98-20202. Niagara Mohawk Power Corp. Late-Filed Request for Rehearing Rejected  

  • [Federal Register Volume 63, Number 145 (Wednesday, July 29, 1998)]
    [Notices]
    [Page 40519]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-20202]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Project No. 2696-006]
    
    
    Niagara Mohawk Power Corp. Late-Filed Request for Rehearing 
    Rejected
    
    July 23, 1998.
        On May 29, 1998, the Commission issued an order accepting the 
    surrender of a license for the Stuyvesant Falls Hydroelectric Project 
    No. 2696 from Niagara Mohawk Power Corporation.\1\ On July 1, 1998, New 
    York Rivers United filed a request for rehearing of the Commission's 
    order, and of the Final Environmental Assessment (EA) issued in 
    connection with the surrender order.\2\
    ---------------------------------------------------------------------------
    
        \1\ 83 FERC para. 61,226.
        \2\ There is no provision under applicable statutes or 
    regulations for requesting rehearing of a Final EA.
    ---------------------------------------------------------------------------
    
        Section 313(a) of the Federal Power Act requires an aggrieved party 
    to file its request for rehearing within 30 days after issuance of a 
    Commission order.\3\ In this instance, the deadline for filing a 
    request for rehearing was June 29, 1998. Because the rehearing deadline 
    is statutorily based, and New York Rivers United did not file its 
    request within the statutorily prescribed period, its request for 
    rehearing must be rejected. The Final EA was attached to, and issued 
    with, the order. The fact that a Notice of Availability of the Final EA 
    was issued on June 1, 1998, does not extend the statutory deadline for 
    requesting rehearing of the order.
    ---------------------------------------------------------------------------
    
        \3\ 16 U.S.C. 825l.
    ---------------------------------------------------------------------------
    
        This notice constitutes final agency action. Requests for rehearing 
    of this notice may be filed within 30 days of the date of issuance of 
    this notice, pursuant to Rule 713 of the Commission's Rules of Practice 
    and Procedure.\4\
    ---------------------------------------------------------------------------
    
        \4\ 18 CFR 385.713 (1998).
    ---------------------------------------------------------------------------
    
    David P. Boergers,
    Acting Secretary.
    [FR Doc. 98-20202 Filed 7-28-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
07/29/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-20202
Pages:
40519-40519 (1 pages)
Docket Numbers:
Project No. 2696-006
PDF File:
98-20202.pdf