2014-17759. FFP Missouri 12, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests
-
Start Preamble
Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: 13755-002.
c. Date Filed: February 3, 2014.
d. Applicant: FFP Missouri 12, LLC.
e. Name of Project: Allegheny Lock and Dam Number 2.
f. Location: The proposed project would be located at the U.S. Army Corps of Engineers' (Corps) Allegheny Lock and Dam Number 2 on the Allegheny River in Allegheny County, Pennsylvania. The project would occupy 37.5 acres of federal land managed by the Corps.
g. Filed Pursuant to: Federal Power Act, 16 USC 791 (a)-825(r).
h. Applicant Contact: Thomas Feldman, Vice President, Free Flow Power Corporation, 239 Causeway Street, Suite 300, Boston, MA 02114; or at (978) 283-2822.
Ramya Swaminathan, Chief Operating Officer, Free Flow Power Corporation, 239 Causeway Street, Suite 300, Boston, MA 02114; or at (978) 283-2822.
Daniel Lissner, General Counsel, Free Flow Power Corporation, 239 Causeway Street, Suite 300, Boston, MA 02114; or at (978) 283-2822.
i. FERC Contact: Allyson Conner, (202) 502-6082 or allyson.conner@ferc.gov.
j. Deadline for filing motions to intervene and protests and requests for cooperating agency status: 60 days from the date of this notice.
The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P-13755-002.
The Commission's Rules of Practice and Procedures require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.
k. This application has been accepted for filing, but is not ready for environmental analysis at this time.
l. The proposed project would utilize the existing Corps' Allegheny Lock and Dam Number 2, and would consist of the following new facilities: (1) A 170-foot-wide, 120-foot-long, 70-foot-high intake structure with two 5-inch clear bar spacing trash racks; (2) two 45-foot-wide, 40-foot-high spillway bays; (3) an 1,100-foot-long, 2.5-foot-high adjustable crest gate on top of the existing dam crest; (4) a 170-foot-wide by 180-foot-long powerhouse along the east side of the river; (5) three Kaplan turbine-generator units with a combined installed capacity of 17,000 kilowatts; (6) a 50-foot-wide by 60-foot-long substation; (7) a 1,265-foot-long, single overhead, 69-kilovolt transmission line to connect the project substation to an existing distribution line owned by Duquesne Light Company; and (8) appurtenant facilities. The project is Start Printed Page 44020estimated to generate an average of 81,950 megawatt-hours annually.
Free Flow Power proposes to operate the project in a “run-of-river” mode using flows made available by the Corps. The proposed project would not change existing flow releases or water surface elevations upstream or downstream of the proposed project.
m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above.
You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.
n. Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified intervention deadline date, a competing development application, or a notice of intent to file such an application. Submission of a timely notice of intent allows an interested person to file the competing development application no later than 120 days after the specified intervention deadline date. Applications for preliminary permits will not be accepted in response to this notice.
A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit a development application. A notice of intent must be served on the applicant named in this public notice.
Anyone may submit a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline for the particular application.
When the application is ready for environmental analysis, the Commission will issue a public notice requesting comments, recommendations, terms and conditions, or prescriptions.
All filings must (1) bear in all capital letters the title “PROTEST” or “MOTION TO INTERVENE,” “NOTICE OF INTENT TO FILE COMPETING APPLICATION,” or “COMPETING APPLICATION;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the applications directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.
Start SignatureDated: July 18, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-17759 Filed 7-28-14; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 07/29/2014
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 2014-17759
- Pages:
- 44019-44020 (2 pages)
- Docket Numbers:
- Project No. 13755-002
- PDF File: