
    transporting waste across state boundaries and in keeping funds that 
    would otherwise be spent on disposal within the community.
        Response. The issue of entombment was not addressed in this rule. 
    The NRC position on entombment is the same as in the current rule. 
    Entombment would only be permitted for very special circumstances but 
    would involve a continued license on a case-by-case basis. The concept 
    of restricted release included in the proposed rule on residual 
    radiation criteria would involve termination of the license with 
    restrictions in place to limit the use of the facility by the public, 
    but certain radiological criteria for restricted release would have to 
    be met.
        Comment. Several individual commenters wanted to know whether NRC 
    rules allow the optional period of storage of the reactor facility to 
    be longer than 60 years and does the 60-year completion date for 
    decommissioning specified in the current rule consider storage of fuel 
    in an ISFSI. One commenter stressed that spent fuel should not be 
    separated from any of the phases of decommissioning because this is a 
    piecemeal approach and inappropriate. Another commenter stated that the 
    licensee should be required to maintain capability to handle the fuel 
    for dry cask storage.
        Response. The primary considerations of the proposed rule were 
    procedural, with emphasis on the issue of premature closure. Other 
    aspects of the existing rule were unchanged. A 60-year period for 
    completion of decommissioning is still imposed, subject to other 
    considerations delineated in the current rule requirements. The 
    existing rule, as well as the proposed rule, consider the storage and 
    maintenance of spent fuel as an operational consideration and provide 
    separate part 50 requirements for this purpose. Regarding maintaining 
    the capability to handle the fuel for dry cask storage, these 
    requirements are maintained in 10 CFR part 72.
        Comment. Several commenters noted that the requirements of this 
    proposed rule and the proposed residual radiological criteria rule 
    should be coordinated to avoid redundancy.
        Response. The two rules will be coordinated.
        Comment. A few commenters noted that a complete site 
    characterization should be included at the initiation of 
    decommissioning activities and that mandatory site radiological surveys 
    should be required before issuing a new license to establish background 
    conditions.
        Response. These considerations are being addressed during 
    finalization of the residual radiological criteria rule.
        Comment. Finally, several commenters requested that the NRC 
    consider the impacts of the proposed ``safeguards for nuclear fuel or 
    high level radioactive waste'' rule (60 FR 42079; August 15, 1995) 
    (which affects parts 60, 72, 73, and 75) on this rule when that 
    proposed rule is issued in final form.
        Response. This rule is primarily directed toward the procedural 
    requirements necessary for power reactor decommissionings. Therefore, 
    the requirements imposed by this rule can be treated independently from 
    the other ``safeguards'' rule under development. That rule, when final, 
    may modify some of the technical requirements imposed by this final 
    rule.
    
    Resolution of Comments on the Draft Policy Statement
    
        On February 3, 1994 (59 FR 5216), the NRC published in the Federal 
    Register a draft policy statement and accompanying criteria relating to 
    power reactor licensee use of decommissioning trust funds before NRC 
    approval of licensees' decommissioning plans. The proposed rulemaking 
    to amend the procedural aspects of decommissioning (60 FR 2210; July 
    20, 1995) codified the position embodied in the draft policy statement. 
    Based on the NRC's resolution of comments on the proposed rule and 
    incorporated into this final rule, the criteria in the draft policy 
    statement have been modified. No final policy statement will be issued. 
    Other changes in the final rule pertaining to licensee use of 
    decommissioning trust funds were discussed earlier in the section on 
    Response to Comments.
        The NRC received comments on the draft policy statement from the 
    following individuals or organizations:
        1. Michigan Department of Commerce
        2. Citizens Awareness Network
        3. Mary P. Sinclair
        4. Detroit Edison Company
        5. Committee for a Safe Energy Future
        6. Jon Block
        7. Nuclear Energy Institute
        8. Yankee Atomic Electric Company
        9. Virginia Power Company
        10. New England Coalition on Nuclear Pollution
        11. Winston & Strawn
        12. Consolidated Edison Company
        13. Maryland Department of the Environment
        14. TU Electric Company
        The public interest group, individual commenters, and one State 
    oppose allowing any withdrawals from decommissioning trust funds before 
    the NRC approves a licensee's decommissioning plan, a procedure that 
    this final rule has discontinued. The other commenters generally 
    supported the draft policy statement, although they disagreed with 
    certain provisions or took issue with the need for it. Specific 
    comments and observations, and the NRC analysis of and response to 
    them, are discussed below.
    
    Specific Comments
    
        Comment 1. The trust agreements may need to be modified to include 
    low-level radioactive waste storage and disposal (LLW) and interim 
    spent fuel storage as allowable decommissioning costs when these costs 
    are incurred as part of additional, temporary facilities at particular 
    sites. LLW disposal costs, in particular, should be able to be paid 
    from the decommissioning waste fund
    
    [[Page 39293]]
    
    without waiting 60 days for NRC approval. Provisions should be included 
    for decommissioning nonradioactive structures associated with the 
    reactor (Commenters 1 and 4).
        Response. The policy statement and this rule were not intended to 
    address this issue. This issue is being addressed separately (see SECY 
    95-223; September 1, 1995). As provided in 10 CFR 50.75, financial 
    assurance for decommissioning includes the cost of disposal of LLW 
    associated with reactor decommissioning. If a temporary facility is 
    built to store LLW under the Part 50 reactor license, the trust 
    agreement should have been structured to include these costs. Although 
    the NRC definition of decommissioning excludes interim storage of spent 
    reactor fuel, a licensee is required to provide for the cost of interim 
    spent fuel storage under 10 CFR 50.54(bb).
        With respect to the issue of waiving the 60-day NRC approval period 
    for withdrawals to pay for LLW shipments, this final rule eliminates 
    the procedure to which this comment referred.
        Comment 2. The NRC should not allow decommissioning trust fund 
    withdrawals before an environmental assessment is performed while the 
    reactor licensee has a possession-only license because: (1) It will 
    allow large-scale decommissioning activities without a resident NRC 
    inspector on-site during the removal of irradiated components; (2) it 
    is inconsistent with the mandate of the NRC, which is to implement a 
    submitted, reviewed, publicly evaluated, and approved decommissioning 
    plan before large-scale decommissioning activities begin; (3) health 
    and safety of the workers and the public can not be adequately served 
    by the experimental process of the component removal process, and (4) 
    existing NRC regulations state that a licensee may only conduct limited 
    activities prior to approval of the decommissioning plan (e.g., 
    decontamination, minor component disassembly, shipment and storage of 
    spent fuel). Reasonable interpretation of the rules does not require 
    expansion of 10 CFR 50.59 and/or activities permitted under a license 
    (Commenters 2, 3, 5, 6, and 10).
    
        There could be insufficient financial resources remaining to 
    decommission Nuclear Power Plants thus, creating a potential burden 
    on the State and, serious impairment of radioactive material 
    licensee's ability to complete decommissioning. Most existing 
    decommissioning `certifications and funding plans' are generally 
    acknowledged by the NRC to already be severely UNDERFUNDED. This 
    rule would exacerbate that situation (Commenter 13).
    
        Response. This final rule addresses the process that licensees are 
    to use for post-shutdown decommissioning activities, as well as the 
    limits on the amounts to be withdrawn from decommissioning trust funds.
        By permitting a licensee to perform certain decommissioning 
    activities and to withdraw funds for those activities through use of 
    the PSDAR submittal process required in the final rule will allow the 
    licensee to reduce its overall decommissioning costs by taking 
    advantage of lower low-level radioactive waste disposal costs. This 
    will benefit the licensee and its ratepayers without adversely 
    affecting public health and safety.
        Comment 3. The NRC should develop a similar policy for operating 
    plants and should allow licensees to withdraw decommissioning trust 
    funds to dispose of structures and equipment no longer being used for 
    operating plants (Commenters 7, 8 (by reference), and 14).
        Footnote 2 of the policy statement should be revised to clarify 
    that the policy statement does not apply ``to licensee withdrawals from 
    decommissioning funds for operating plants'' rather than stating that 
    the policy statement does not apply ``to licensees with operating 
    nuclear reactors'' (Commenter 11).
        Response. The NRC has concluded that allowing decommissioning trust 
    fund withdrawals for disposals by nuclear power plants that continue to 
    operate is not warranted. These activities are more appropriately 
    considered operating activities and should be financed in that way.
        Footnote 2 is not included in this final rule.
        Comment 4. The policy statement may become obsolete if the NRC 
    adopts a new definition of decommissioning as proposed on February 2, 
    1994 (59 FR 4868). This definition states, ``Decommissioning means to 
    remove a facility or site safely from service and reduce residual 
    radioactivity to a level that permits use of the property for 
    unrestricted use and termination of the license, or (2) release of the 
    property under restricted conditions and termination of the license.'' 
    To avoid obsolescence of the policy statement as a result of changes in 
    the definition of decommissioning, the commenters recommend replacing 
    all references to release of the site for unrestricted use with 
    ``decommissioning of the site consistent with the definition in 
    Sec. 50.2'' (Commenters 7, 8 (by reference), and 11).
        Response. The NRC agrees with this recommendation and has changed 
    this final rule accordingly.
        Comment 5. Two commenters disagree with a statement in the draft 
    policy statement, ``If a licensee of a permanently shut down facility 
    spends decommissioning trust funds on legitimate decommissioning 
    activities, the timing of these expenditures, either before or after 
    NRC approves a licensee's decommissioning plan, should not adversely 
    affect public health and safety, provided adequate funds are maintained 
    to restore the facility to a safe storage configuration in case 
    decommissioning activities are interrupted unexpectedly'' (Commenter 
    7's emphasis). The commenters state that maintaining a viable SAFSTOR 
    option beyond plan approval should not be required for cases where 
    another option has been approved by NRC (Commenters 7 and 8).
        The draft policy statement misuses the term ``SAFSTOR'' to mean 
    maintenance of a site in a safe storage condition prior to receipt of 
    Decommissioning Plan approval and commencement of decommissioning 
    rather than a specific decommissioning alternative defined in NRC 
    regulations (Commenters 11 and 14).
        Response. Commenter 7 has misinterpreted the intent of this 
    statement. First, this part of the policy statement was drafted to make 
    the point that any expenditures for decommissioning activities normally 
    viewed as necessary would not be detrimental to public health and 
    safety, notwithstanding the timing of these expenditures, unless they 
    were large enough to prevent the licensee from returning its facility 
    to a safe storage configuration if the decommissioning process were to 
    go awry. This is not the same as requiring a licensee to switch from 
    DECON (immediate dismantlement) to SAFSTOR after the NRC has approved 
    the licensee's decommissioning plan.
        This final rule modifies use of the above-referenced criterion for 
    decommissioning trust fund withdrawals. However, the rule corrects any 
    references to SAFSTOR when it means to address the general ability of a 
    licensee to return its reactor to safe storage while awaiting further 
    decommissioning.
        Comment 6. Criterion 4 is redundant of the other criteria 
    (Commenters 7 and 8). At a minimum, the statement should indicate that 
    items (c) and (d) of criterion 4 do not require NRC approval before a 
    licensee undertakes the proposed activities (Commenter 8). Redundancies 
    can be eliminated by
    
    [[Page 39294]]
    
    factoring the first three criteria into criterion 4. However, issuance 
    of the policy statement based on criterion 4 (or the other criteria) is 
    premature in that the NRC is currently considering more definitive 
    guidance on acceptable pre-plan-approval decommissioning activities 
    (Commenter 11).
        Response. The NRC agrees that some confusion may have arisen by 
    including criterion 4 in the policy statement. The NRC included this 
    criterion to provide guidance on the allowed decommissioning activities 
    as opposed to the use of decommissioning trust funds for those 
    activities. Criterion 4 is a quote from Commission guidance in the SRM 
    of January 14, 1993, and, to some degree, overlaps the other criteria 
    of the policy statement. The NRC has removed criterion 4 as a separate 
    criterion in this final rule.
        Comment 7. The ``ancillary issue'' in the draft policy statement 
    should be expanded to include a number of expenses that are paid out of 
    decommissioning trusts by operating plants well in advance of licensee 
    preparation and submission of the decommissioning plan. These expenses 
    include, but are not limited to, trust fees, investment manager fees, 
    income taxes, and periodic site-specific studies (Commenters 7, 8 (by 
    reference), 11, and 14).
        The policy statement should be revised to state specifically that 
    if a licensee determines that it meets the criteria for de minimis 
    withdrawals, it need not request permission from the NRC to use these 
    funds (Commenter 8).
    
        * * * The section dealing with `de minimis' withdrawals for 
    developing the decommissioning plan also seems to be outside the 
    original intent for use of these funds. These withdrawals may seem 
    to be a minor portion of funds allocated for decommissioning, but it 
    starts a process that would allow utilities to tap these funds, if 
    they can fit activities into the definition of decommissioning or 
    simply request to use these funds for other purposes * * * Other 
    uses are unacceptable, even if they are subject to prior regulator 
    approval (Commenter 13).
    
        Response. The intent of the ancillary issue was to allow de minimis 
    withdrawals from decommissioning trust funds of up to $5 million for 
    decommissioning-related administrative and other expenses without prior 
    NRC consent notwithstanding the operating status of the plant. The 
    final rule has changed this withdrawal amount to up to 3 percent of the 
    generic amount specified in Sec. 50.75(c). This withdrawal amount is 
    for purposes of planning for decommissioning (paper studies) and 
    pertains to licensees of operating as well as permanently shut down 
    plants. Permission from the NRC to use these funds in de minimis 
    amounts is unnecessary as long as the amount and purpose of the 
    withdrawal is documented.
        With respect to Commenter 13's concerns, the NRC has specified a 
    maximum limit for de minimis withdrawals. If a licensee were to exceed 
    this limit or use funds for non-decommissioning purposes, it would be 
    subject to NRC enforcement action.
        Comment 8. ``* * * The NRC has neither articulated the reasons why 
    this detailed level of oversight (discussed in the policy statement) is 
    needed, nor has the NRC provided specific examples of potential waste 
    and misuse of funds that would warrant their proposed oversight * * * 
    Absent an appropriate justification for the implementation of this 
    policy statement, * * * this policy statement represents regulation 
    without benefit (and that NRC concerns expressed in the policy 
    statement) are not tangible for decommissioning.'' Thus, the policy 
    statement should not be issued (Commenter 9).
        Also, ``the draft policy statement provides no basis for the NRC's 
    conclusion that prior NRC review of pre-plan-approval decommissioning 
    fund expenditures should be required.'' The draft policy statement may 
    satisfy the Commission's directive to the NRC staff to develop a policy 
    without including an approval mechanism (Commenter 11).
        The draft policy statement is not clear as to the purpose of the 
    NRC review of decommissioning expenditures before decommissioning plan 
    approval. The only reason for the review, given in the statement of 
    policy, is to ensure the health and safety of the general public. There 
    are other regulatory mechanisms for evaluating the activity for which 
    the funds are withdrawn without reviewing the actual withdrawal from 
    the fund. The expenditure of decommissioning trust funds for legitimate 
    decommissioning activities is an economic and not a safety concern 
    (Commenter 14).
        Response. Although the NRC did not include specific examples of 
    waste and misuse of funds in the policy statement, as with any 
    industrial process, costly mistakes can conceivably occur in 
    decommissioning. The NRC also disagrees that codifying decommissioning 
    trust fund withdrawals represents regulation without benefit. The NRC 
    has specifically promulgated decommissioning requirements in 10 CFR 
    50.82 that include licensee PSDAR submittal process that is intended 
    for keeping the NRC and public informed of the licensee's planned 
    decommissioning activities. The intent of the regulations is to require 
    licensees to maintain the entire amount of funds needed for 
    decommissioning in a specified assurance mechanism until the funds are 
    used for their intended decommissioning activities.
        The PSDAR is closely tied to a licensee's provision of assurance to 
    fund the decommissioning activities adequately. Without any NRC 
    criteria for expenditures before the PSDAR submittal process is 
    completed, the decommissioning trust fund could become a shell and thus 
    defeat the purpose of NRC decommissioning funding assurance 
    regulations. Because of the safety implications of inadequate 
    decommissioning funds, the NRC believes it has responsibility for 
    specifying withdrawal rates, notwithstanding the reviews that rate 
    regulators may perform.
        Comment 9. Trust fund withdrawals should also be permitted for 
    early decommissioning-related activities that, although not themselves 
    directly reducing radioactivity at the site, will significantly 
    facilitate such activities when they subsequently occur (Commenters 11 
    and 12).
        Response. In this final rule, withdrawals for planning activities 
    are allowed before completion of the PSDAR process.
        Comment 10. The NRC should clarify footnote 2 to indicate that it 
    applies to licensees of multi-unit sites. ``So long as usage of trust 
    withdrawals is identifiable with the shut down reactor and does not 
    diminish decontamination funding subsequently available for reactors 
    which are continuing to operate, there is no reason why multi-reactor 
    licensees should be treated differently than single-reactor licensees 
    for purposes of this policy statement'' (Commenter 12).
        Response. The NRC agrees with this statement. However, footnote 2 
    is not included in this final rule.
        Comment 11. ``If the NRC believes that NRC review and approval of 
    pre-plan-approval decommissioning expenditures is necessary, it should 
    act through rulemaking rather than policy * * * Since prior NRC review 
    of decommissioning fund withdrawals is not currently required, if the 
    NRC wishes to impose such a requirement, it should initiate rulemaking 
    to revise its decommissioning regulations accordingly'' (Commenter 11).
        Response. This final rule codifies criteria for decommissioning 
    trust fund withdrawals. Thus, this commenter's concerns have been 
    addressed.
    
    [[Page 39295]]
    
        Comment 12. ``The `tacit consent' approach for reviewing licensee 
    expenditure plans is inappropriate'' and unsupported by the reasons the 
    NRC stated for its policy. By expressly preserving the possibility that 
    it would take action to prevent a fund withdrawal, the NRC blurs its 
    asserted distinction between review and approval. Also, it is not clear 
    that ``tacit consent'' and ``approval'' are legally distinguishable for 
    purposes of determining whether the NRC is engaged in a ``licensing 
    action'' that could involve public participation and environmental 
    review (Commenter 11).
        Response. The NRC does not use ``tacit consent'' in this final 
    rule. Thus, the concerns expressed in this comment should be assuaged.
        Comment 13. ``Criterion 1 * * * should be revised to eliminate the 
    provision that withdrawals must be for activities `that would 
    necessarily occur under most reasonable decommissioning scenarios.''' 
    This phrase adds nothing to the preceding provision that the withdrawal 
    must be for ``legitimate decommissioning activities.'' Because 
    licensees may face decommissioning expenditures for activities that are 
    within the NRC's definition of decommissioning but nonetheless unique 
    to their plant(s), the proposed provision is inappropriately 
    restrictive (Commenter 11).
    
        Criterion 1 is overly restrictive and burdensome * * * If the 
    NRC wants to prevent activities that preclude release of the site 
    for (un)restricted use or are not in support of decommissioning 
    efforts it should require review of the activity itself through any 
    of the other available mechanisms such as 10 CFR 50.59 or special 
    rulemaking * * * The basic premise is that in the event that there 
    are circumstances or conditions which delay or preclude proceeding 
    with the decommissioning effort there will be funds available to 
    place the plant in a storage condition until the event or 
    circumstance is resolved. Thus, as long as the value of the fund 
    does not fall below the regulatory required amount in effect at the 
    time of the request the withdrawal should be allowed. Thus, the only 
    requirement should be that the utility document that [the] activity 
    was a legitimate decommissioning activity and the expenditure was 
    reasonable (Commenter 14).
    
        Response. The NRC did not mean to imply that decommissioning 
    activities unique to one site would not be eligible for early trust 
    fund withdrawals. However, because we agree that the phrase, 
    ``legitimate decommissioning activities,'' is sufficient, the NRC has 
    eliminated the phrase from this final rule.
        Comment 14. ``* * * The explicit characterization as a 
    decommissioning `contingency' of the funding `necessary to maintain the 
    status quo' could be construed inappropriately to require that 
    licensees include funding for that purpose in their decommissioning 
    funds * * * If this criterion is retained, the language regarding 
    provisions for this contingency should be deleted from the policy 
    statement'' (Commenter 11).
        Response. This terminology has been eliminated in this final rule.
        Comment 15. ``It does not seem necessary that NRC approve requests 
    for the `withdrawal of decommissioning funds for early equipment 
    removal, prior to approval of the utilities['] decommissioning plans. 
    This does not seem in concert with the intent of the sample statement 
    under Background `* * * the fund trustee should only release funds upon 
    certification that decommissioning is proceeding pursuant to an NRC-
    approved plan' '' (Commenter 13).
        Response. This final rule does not continue the language in 
    question.
        Comment 16. ``* * * This ruling may be judged as an item of 
    Compatibility (for Agreement States). Because Maryland regulations, 
    policies, etc., are expected to closely follow Federal rules and 
    procedures, we would be forced to adopt and allow our licensees to use 
    the same principle'' (Commenter 13).
        Response. The NRC does not believe that this is an issue of State 
    compatibility because this final rule only applies to power reactor 
    licensees, which are exclusively NRC licensees.
    
    Summary of Changes in the Final Rule
    
        Based on the response to comments, a few changes were made in the 
    final rule. Otherwise, the final rule provisions are the same as those 
    presented in the ``background'' section under the section titled 
    proposed amendments. Specific changes made to the proposed rule in the 
    final rule are summarized as follows:
        (1) Section 50.2. The definition of ``major radioactive 
    components'' has been clarified.
        (2) Section 50.36a(a)(1). The amendment has been changed to exclude 
    systems that are no longer necessary for compliance.
        (3) Section 50.59. Proposed Sec. 50.59(e) was eliminated. However, 
    three of the proposed rule requirements contained in Sec. 50.59(e) were 
    moved to Sec. 50.82(a) (6) and (7). Placing these requirements in 
    Sec. 50.82 as overall constraints, rather than specific requirements 
    for each Sec. 50.59 activity, required modification of the constraint 
    that the decommissioning activities not result in significantly 
    increasing decommissioning costs. Thus, the final rule 
    (Sec. 50.82(a)(6)(iii)) prohibits decommissioning activities that would 
    result in there no longer being reasonable assurance that adequate 
    funds will be available to complete decommissioning. In addition, the 
    final rule requires in Sec. 50.82(a)(7) that changes from those 
    specified in the PSDAR that would result in significantly increasing 
    decommissioning costs require written notification to the NRC. The 
    fourth requirement that the terms of the existing license not be 
    violated was eliminated. The requirement to consider environmental 
    impact in the PSDAR, Sec. 50.82(a)(4) was modified to explicitly 
    require the reasons for concluding that any environmental impacts will 
    be bounded by existing analysis.
        (4) Section 50.71. Section 50.71(e)(4) was revised to permit 
    nuclear power reactor licensees that have submitted the certifications 
    required under Sec. 50.82(a)(1) to update the FSAR every 24-months.
        (5) Sections 50.82(a)(4)(i) and (6). The licensee is required to 
    send a copy of the PSDAR and written notification of departure from the 
    PSDAR to the NRC and affected State(s).
        (6) Section 50.82(a)(8)(ii). The phrase ``being permitted to use'' 
    was removed from this section to avoid any incorrect interpretation 
    that the NRC must explicitly approve decommissioning funding 
    expenditures.
        (7) Section 50.82. Specifies that once the rule is effective, all 
    power reactor licensees must comply with it. Power reactor licensees 
    that possess an approved plan as well as licensees that applied for 
    plan approval before the rule took effect would have the plan 
    considered a PSDAR submittal, and licensees would be permitted to 
    perform decommissioning activities in accordance with Sec. 50.82. 
    However, for power reactor licensees who are involved in subpart G 
    hearings of 10 CFR part 2, conversion to the new rule will not be 
    permitted until the hearing process is completed and those licensees 
    will be subject to any orders arising from these hearings absent any 
    orders from the Commission.
        (8) Section 50.82(a)(1)(iii). Specifies that once the rule is 
    effective, power reactor licensees whose licenses have been modified, 
    before the effective date of this rule, to possess but not operate the 
    facility, will be considered to have submitted the certifications 
    required in Sec. 50.82(a)(1).
        (9) To improve clarity, the first sentence in Sec. 2.1205(d)(1) has 
    been rewritten from that proposed to that found in the existing 
    regulation.
        (10) To improve clarity and maintain parallelism of requirements, 
    the last
    
    [[Page 39296]]
    
    sentence of Sec. 51.53(b) has been rewritten from that found in the 
    proposed rule to correspond with the language found in Sec. 51.95(b) of 
    the proposed (and existing) rule.
        (11) To improve clarity, Sec. 50.82(a)(9)(ii) (B) and (F) have been 
    rewritten.
    
    Finding of No Significant Environmental Impact: Availability
    
        The Commission has determined under the National Environmental 
    Policy Act of 1969, as amended, and the Commission's regulations in 
    subpart A of 10 CFR Part 51, that this rule, if adopted, would not be a 
    major Federal action significantly affecting the quality of the human 
    environment and therefore, an environmental impact statement is not 
    required. The final rule clarifies current decommissioning requirements 
    for nuclear power reactors in 10 CFR Part 50 and presents a more 
    efficient, uniform, and understandable process. The Commission has 
    analyzed the major environmental impacts associated with 
    decommissioning in the Generic Environmental Impact Statement (GEIS), 
    NUREG-0586, August 1988,\1\ published in conjunction with the 
    Commission's final decommissioning rule (53 FR 24018; June 27, 1988).
        Insofar as this rule would allow major decommissioning 
    (dismantlement) to proceed without an environmental assessment, the 
    environmental impacts of this rule are within the scope of the prior 
    GEIS. The environmental assessment for the final rule and finding of no 
    significant impact on which this determination is based are available 
    for inspection and photocopying for a fee at the NRC Public Document 
    Room, 2120 L Street NW. (Lower Level), Washington, DC. Single copies of 
    the environmental assessment and the finding of no significant impact 
    are available from Carl Feldman, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555-0001, (301) 415-6194.
    
    Paperwork Reduction Act Statement
    
        This final rule amends information collection requirements that are 
    subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et 
    seq.). These requirements were approved by the Office of Management and 
    Budget, approval number 3150-0011.
        Because the rule will relax existing information collection 
    requirements, the public burden for this collection of information is 
    expected to be decreased by 12,202 hours per licensee. This reduction 
    includes the time required for reviewing instructions, searching 
    existing data sources, gathering and maintaining the data needed and 
    completing and reviewing the collection of information. Send comments 
    on any aspect of this collection of information, including suggestions 
    for further reducing this burden, to the Information and Records 
    Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, 
    Washington, DC, 20555-0001, or by Internet electronic mail to 
    [email protected]; and to the Desk Officer, Office of Information and 
    Regulatory Affairs, NEOB-10202, (3150-0011), Office of Management and 
    Budget, Washington, DC 20503.
    
    Public Protection Notification
    
        The NRC may not conduct or sponsor, and a person is not required to 
    respond to, a collection of information unless it displays a currently 
    valid OMB control number.
    
    Regulatory Analysis
    
        The NRC has prepared a regulatory analysis for this final rule. The 
    analysis qualitatively examines the costs and benefits of the 
    alternatives considered by the NRC. In the response to comments, the 
    NRC concluded that only some minor changes to the draft regulatory 
    analysis were necessary, corresponding to some minor procedural changes 
    in the final rule. The regulatory analysis is available for inspection 
    in the NRC Public Document Room, 2120 L Street NW. (Lower Level), 
    Washington, DC 20555-0001. Single copies of the analysis may be 
    obtained from Dr. Carl Feldman, Office of Nuclear Regulatory Research, 
    U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, 
    telephone (301) 415-6194.
    
    Regulatory Flexibility Certification
    
        In accordance with the Regulatory Flexibility Act of 1980 (5 U.S.C. 
    605(b)), the Commission certifies that this rule will not have a 
    significant economic impact on a substantial number of small entities. 
    The final rule modifies requirements for timely decommissioning of 
    nuclear power plants. The companies that own these plants do not fall 
    within the scope of the definition of small entities as given in the 
    Regulatory Flexibility Act or the Small Business Size Standards 
    promulgated in regulations issued by the Small Business Administration 
    (13 CFR Part 121). This discussion constitutes the analysis for the 
    regulatory flexibility certification requirement.
    
    Small Business Regulatory Enforcement Fairness Act
    
        In accordance with the Small Business Regulatory Enforcement 
    Fairness Act of 1996, the NRC has determined that this action is not a 
    major rule and has verified this determination with the Office of 
    Information and Regulatory Affairs, OMB
    
    Backfit Analysis
    
        The Commission has determined that the backfit rule, 10 CFR 50.109, 
    does not apply to these final amendments, and therefore, a backfit 
    analysis has not been prepared for this rule. The scope of the backfit 
    provision in 10 CFR 50.109 is limited to construction and operation of 
    reactors. These final amendments would only apply to reactors that have 
    permanently ceased operations and, as such, would not constitute 
    backfits under 10 CFR 50.109.
    
    List of Subjects
    
    10 CFR Part 2
    
        Administrative practice and procedure, Antitrust, Byproduct 
    material, Classified information, Environmental protection, Nuclear 
    materials, Nuclear power plants and reactors, Penalties, Sex 
    discrimination, Source material, Special nuclear material, Waste 
    treatment and disposal.
    
    10 CFR Part 50
    
        Antitrust, Classified information, Criminal penalties, Fire 
    protection, Intergovernmental relations, Nuclear power plants and 
    reactors, Radiation protection, Reactor siting criteria, Reporting and 
    recordkeeping requirements.
    
    10 CFR Part 51
    
        Administrative practice and procedure, Environmental impact 
    statement, Nuclear materials, Nuclear power plants and reactors, 
    Reporting and recordkeeping requirements.
        For reasons set out in the preamble and under the authority of the 
    Atomic Energy Act of 1954, as amended, the Energy Reorganization Act of 
    1974, as amended, and 5 U.S.C. 552 and 553, the NRC is adopting the 
    following amendments to 10 CFR parts 2, 50, and 51.
    
    PART 2-- RULES OF PRACTICE FOR DOMESTIC LICENSING PROCEEDINGS AND 
    ISSUANCE OF ORDERS
    
        1. The authority citation for part 2 continues to read as follows:
    
        Authority: Secs. 161, 181, 68 Stat. 948, 953, as amended (42 
    U.S.C. 2201, 2231); sec. 191, as amended, Pub. L. 87-615, 76 Stat. 
    409
    
    [[Page 39297]]
    
    (42 U.S.C. 2241); sec. 201, 88 Stat. 1242, as amended (42 U.S.C. 
    5841); 5 U.S.C. 552.
        Section 2.101 also issued under secs. 53, 62, 63, 81, 103, 104, 
    105, 68 Stat. 930, 932, 933, 935, 936, 937, 938, as amended (42 
    U.S.C. 2073, 2092, 2093, 2111, 2133, 2134, 2135); sec. 114(f), Pub. 
    L. 97-425 96 Stat. 2213, as amended (42 U.S.C. 10134(f)); sec. 102, 
    Pub. L. 91-190, 83 Stat 853, as amended (42 U.S.C. 4332); sec. 301, 
    88 Stat. 1248 (42 U.S.C. 5871). Sections 2.102, 2.103, 2.104, 2.105, 
    2.721 also issued under secs. 102, 103, 104, 105, 183, 189, 68 Stat. 
    936, 937, 938, 954, 955, as amended (42 U.S.C. 2132, 2133, 2134, 
    2135, 2233, 2239). Section 2.105 also issued under Pub. L. 97-415, 
    96 Stat. 2073 (42 U.S.C. 2239). Sections 2.200-2.206 also issued 
    under secs. 161b, i, o, 182, 186, 234, 68 Stat. 948-951, 955, 83 
    Stat. 444, as amended (42 U.S.C. 2201(b), (i), (o), 2236, 2282); 
    sec. 206, 88 Stat. 1246 (42 U.S.C. 5846). Sections 2.600-2.606 also 
    issued under sec. 102, Pub. L. 91-190, 83 Stat. 853, as amended (42 
    U.S.C. 4332). Sections 2.700a, 2.719 also issued under 5 U.S.C. 554. 
    Sections 2.754, 2.760, 2.770, 2.780, also issued under 5 U.S.C. 557. 
    Section 2.764 and Table 1A of Appendix C also issued under secs. 
    135, 141, Pub. L. 97-425, 96 Stat. 2232, 2241 (42 U.S.C. 10155, 
    10161). Section 2.790 also issued under sec. 103, 68 Stat. 936, as 
    amended (42 U.S.C. 2133) and 5 U.S.C. 552. Sections 2.800 and 2.808 
    also issued under 5 U.S.C. 553. Section 2.809 also issued under 5 
    U.S.C. 553 and sec. 29, Pub. L. 85 256, 71 Stat. 579, as amended (42 
    U.S.C. 2039). Subpart K also issued under sec. 189, 68 Stat. 955 (42 
    U.S.C. 2239); sec. 134, Pub. L. 97-425, 96 Stat. 2230 (42 U.S.C. 
    10154). Subpart L also issued under sec. 189, 68 Stat. 955 (42 
    U.S.C. 2239). Appendix A also issued under sec. 6, Pub. L. 91-560, 
    84 Stat. 1473 (42 U.S.C. 2135). Appendix B also issued under sec. 
    10, Pub. L. 99-240, 99 Stat. 1842 (42 U.S.C. 2021b et. seq.).
    
        2. Section 2.1201, paragraph (a)(3) is added to read as follows:
    
    
    Sec. 2.1201  Scope of subpart.
    
        (a) * * *
        (3) The amendment of a Part 50 license following permanent removal 
    of fuel from the Part 50 facility to an authorized facility for 
    licensees that have previously made declarations related to permanent 
    cessation of operations and permanent removal of fuel from the reactor 
    in accordance with Sec. 50.82(a)(1). Subpart L hearings for the license 
    termination plan amendment, if conducted, must be completed before 
    license termination.
    * * * * *
         3. Section 2.1203, paragraph (e) is revised to read as follows:
    
    
    Sec. 2.1203  Docket; filing; service.
    
    * * * * *
        (e) A request for a hearing or petition for leave to intervene must 
    be served in accordance with Sec. 2.712 and Sec. 2.1205(f) and (R). All 
    other documents issued by the presiding officer or the Commission or 
    offered for filing are served in accordance with Sec. 2.712.
        4. Section 2.1205, paragraphs (c) through (n) are redesignated as 
    paragraphs (d) through (o), a new paragraph (c) is added, and newly 
    designated paragraphs (d), (e)(2), (e)(4), the introductory text of 
    paragraph (h), (i), the introductory text of paragraph (j), the 
    introductory text of paragraph (k), (k)(3), the introductory text of 
    paragraphs (l)(1) and (l)(2) are revised to read as follows:
    
    
    Sec. 2.1205  Request for a hearing; petition for leave to intervene.
    
    * * * * *
        (c) For amendments of Part 50 licenses under Sec. 2.1201(a)(3), a 
    notice of receipt of the application, with reference to the opportunity 
    for a hearing under the procedures set forth in this subpart, must be 
    published in the Federal Register at least 30 days prior to issuance of 
    the requested amendment by the Commission.
        (d) A person, other than an applicant, shall file a request for a 
    hearing within--
        (1) Thirty days of the agency's publication in the Federal Register 
    of a notice referring or relating to an application or the licensing 
    action requested by an application, which must include a reference to 
    the opportunity for a hearing under the procedures set forth in this 
    subpart. With respect to an amendment described in Sec. 2.1201(a)(3), 
    other than the one to terminate the license, the Commission, prior to 
    issuance of the requested amendment, will follow the procedures in 
    Sec. 50.91 and Sec. 50.92(c) to the extent necessary to make a 
    determination on whether the amendment involves a significant hazards 
    consideration. If the Commission finds there are significant hazards 
    considerations involved in the requested amendment, the amendment will 
    not be issued until any hearings under this paragraph are completed.
        (2) If a Federal Register notice is not published in accordance 
    with paragraph (d)(1), the earliest of--
        (i) Thirty days after the requester receives actual notice of a 
    pending application, or
        (ii) Thirty days after the requester receives actual notice of an 
    agency action granting an application in whole or in part, or
        (iii) One hundred and eighty days after agency action granting an 
    application in whole or in part.
        (e) * * *
        (2) How the interests may be affected by the results of the 
    proceeding, including the reasons why the requestor should be permitted 
    a hearing, with particular reference to the factors set out in 
    paragraph (h) of this section;
    * * * * *
        (4) The circumstances establishing that the request for a hearing 
    is timely in accordance with paragraph (d) of this section.
    * * * * *
        (h) In ruling on a request for a hearing filed under paragraph (d) 
    of this section, the presiding officer shall determine that the 
    specified areas of concern are germane to the subject matter of the 
    proceeding and that the petition is timely. The presiding officer also 
    shall determine that the requestor meets the judicial standards for 
    standing and shall consider, among other factors--
    * * * * *
        (i) If a hearing request filed under paragraph (b) of this section 
    is granted, the applicant and the NRC staff shall be parties to the 
    proceeding. If a hearing request filed under paragraph (c) or (d) of 
    this section is granted, the requestor shall be a party to the 
    proceeding along with the applicant and the NRC staff, if the NRC staff 
    chooses or is ordered to participate as a party in accordance with 
    Sec. 2.1213.
        (j) If a request for hearing is granted and a notice of the kind 
    described in paragraph (d)(1) previously has not been published in the 
    Federal Register, a notice of hearing must be published in the Federal 
    Register stating--
    * * * * *
        (k) Any petition for leave to intervene must be filed within 30 
    days of the date of publication of the notice of hearing. The petition 
    must set forth the information required under paragraph (e) of this 
    section.
    * * * * *
        (3) Thereafter, the petition for leave to intervene must be ruled 
    upon by the presiding officer, taking into account the matters set 
    forth in paragraph (h) of this section.
    * * * * *
        (l)(1) A request for a hearing or a petition for leave to intervene 
    found by the presiding officer to be untimely under paragraph (d) or 
    (k) of this section will be entertained only upon determination by the 
    Commission or the presiding officer that the requestor or petitioner 
    has established that--
    * * * * *
        (2) If the request for a hearing on the petition for leave to 
    intervene is found to be untimely and the requestor or petitioner fails 
    to establish that it otherwise should be entertained on the paragraph 
    (l)(1) of this section, the request or petition will be treated as a
    
    [[Page 39298]]
    
    petition under Sec. 2.206 and referred for appropriate disposition.
    * * * * *
        5. Section 2.1211, paragraph (b) is revised to read as follows:
    
    
    Sec. 2.1211  Participation by a person not a party.
    
    * * * * *
        (b) Within 30 days of an order granting a request for a hearing 
    made under Sec. 2.1205 (b)-(d) or, in instances when it is published, 
    within 30 days of notice of hearing issued under Sec. 2.1205(j), the 
    representative of the interested State, county, municipality, or an 
    agency thereof, may request an opportunity to participate in a 
    proceeding under this subpart. The request for an opportunity to 
    participate must state with reasonable specificity the requestor's 
    areas of concern about the licensing activity that is the subject 
    matter of the proceeding. Upon receipt of a request that is filed in 
    accordance with these time limits and that specifies the requestor's 
    areas of concern, the presiding officer shall afford the representative 
    a reasonable opportunity to make written and oral presentations in 
    accordance with Secs. 2.1233 and 2.1235, without requiring the 
    representative to take a position with respect to the issues. 
    Participants under this subsection may notice an appeal of an initial 
    decision in accordance with Sec. 2.1253 with respect to any issue on 
    which they participate.
    * * * * *
        6. Section 2.1213 is revised to read as follows:
    
    
    Sec. 2.1213  Role of the NRC staff.
    
        If a hearing request is filed under Sec. 2.1205(b), the NRC staff 
    shall be a party to the proceeding. If a hearing request is filed under 
    Sec. 2.1205 (c) or (d), within 10 days of the designation of a 
    presiding officer pursuant to Sec. 2.1207, the NRC staff shall notify 
    the presiding officer whether or not the staff desires to participate 
    as a party to the adjudication. In addition, upon a determination by 
    the presiding officer that the resolution of any issue in the 
    proceeding would be aided materially by the staff's participation in 
    the proceeding as a party, the presiding officer may order or permit 
    the NRC staff to participate as a party with respect to that particular 
    issue.
        7. Section 2.1233, paragraph (c) is revised to read as follows:
    
    
    Sec. 2.1233  Written presentations; written questions.
    
    * * * * *
        (c) In a hearing initiated under Sec. 2.1205(d), the initial 
    written presentation of a party that requested a hearing or petitioned 
    for leave to intervene must describe in detail any deficiency or 
    omission in the license application, with references to any particular 
    section or portion of the application considered deficient, give a 
    detailed statement of reasons why any particular sections or portion is 
    deficient or why an omission is material, and describe in detail what 
    relief is sought with respect to each deficiency or omission.
    * * * * *
        8. Section 2.1263 is revised to read as follows:
    
    
    Sec. 2.1263  Stays of NRC staff licensing actions or of decisions of a 
    presiding officer or the Commission pending hearing or review.
    
        Applications for a stay of any decision or action of the 
    Commission, a presiding officer, or any action by the NRC staff in 
    issuing a license in accordance with Sec. 2.1205(m) are governed by 
    Sec. 2.788, except that any request for a stay of staff licensing 
    action pending completion of an adjudication under this subpart must be 
    filed at the time a request for a hearing or petition to intervene is 
    filed or within 10 days of the staff's action, whichever is later. A 
    request for a stay of a staff licensing action must be filed with the 
    adjudicatory decisionmaker before which the licensing proceeding is 
    pending.
    
    PART 50--DOMESTIC LICENSING OF PRODUCTION AND UTILIZATION 
    FACILITIES
    
        9. The authority citation for Part 50 continues to read as follows:
    
        Authority: Secs. 102, 103, 104, 105, 161, 182, 183, 186, 189, 68 
    Stat. 936, 937, 938, 948, 953, 954, 955, 956, as amended, sec. 234, 
    83 Stat. 1244, as amended (42 U.S.C. 2132, 2133, 2134, 2135, 2201, 
    2232, 2233, 2236, 2239, 2282); secs. 201, as amended, 202, 206, 88 
    Stat. 1242, as amended, 1244, 1246 (42 U.S.C. 5841, 5842, 5846).
        Section 50.7 also issued under Pub. L. 95-601, sec. 10, 92 Stat. 
    2951 (42 U.S.C. 5851). Section 50.10 also issued under secs. 101, 
    185, 68 Stat. 955, as amended (42 U.S.C. 2131, 2235); sec. 102 Pub. 
    L. 91-190, 83 Stat. 853 (42 U.S.C. 4332). Sections 50.13, 50.54(dd), 
    and 50.103 also issued under sec. 108, 68 Stat. 939, as amended (42 
    U.S.C. 2138). Sections 50.23, 50.35, 50.55, and 50.56 also issued 
    under sec. 185, 68 Stat. 955 (42 U.S.C. 2235). Sections 50.33a, 
    50.55a and Appendix Q also issued under sec. 102, Pub. L. 91-190, 83 
    Stat. 853 (42 U.S.C. 4332). Sections 50.34 and 50.54 also issued 
    under sec. 204, 88 Stat. 1245 (42 U.S.C. 5844). Sections 50.58, 
    50.91, and 50.92 also issued under Pub. L. 97-415, 96 Stat. 2073 (42 
    U.S.C. 2239). Section 50.78 also issued under sec. 122, 68 Stat. 939 
    (42 U.S.C. 2152). Sections 50.80-50.81 also issued under sec. 184, 
    68 Stat. 954, as amended (42 U.S.C. 2234). Appendix F also issued 
    under sec. 187, 68 Stat. 955 (42 U.S.C. 2237).
    
        10. Section 50.2, the terms ``Certified fuel handler,'' ``Major 
    decommissioning activity,'' ``Major radioactive components,'' 
    ``Permanent cessation of operations,'' and ``Permanent fuel removal,'' 
    are added to read as follows:
    
    
    Sec. 50.2  Definitions.
    
    * * * * *
        Certified fuel handler means, for a nuclear power reactor facility, 
    a non-licensed operator who has qualified in accordance with a fuel 
    handler training program approved by the Commission.
    * * * * *
        Major decommissioning activity means, for a nuclear power reactor 
    facility, any activity that results in permanent removal of major 
    radioactive components, permanently modifies the structure of the 
    containment, or results in dismantling components for shipment 
    containing greater than class C waste in accordance with Sec. 61.55 of 
    this chapter.
        Major radioactive components means, for a nuclear power reactor 
    facility, the reactor vessel and internals, steam generators, 
    pressurizers, large bore reactor coolant system piping, and other large 
    components that are radioactive to a comparable degree.
    * * * * *
        Permanent cessation of operation(s) means, for a nuclear power 
    reactor facility, a certification by a licensee to the NRC that it has 
    permanently ceased or will permanently cease reactor operation(s), or a 
    final legally effective order to permanently cease operation(s) has 
    come into effect.
        Permanent fuel removal means, for a nuclear power reactor facility, 
    a certification by the licensee to the NRC that it has permanently 
    removed all fuel assemblies from the reactor vessel.
    * * * * *
        11. Section 50.4, paragraphs (b)(8) and (b)(9) are added to read as 
    follows:
    
    
    Sec. 50.4  Written communications.
    
    * * * * *
        (b) * * *
        (8) Certification of permanent cessation of operations. The 
    licensee's certification of permanent cessation of operations, pursuant 
    to Sec. 50.82(a)(1), must state the date on which operations have 
    ceased or will cease, and the signed and notarized original must be 
    submitted to: The Nuclear Regulatory Commission, Document Control Desk, 
    Washington, DC 20555-0001.
        (9) Certification of permanent fuel removal. The licensee's 
    certification of
    
    [[Page 39299]]
    
    permanent fuel removal, pursuant to Sec. 50.82(a)(1), must state the 
    date on which the fuel was removed from the reactor vessel and the 
    disposition of the fuel, and the signed and notarized original must be 
    submitted to: The Nuclear Regulatory Commission, Document Control Desk, 
    Washington, DC 20555-0001.
    * * * * *
        12. Section 50.36, paragraphs (c)(6) and (c)(7) are redesignated as 
    (c)(7) and (c)(8) and new paragraphs (c)(6) and (e) are added to read 
    as follows:
    
    
    Sec. 50.36  Technical specifications.
    
    * * * * *
        (c) * * *
        (6) Decommissioning. This paragraph applies only to nuclear power 
    reactor facilities that have submitted the certifications required by 
    Sec. 50.82(a)(1) and to non-power reactor facilities which are not 
    authorized to operate. Technical specifications involving safety 
    limits, limiting safety system settings, and limiting control system 
    settings; limiting conditions for operation; surveillance requirements; 
    design features; and administrative controls will be developed on a 
    case-by-case basis.
    * * * * *
        (e) The provisions of this section apply to each nuclear reactor 
    licensee whose authority to operate the reactor has been removed by 
    license amendment, order, or regulation.
        13. Section 50.36a is revised to read as follows:
    
    
    Sec. 50.36a  Technical specifications on effluents from nuclear power 
    reactors.
    
        (a) In order to keep releases of radioactive materials to 
    unrestricted areas during normal conditions, including expected 
    occurrences, as low as is reasonably achievable, each licensee of a 
    nuclear power reactor will include technical specifications that, in 
    addition to requiring compliance with applicable provisions of 
    Sec. 20.1301 of this chapter, require that:
        (1) Operating procedures developed pursuant to Sec. 50.34a(c) for 
    the control of effluents be established and followed and that the 
    radioactive waste system, pursuant to Sec. 50.34a, be maintained and 
    used. The licensee shall retain the operating procedures in effect as a 
    record until the Commission terminates the license and shall retain 
    each superseded revision of the procedures for 3 years from the date it 
    was superseded.
        (2) Each licensee shall submit a report to the Commission annually 
    that specifies the quantity of each of the principal radionuclides 
    released to unrestricted areas in liquid and in gaseous effluents 
    during the previous 12 months, including any other information as may 
    be required by the Commission to estimate maximum potential annual 
    radiation doses to the public resulting from effluent releases. The 
    report must be submitted as specified in Sec. 50.4, and the time 
    between submission of the reports must be no longer than 12 months. If 
    quantities of radioactive materials released during the reporting 
    period are significantly above design objectives, the report must cover 
    this specifically. On the basis of these reports and any additional 
    information the Commission may obtain from the licensee or others, the 
    Commission may require the licensee to take action as the Commission 
    deems appropriate.
        (b) In establishing and implementing the operating procedures 
    described in paragraph (a) of this section, the licensee shall be 
    guided by the following considerations: Experience with the design, 
    construction, and operation of nuclear power reactors indicates that 
    compliance with the technical specifications described in this section 
    will keep average annual releases of radioactive material in effluents 
    and their resultant committed effective dose equivalents at small 
    percentages of the dose limits specified in Sec. 20.1301 and in the 
    license. At the same time, the licensee is permitted the flexibility of 
    operation, compatible with considerations of health and safety, to 
    assure that the public is provided a dependable source of power even 
    under unusual conditions which may temporarily result in releases 
    higher than such small percentages, but still within the limits 
    specified in Sec. 20.1301 of this chapter and in the license. It is 
    expected that in using this flexibility under unusual conditions, the 
    licensee will exert its best efforts to keep levels of radioactive 
    material in effluents as low as is reasonably achievable. The guides 
    set out in appendix I, provide numerical guidance on limiting 
    conditions for operation for light-water cooled nuclear power reactors 
    to meet the requirement that radioactive materials in effluents 
    released to unrestricted areas be kept as low as is reasonably 
    achievable.
        14. Section 50.36b is revised to read as follows:
    
    
    Sec. 50.36b  Environmental conditions.
    
        Each license authorizing operation of a production or utilization 
    facility, and each license for a nuclear power reactor facility for 
    which the certification of permanent cessation of operations required 
    under Sec. 50.82(a)(1) has been submitted, which is of a type described 
    in Sec. 50.21(b) (2) or (3) or Sec. 50.22 or is a testing facility, may 
    include conditions to protect the environment to be set out in an 
    attachment to the license which is incorporated in and made a part of 
    the license. These conditions will be derived from information 
    contained in the environmental report and the supplement to the 
    environmental report submitted pursuant to Secs. 51.50 and 51.53 of 
    this chapter as analyzed and evaluated in the NRC record of decision, 
    and will identify the obligations of the licensee in the environmental 
    area, including, as appropriate, requirements for reporting and keeping 
    records of environmental data, and any conditions and monitoring 
    requirement for the protection of the nonaquatic environment.
        15. Section 50.44, paragraph (a), is revised to read as follows:
    
    
    Sec. 50.44  Standards for combustible gas control system in light-
    water-cooled power reactors.
    
        (a) Each boiling or pressurized light-water nuclear power reactor 
    fueled with oxide pellets within cylindrical zircaloy or ZIRLO 
    cladding, must, as provided in paragraphs (b) through (d) of this 
    section, include means for control of hydrogen gas that may be 
    generated, following a postulated loss-of-coolant accident (LOCA) by--
        (1) Metal-water reaction involving the fuel cladding and the 
    reactor coolant,
        (2) Radiolytic decomposition of the reactor coolant, and
        (3) Corrosion of metals.
    
    This section does not apply to a nuclear power reactor facility for 
    which the certifications required under Sec. 50.82(a)(1) have been 
    submitted.
    * * * * *
        16. Section 50.46, paragraph (a)(1)(i) is revised to read as 
    follows:
    
    
    Sec. 50.46  Acceptance criteria for emergency core cooling systems for 
    light-water nuclear power reactors.
    
        (a)(1)(i) Each boiling or pressurized light-water nuclear power 
    reactor fueled with uranium oxide pellets within cylindrical zircaloy 
    or ZIRLO cladding must be provided with an emergency core cooling 
    system (ECCS) that must be designed so that its calculated cooling 
    performance following postulated loss-of-coolant accidents conforms to 
    the criteria set forth in paragraph (b) of this section. ECCS cooling 
    performance must be calculated in accordance with an acceptable 
    evaluation model and must be calculated for a number of postulated 
    loss-of-coolant accidents of different sizes, locations, and other 
    properties sufficient to provide assurance that the
    
    [[Page 39300]]
    
    most severe postulated loss-of-coolant accidents are calculated. Except 
    as provided in paragraph (a)(1)(ii) of this section, the evaluation 
    model must include sufficient supporting justification to show that the 
    analytical technique realistically describes the behavior of the 
    reactor system during a loss-of-coolant accident. Comparisons to 
    applicable experimental data must be made and uncertainties in the 
    analysis method and inputs must be identified and assessed so that the 
    uncertainty in the calculated results can be estimated. This 
    uncertainty must be accounted for, so that, when the calculated ECCS 
    cooling performance is compared to the criteria set forth in paragraph 
    (b) of this section, there is a high level of probability that the 
    criteria would not be exceeded. Appendix K, Part II Required 
    Documentation, sets forth the documentation requirements for each 
    evaluation model. This section does not apply to a nuclear power 
    reactor facility for which the certifications required under 
    Sec. 50.82(a)(1) have been submitted.
    * * * * *
        17. Section Sec. 50.48, paragraph (f) is added to read as follows:
    
    
    Sec. 50.48  Fire protection.
    
    * * * * *
        (f) Licensees that have submitted the certifications required under 
    Sec. 50.82(a)(1) shall maintain a fire protection program to address 
    the potential for fires which could cause the release or spread of 
    radioactive materials (i.e., which could result in a radiological 
    hazard).
        (1) The objectives of the fire protection program are to--
        (i) Reasonably prevent such fires from occurring;
        (ii) Rapidly detect, control, and extinguish those fires which do 
    occur and which could result in a radiological hazard; and
        (iii) Ensure that the risk of fire-induced radiological hazards to 
    the public, environment and plant personnel is minimized.
        (2) The fire protection program must be assessed by the licensee on 
    a regular basis and revised as appropriate throughout the various 
    stages of facility decommissioning.
        (3) The licensee may make changes to the fire protection program 
    without NRC approval if these changes do not reduce the effectiveness 
    of fire protection for facilities, systems, and equipment which could 
    result in a radiological hazard, taking into account the 
    decommissioning plant conditions and activities.
        18. Section 50.49, paragraph (a) is revised to read as follows:
    
    
    Sec. 50.49  Environmental qualification of electric equipment important 
    to safety for nuclear power plants.
    
        (a) Each holder of or an applicant for a license for a nuclear 
    power plant, other than a nuclear power plant for which the 
    certifications required under Sec. 50.82(a)(1) have been submitted, 
    shall establish a program for qualifying the electric equipment defined 
    in paragraph (b) of this section.
    * * * * *
        19. Section 50.51, the section heading is revised, the existing 
    paragraph is designated paragraph (a), and new paragraph (b) is added 
    to read as follows:
    * * * * *
    
    
    Sec. 50.51  Continuation of license.
    
    * * * * *
        (b) Each license for a facility that has permanently ceased 
    operations, continues in effect beyond the expiration date to authorize 
    ownership and possession of the production or utilization facility, 
    until the Commission notifies the licensee in writing that the license 
    is terminated. During such period of continued effectiveness the 
    licensee shall--
        (1) Take actions necessary to decommission and decontaminate the 
    facility and continue to maintain the facility, including, where 
    applicable, the storage, control and maintenance of the spent fuel, in 
    a safe condition, and
        (2) Conduct activities in accordance with all other restrictions 
    applicable to the facility in accordance with the NRC regulations and 
    the provisions of the specific 10 CFR part 50 license for the facility.
    
        20. Section 50.54, paragraphs (o) and (y) are revised to read as 
    follows:
    
    
    Sec. 50.54  Conditions of licenses.
    
    * * * * *
        (o) Primary reactor containments for water cooled power reactors, 
    other than facilities for which the certifications required under 
    Sec. 50.82(a)(1) have been submitted, shall be subject to the 
    requirements set forth in appendix J to this part.
    * * * * *
        (y) Licensee action permitted by paragraph (x) of this section 
    shall be approved, as a minimum, by a licensed senior operator, or, at 
    a nuclear power reactor facility for which the certifications required 
    under Sec. 50.82(a)(1) have been submitted, by either a licensed senior 
    operator or a certified fuel handler, prior to taking the action.
    * * * * *
        21. Section 50.59, paragraphs (d) and (e) are added to read as 
    follows:
    
    
    Sec. 50.59  Changes, tests and experiments.
    
    * * * * *
        (d) The provisions of this section apply to each nuclear power 
    reactor licensee that has submitted the certification of permanent 
    cessation of operations required under Sec. 50.82(a)(1)(i).
        (e) The provisions of paragraphs (a) through (c) of this section 
    apply to each non-power reactor licensee whose license no longer 
    authorizes operation of the reactor.
    
        22. Section 50.60, paragraph (a) is revised to read as follows:
    
    
    Sec. 50.60  Acceptance criteria for fracture prevention measures for 
    light-water nuclear power reactors for normal operation.
    
        (a) Except as provided in paragraph (b) of this section, all light-
    water nuclear power reactors, other than reactor facilities for which 
    the certifications required under Sec. 50.82(a)(1) have been submitted, 
    must meet the fracture toughness and material surveillance program 
    requirements for the reactor coolant pressure boundary set forth in 
    appendices G and H to this part.
    * * * * *
        23. Section 50.61, paragraph (b)(1) is revised to read as follows:
    
    
    Sec. 50.61  Fracture toughness requirements for protection against 
    pressurized thermal shock events.
    
    * * * * *
        (b) Requirements.
         (1) For each pressurized water nuclear power reactor for which an 
    operating license has been issued, other than a nuclear power reactor 
    facility for which the certifications required under Sec. 50.82(a)(1) 
    have been submitted, the licensee shall have projected values of 
    RTPTS, accepted by the NRC, for each reactor vessel beltline 
    material for the EOL fluence of the material. The assessment of 
    RTPTS must use the calculation procedures given in paragraph 
    (c)(1) of this section, except as provided in paragraphs (c)(2) and 
    (c)(3) of this section. The assessment must specify the bases for the 
    projected value of RTPTS for each vessel beltline material, 
    including the assumptions regarding core loading patterns, and must 
    specify the copper and nickel contents and the fluence value used in 
    the calculation for each beltline material. This assessment must be 
    updated whenever there is a significant 2 change in projected 
    values of RTPTS, or
    
    [[Page 39301]]
    
    upon request for a change in the expiration date for operation of the 
    facility.
    ---------------------------------------------------------------------------
    
        \2\ Changes to RTPTS values are considered significant if 
    either the previous value or the current value, or both values, 
    exceed the screening criterion prior to the expiration of the 
    operating license, including any renewed term, if applicable for the 
    plant.
    ---------------------------------------------------------------------------
    
    * * * * *
        24. Section 50.62, paragraph (a) is revised to read as follows:
    
    
    Sec. 50.62  Requirements for reduction of risk from anticipated 
    transients without scram (ATWS) events for light-water-cooled nuclear 
    power plants.
    
         (a) Applicability. The requirements of this section apply to all 
    commercial light-water-cooled nuclear power plants, other than nuclear 
    power reactor facilities for which the certifications required under 
    Sec. 50.82(a)(1) have been submitted.
    * * * * *
        25. Section 50.65, paragraph (a)(1) is revised to read as follows:
    
    
    Sec. 50.65  Requirements for monitoring the effectiveness of 
    maintenance at nuclear power plants.
    
        (a)(1) Each holder of a license to operate a nuclear power plant 
    under Secs. 50.21(b) or 50.22 shall monitor the performance or 
    condition of structures, systems, or components, against licensee-
    established goals, in a manner sufficient to provide reasonable 
    assurance that such structures, systems, and components, as defined in 
    paragraph (b), are capable of fulfilling their intended functions. Such 
    goals shall be established commensurate with safety and, where 
    practical, take into account industry-wide operating experience. When 
    the performance or condition of a structure, system, or component does 
    not meet established goals, appropriate corrective action shall be 
    taken. For a nuclear power plant for which the licensee has submitted 
    the certifications specified in Sec. 50.82(a)(1), this section only 
    shall apply to the extent that the licensee shall monitor the 
    performance or condition of all structures, systems, or components 
    associated with the storage, control, and maintenance of spent fuel in 
    a safe condition, in a manner sufficient to provide reasonable 
    assurance that such structures, systems, and components are capable of 
    fulfilling their intended functions.
    * * * * *
        26. Section 50.71, paragraph (e)(4) is revised and paragraph (f) is 
    added to read as follows:
    
    
    Sec. 50.71  Maintenance of records, making of reports.
    
    * * * * *
        (e) * * *
        (4) Subsequent revisions must be filed annually or 6 months after 
    each refueling outage provided the interval between successive updates 
    does not exceed 24 months. The revisions must reflect all changes up to 
    a maximum of 6 months prior to the date of filling. For nuclear power 
    reactor facilities that have submitted the certifications required by 
    Sec. 50.82(a)(1), subsequent revisions must be filed every 24 months.
    * * * * *
        (f) The provisions of this section apply to nuclear power reactor 
    licensees that have submitted the certification of permanent cessation 
    of operations required under Sec. 50.82(a)(1)(i). The provisions of 
    paragraphs (a), (c), and (d) of this section also apply to non-power 
    reactor licensees that are no longer authorized to operate.
        27. Section 50.75, paragraph (f) is revised to read as follows:
    
    
    Sec. 50.75  Reporting and recordkeeping for decommissioning planning.
    
    * * * * *
        (f)(1) Each power reactor licensee shall at or about 5 years prior 
    to the projected end of operations submit a preliminary decommissioning 
    cost estimate which includes an up-to-date assessment of the major 
    factors that could affect the cost to decommission.
        (2) Each non-power reactor licensee shall at or about 2 years prior 
    to the projected end of operations submit a preliminary decommissioning 
    plan containing a cost estimate for decommissioning and an up-to-date 
    assessment of the major factors that could affect planning for 
    decommissioning. Factors to be considered in submitting this 
    preliminary plan information include--
        (i) The decommissioning alternative anticipated to be used. The 
    requirements of Sec. 50.82(b)(4)(i) must be considered at this time;
        (ii) Major technical actions necessary to carry out decommissioning 
    safely;
        (iii) The current situation with regard to disposal of high-level 
    and low-level radioactive waste;
        (iv) Residual radioactivity criteria;
        (v) Other site specific factors which could affect decommissioning 
    planning and cost.
        (3) If necessary, the cost estimate, for power and non-power 
    reactors, shall also include plans for adjusting levels of funds 
    assured for decommissioning to demonstrate that a reasonable level of 
    assurance will be provided that funds will be available when needed to 
    cover the cost of decommissioning.
    * * * * *
        28. Section 50.82 is revised to read as follows:
    
    
    Sec. 50.82  Termination of license.
    
        For power reactor licensees who, before the effective date of this 
    rule, either submitted a decommissioning plan for approval or possess 
    an approved decommissioning plan, the plan is considered to be the 
    PSDAR submittal required under paragraph (a)(4) of this section and the 
    provisions of this section apply accordingly. For power reactor 
    licensees whose decommissioning plan approval activities have been 
    relegated to notice of opportunity for a hearing under subpart G of 10 
    CFR part 2, the public meeting convened and 90-day delay of major 
    decommissioning activities required in paragraphs (a)(4)(ii) and (a)(5) 
    of this section shall not apply, and any orders arising from 
    proceedings under subpart G of 10 CFR part 2 shall continue and remain 
    in effect absent any orders from the Commission.
        (a) For power reactor licensees--
        (1) (i) When a licensee has determined to permanently cease 
    operations the licensee shall, within 30 days, submit a written 
    certification to the NRC, consistent with the requirements of 
    Sec. 50.4(b)(8);
        (ii) Once fuel has been permanently removed from the reactor 
    vessel, the licensee shall submit a written certification to the NRC 
    that meets the requirements of Sec. 50.4(b)(9) and;
        (iii) For licensees whose licenses have been permanently modified 
    to allow possession but not operation of the facility, before the 
    effective date of this rule, the certifications required in paragraphs 
    (a)(1) (i)-(ii) of this section shall be deemed to have been submitted.
        (2) Upon docketing of the certifications for permanent cessation of 
    operations and permanent removal of fuel from the reactor vessel, or 
    when a final legally effective order to permanently cease operations 
    has come into effect, the 10 CFR part 50 license no longer authorizes 
    operation of the reactor or emplacement or retention of fuel into the 
    reactor vessel.
        (3) Decommissioning will be completed within 60 years of permanent 
    cessation of operations. Completion of decommissioning beyond 60 years 
    will be approved by the Commission only when necessary to protect 
    public health and safety. Factors that will be considered by the 
    Commission in evaluating an alternative that provides for completion of 
    decommissioning beyond 60 years of permanent cessation of operations 
    include unavailability of waste disposal capacity and other site-
    specific factors affecting the licensee's capability to carry out 
    decommissioning, including presence of other nuclear facilities at the 
    site.
    
    [[Page 39302]]
    
        (4) (i) Prior to or within 2 years following permanent cessation of 
    operations, the licensee shall submit a post-shutdown decommissioning 
    activities report (PSDAR) to the NRC, and a copy to the affected 
    State(s). The report must include a description of the planned 
    decommissioning activities along with a schedule for their 
    accomplishment, an estimate of expected costs, and a discussion that 
    provides the reasons for concluding that the environmental impacts 
    associated with site-specific decommissioning activities will be 
    bounded by appropriate previously issued environmental impact 
    statements.
        (ii) The NRC shall notice receipt of the PSDAR and make the PSDAR 
    available for public comment. The NRC shall also schedule a public 
    meeting in the vicinity of the licensee's facility upon receipt of the 
    PSDAR. The NRC shall publish a notice in the Federal Register and in a 
    forum, such as local newspapers, that is readily accessible to 
    individuals in the vicinity of the site, announcing the date, time and 
    location of the meeting, along with a brief description of the purpose 
    of the meeting.
        (5) Licensees shall not perform any major decommissioning 
    activities, as defined in Sec. 50.2, until 90 days after the NRC has 
    received the licensee's PSDAR submittal and until certifications of 
    permanent cessation of operations and permanent removal of fuel from 
    the reactor vessel, as required under Sec. 50.82(a)(1), have been 
    submitted.
        (6) Licensees shall not perform any decommissioning activities, as 
    defined in Sec. 50.2, that--
        (i) Foreclose release of the site for possible unrestricted use;
        (ii) Result in significant environmental impacts not previously 
    reviewed; or
        (iii) Result in there no longer being reasonable assurance that 
    adequate funds will be available for decommissioning.
        (7) In taking actions permitted under Sec. 50.59 following 
    submittal of the PSDAR, the licensee shall notify the NRC, in writing 
    and send a copy to the affected State(s), before performing any 
    decommissioning activity inconsistent with, or making any significant 
    schedule change from, those actions and schedules described in the 
    PSDAR, including changes that significantly increase the 
    decommissioning cost.
        (8)(i) Decommissioning trust funds may be used by licensees if--
        (A) The withdrawals are for expenses for legitimate decommissioning 
    activities consistent with the definition of decommissioning in 
    Sec. 50.2;
        (B) The expenditure would not reduce the value of the 
    decommissioning trust below an amount necessary to place and maintain 
    the reactor in a safe storage condition if unforeseen conditions or 
    expenses arise and;
        (C) The withdrawals would not inhibit the ability of the licensee 
    to complete funding of any shortfalls in the decommissioning trust 
    needed to ensure the availability of funds to ultimately release the 
    site and terminate the license.
        (ii) Initially, 3 percent of the generic amount specified in 
    Sec. 50.75 may be used for decommissioning planning. For licensees that 
    have submitted the certifications required under Sec. 50.82(a)(1) and 
    commencing 90 days after the NRC has received the PSDAR, an additional 
    20 percent may be used. A site-specific decommissioning cost estimate 
    must be submitted to the NRC prior to the licensee using any funding in 
    excess of these amounts.
        (iii) Within 2 years following permanent cessation of operations, 
    if not already submitted, the licensee shall submit a site-specific 
    decommissioning cost estimate.
        (iv) For decommissioning activities that delay completion of 
    decommissioning by including a period of storage or surveillance, the 
    licensee shall provide a means of adjusting cost estimates and 
    associated funding levels over the storage or surveillance period.
        (9) All power reactor licensees must submit an application for 
    termination of license. The application for termination of license must 
    be accompanied or preceded by a license termination plan to be 
    submitted for NRC approval.
        (i) The license termination plan must be a supplement to the FSAR 
    or equivalent and must be submitted at least 2 years before termination 
    of the license date.
        (ii) The license termination plan must include--
        (A) A site characterization;
        (B) Identification of remaining dismantlement activities;
        (C) Plans for site remediation;
        (D) Detailed plans for the final radiation survey;
        (E) A description of the end use of the site, if restricted;
        (F) An updated site-specific estimate of remaining decommissioning 
    costs; and
        (G) A supplement to the environmental report, pursuant to 
    Sec. 51.53, describing any new information or significant environmental 
    change associated with the licensee's proposed termination activities.
        (iii) The NRC shall notice receipt of the license termination plan 
    and make the license termination plan available for public comment. The 
    NRC shall also schedule a public meeting in the vicinity of the 
    licensee's facility upon receipt of the license termination plan. The 
    NRC shall publish a notice in the Federal Register and in a forum, such 
    as local newspapers, which is readily accessible to individuals in the 
    vicinity of the site, announcing the date, time and location of the 
    meeting, along with a brief description of the purpose of the meeting.
        (10) If the license termination plan demonstrates that the 
    remainder of decommissioning activities will be performed in accordance 
    with the regulations in this chapter, will not be inimical to the 
    common defense and security or to the health and safety of the public, 
    and will not have a significant effect on the quality of the 
    environment and after notice to interested persons, the Commission 
    shall approve the plan, by license amendment, subject to such 
    conditions and limitations as it deems appropriate and necessary and 
    authorize implementation of the license termination plan.
        (11) The Commission shall terminate the license if it determines 
    that--
        (i) The remaining dismantlement has been performed in accordance 
    with the approved license termination plan, and
        (ii) The terminal radiation survey and associated documentation 
    demonstrates that the facility and site are suitable for release.
        (b) For non-power reactor licensees--
        (1) A licensee that permanently ceases operations must make 
    application for license termination within 2 years following permanent 
    cessation of operations, and in no case later than 1 year prior to 
    expiration of the operating license. Each application for termination 
    of a license must be accompanied or preceded by a proposed 
    decommissioning plan. The contents of the decommissioning plan are 
    specified in paragraph (b)(4) of this section.
        (2) For decommissioning plans in which the major dismantlement 
    activities are delayed by first placing the facility in storage, 
    planning for these delayed activities may be less detailed. Updated 
    detailed plans must be submitted and approved prior to the start of 
    these activities.
        (3) For decommissioning plans that delay completion of 
    decommissioning by including a period of storage or surveillance, the 
    licensee shall provide that--
        (i) Funds needed to complete decommissioning be placed into an 
    account segregated from the licensee's assets and outside the 
    licensee's
    
    [[Page 39303]]
    
    administrative control during the storage or surveillance period, or a 
    surety method or fund statement of intent be maintained in accordance 
    with the criteria of Sec. 50.75(e); and
        (ii) Means be included for adjusting cost estimates and associated 
    funding levels over the storage or surveillance period.
        (4) The proposed decommissioning plan must include--
        (i) The choice of the alternative for decommissioning with a 
    description of activities involved. An alternative is acceptable if it 
    provides for completion of decommissioning without significant delay. 
    Consideration will be given to an alternative which provides for 
    delayed completion of decommissioning only when necessary to protect 
    the public health and safety. Factors to be considered in evaluating an 
    alternative which provides for delayed completion of decommissioning 
    include unavailability of waste disposal capacity and other site-
    specific factors affecting the licensee's capability to carry out 
    decommissioning, including the presence of other nuclear facilities at 
    the site.
        (ii) A description of the controls and limits on procedures and 
    equipment to protect occupational and public health and safety;
        (iii) A description of the planned final radiation survey;
        (iv) An updated cost estimate for the chosen alternative for 
    decommissioning, comparison of that estimate with present funds set 
    aside for decommissioning, and plan for assuring the availability of 
    adequate funds for completion of decommissioning; and
        (v) A description of technical specifications, quality assurance 
    provisions and physical security plan provisions in place during 
    decommissioning.
        (5) If the decommissioning plan demonstrates that the 
    decommissioning will be performed in accordance with the regulations in 
    this chapter and will not be inimical to the common defense and 
    security or to the health and safety of the public, and after notice to 
    interested persons, the Commission will approve, by amendment, the plan 
    subject to such conditions and limitations as it deems appropriate and 
    necessary. The approved decommissioning plan will be a supplement to 
    the Safety Analysis report or equivalent.
        (6) The Commission will terminate the license if it determines 
    that--
        (i) The decommissioning has been performed in accordance with the 
    approved decommissioning plan, and
        (ii) The terminal radiation survey and associated documentation 
    demonstrates that the facility and site are suitable for release.
        (c) For a facility that has permanently ceased operation before the 
    expiration of its license, the collection period for any shortfall of 
    funds will be determined, upon application by the licensee, on a case-
    by-case basis taking into account the specific financial situation of 
    each licensee.
         29. Section 50.91, the introductory text is revised to read as 
    follows:
    
    
    Sec. 50.91  Notice for public comment; State consultation.
    
        The Commission will use the following procedures for an application 
    requesting an amendment to an operating license for a facility licensed 
    under Sec. 50.21(b) or Sec. 50.22 or for a testing facility, except for 
    amendments subject to hearings governed by Secs. 2.1201-2.1263 of this 
    chapter. For amendments subject to Secs. 2.1201-2.1263 of this chapter, 
    the following procedures will apply only to the extent specifically 
    referenced in Sec. 2.1205 (c) and (d) of this chapter:
    * * * * *
        30. Section 50.111, paragraph (b) is revised to read as follows:
    
    
    Sec. 50.111  Criminal penalties.
    
    * * * * *
        (b) The regulations in 10 CFR Part 50 that are not issued under 
    sections 161b, 161i, or 161o for the purposes of section 223 are as 
    follows: Secs. 50.1, 50.2, 50.3, 50.4, 50.8, 50.11, 50.12, 50.13, 
    50.20, 50.21, 50.22, 50.23, 50.30, 50.31, 50.32, 50.33, 50.34a, 50.35, 
    50.36b, 50.37, 50.38, 50.39, 50.40, 50.41, 50.42, 50.43, 50.45, 50.50, 
    50.51, 50.52, 50.53, 50.56, 50.57, 50.58, 50.81, 50.90, 50.91, 50.92, 
    50.100, 50.101, 50.102, 50.103, 50.109, 50.110, 50.111.
        31. Appendix I to 10 CFR part 50 is amended by revising Section 
    (I), the introductory text of Section (IV), and Section (IV)(C) to read 
    as follows:
    
    Appendix I to Part 50--Numerical Guides for Design Objectives and 
    Limiting Conditions of Operation to Meet the Criterion ``As Low As Is 
    Reasonably Achievable'' for Radioactive Material in Light-Water-Cooled 
    Nuclear Power Reactor Effluents
    
        SECTION I. Introduction. Section 50.34a provides that an 
    application for a permit to construct a nuclear power reactor shall 
    include a description of the preliminary design of equipment to be 
    installed to maintain control over radioactive materials in gaseous 
    and liquid effluents produced during normal conditions, including 
    expected occurrences. In the case of an application filed on or 
    after January 2, 1971, the application must also identify the design 
    objectives, and the means to be employed, for keeping levels of 
    radioactive material in effluents to unrestricted areas as low as 
    practicable.
        Section 50.36a contains provisions designed to assure that 
    releases of radioactive material from nuclear power reactors to 
    unrestricted areas during normal conditions, including expected 
    occurrences, are kept as low as practicable.
    * * * * *
        SEC. IV. Guides on technical specifications for limiting 
    conditions for operation for light-water-cooled nuclear power 
    reactors licensed under 10 CFR part 50. The guides on limiting 
    conditions for operation for light-water-cooled nuclear power 
    reactors set forth below may be used by an applicant for a license 
    to operate a light-water-cooled nuclear power reactor or a licensee 
    who has submitted a certification of permanent cessation of 
    operations under Sec. 50.82(a)(1) as guidance in developing 
    technical specifications under Sec. 50.36a(a) to keep levels of 
    radioactive materials in effluents to unrestricted areas as low as 
    is reasonably achievable.
        Section 50.36a(b) provides that licensees shall be guided by 
    certain considerations in establishing and implementing operating 
    procedures specified in technical specifications that take into 
    account the need for operating flexibility and at the same time 
    assure that the licensee will exert his best effort to keep levels 
    of radioactive material in effluents as low as is reasonably 
    achievable. The guidance set forth below provides additional and 
    more specific guidance to licensees in this respect.
        Through the use of the guides set forth in this section it is 
    expected that the annual release of radioactive material in 
    effluents from light-water-cooled nuclear power reactors can 
    generally be maintained within the levels set forth as numerical 
    guides for design objectives in Section II.
        At the same time, the licensee is permitted the flexibility of 
    operations, compatible with considerations of health and safety, to 
    assure that the public is provided a dependable source of power even 
    under unusual conditions which may temporarily result in releases 
    higher than numerical guides for design objectives but still within 
    levels that assure that the average population exposure is 
    equivalent to small fractions of doses from natural background 
    radiation. It is expected that in using this operational flexibility 
    under unusual conditions, the licensee will exert his best efforts 
    to keep levels of radioactive material in effluents within the 
    numerical guides for design objectives.
    * * * * *
        C. If the data developed in the surveillance and monitoring 
    program described in paragraph B of Section III or from other 
    monitoring programs show that the relationship between the 
    quantities of radioactive material released in liquid and gaseous 
    effluents and the dose to individuals in unrestricted areas is 
    significantly different from that assumed in the calculations used 
    to determine design objectives pursuant to Sections II and III, the 
    Commission may modify the quantities in the technical
    
    [[Page 39304]]
    
    specifications defining the limiting conditions in a license to 
    operate a light-water-cooled nuclear power reactor or a license 
    whose holder has submitted a certification of permanent cessation of 
    operations under Sec. 50.82(a)(1).
    * * * * *
    
    PART 51--ENVIRONMENTAL PROTECTION REGULATIONS FOR DOMESTIC 
    LICENSING AND RELATED REGULATORY FUNCTIONS
    
        32. The authority citation for Part 51 continues to read as 
    follows:
    
        Authority: Sec. 161, 68 Stat. 948, as amended, sec. 1701, 106 
    Stat. 2951, 2952, 2953, (42 U.S.C. 2201, 2297f); secs. 201, as 
    amended, 202, 88 Stat. 1242, as amended, 1244 (42 U.S.C. 5841, 
    5842).
    
        Subpart A also issued under National Environmental Policy Act of 
    1969, secs. 102, 104, 105, 83 Stat. 853-854, as amended (42 U.S.C. 
    4332, 4334, 4335); and Pub. L. 95-604, Title II, 92 Stat. 3033-3041; 
    and sec. 193, Pub. L. 101-575, 104 Stat. 2835 42 U.S.C. 2243). 
    Sections 51.20, 51.30, 51.60, 51.80, and 51.97 also issued under 
    secs. 135, 141, Pub. L. 97-425, 96 Stat. 2232, 2241, and sec. 148, 
    Pub. L. 100-203, 101 Stat. 1330-223 (42 U.S.C. 10155, 10161, 10168). 
    Section 51.22 also issued under sec. 274, 73 Stat. 688, as amended 
    by 92 Stat. 3036-3038 (42 U.S.C. 2021) and under Nuclear Waste 
    Policy Act of 1982, sec. 121, 96 Stat. 2228 (42 U.S.C. 10141). 
    Sections 51.43, 51.67, and 51.109 also under Nuclear Waste Policy 
    Act of 1982, sec. 114(f), 96 Stat. 2216, as amended (42 U.S.C. 
    10134(f)).
    * * * * *
        33. Section 51.53, paragraph (b) is revised to read as follows:
    
    
    Sec. 51.53  Supplement to environmental report.
    
    * * * * *
        (b) Post operating license stage. Each applicant for a license 
    amendment authorizing decommissioning activities for a production or 
    utilization facility either for unrestricted use or based on continuing 
    use restrictions applicable to the site; and each applicant for a 
    license amendment approving a license termination plan or 
    decommissioning plan under Sec. 50.82 of this chapter either for 
    unrestricted use or based on continuing use restrictions applicable to 
    the site; and each applicant for a license or license amendment to 
    store spent fuel at a nuclear power reactor after expiration of the 
    operating license for the nuclear power reactor shall submit with its 
    application the number of copies, as specified in Sec. 51.55, of a 
    separate document, entitled ``Supplement to Applicant's Environmental 
    Report--Post Operating License Stage,'' which will update ``Applicant's 
    Environmental Report--Operating License Stage,'' as appropriate, to 
    reflect any new information or significant environmental change 
    associated with the applicant's proposed decommissioning activities or 
    with the applicant's proposed activities with respect to the planned 
    storage of spent fuel. Unless otherwise required by the Commission, in 
    accordance with the generic determination in Sec. 51.23(a) and the 
    provisions in Sec. 51.23(b), the applicant shall only address the 
    environmental impact of spent fuel storage for the term of the license 
    applied for. The ``Supplement to Applicant's Environmental Report--Post 
    Operating License Stage'' may incorporate by reference any information 
    contained in ``Applicant's Environmental Report--Construction Permit 
    Stage,'' ``Supplement to Applicant's Environmental Report--Operating 
    License Stage,'' final environmental impact statement, supplement to 
    final environmental impact statement--operating license stage, or in 
    the records of decision prepared in connection with the construction 
    permit or the operating license for that facility.
    * * * * *
        34. Section 51.95, paragraph (b) is revised to read as follows:
    
    
    Sec. 51.95  Supplement to final environmental impact statement.
    
    * * * * *
        (b) Post operating license stage. In connection with the amendment 
    of an operating license authorizing decommissioning activities at a 
    production or utilization facility covered by Sec. 51.20, either for 
    unrestricted use or based on continuing use restrictions applicable to 
    the site, or with the issuance, amendment or renewal of a license to 
    store spent fuel at a nuclear power reactor after expiration of the 
    operating license for the nuclear power reactor, the NRC staff will 
    prepare a supplemental environmental impact statement for the post 
    operating license stage or an environmental assessment, as appropriate, 
    which will update the prior environmental review. The supplement or 
    assessment may incorporate by reference any information contained in 
    the final environmental impact statement, the supplement to the final 
    environmental impact statement--operating license stage, or in the 
    records of decision prepared in connection with the construction permit 
    or the operating license for that facility. The supplement will include 
    a request for comments as provided in Sec. 51.73. Unless otherwise 
    required by the Commission, in accordance with the generic 
    determination in Sec. 51.23(a) and the provisions of Sec. 51.23(b), a 
    supplemental environmental impact statement for the post operating 
    license stage or an environmental assessment, as appropriate, will 
    address the environmental impacts of spent fuel storage only for the 
    term of the license, license amendment or license renewal applied for.
    
        Dated at Rockville, MD, this 19th day of July, 1996.
    
        For the Nuclear Regulatory Commission.
    John C. Hoyle,
     Secretary of the Commission.
    [FR Doc. 96-19031 Filed 7-26-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Effective Date:
8/28/1996
Published:
07/29/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Rule
Action:
Final rule.
Document Number:
96-19031
Dates:
August 28, 1996.
Pages:
39278-39304 (27 pages)
RINs:
3150-AE96: Decommissioning of Nuclear Power Reactors
RIN Links:
https://www.federalregister.gov/regulations/3150-AE96/decommissioning-of-nuclear-power-reactors
PDF File:
96-19031.pdf
CFR: (55)
10 CFR 50.2''
10 CFR 50.82(a)(7)
10 CFR 50.59(a)(2)
10 CFR 50.82(a)(4))
10 CFR 50.82(a)(8))
More ...