96-16927. Algonquin Gas Transmission; Notice of Request Under Blanket Authorization
[Federal Register Volume 61, Number 129 (Wednesday, July 3, 1996)]
[Notices]
[Page 34804]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 96-16927]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP96-591-000]
Algonquin Gas Transmission; Notice of Request Under Blanket
Authorization
June 27, 1996.
Take notice that on June 21, 1996, Algonquin Gas Transmission
Company (Algonquin), 1284 Soldiers Field Road, Boston, Massachusetts
02135, filed in Docket No. CP96-591-000 a request pursuant to Sections
157.205 and 157.211 of the Commission's Regulations under the National
Gas Act (18 CFR 157.205 and 157.211) for authorization to construct and
operate a tap valve interconnecting its existing T-system in Milford,
Massachusetts with facilities constructed by Ball-Foster Glass
Container Co., L.L.C. (Ball-Foster), under the blanket certificate
issued in Docket No. CP87-317-000, all as more fully set forth in the
request which is on file with the Commission and open to public
inspection.
Algonquin states that the proposed delivery facilities will consist
of a tap, meter and related data acquisition system facilities which
will be installed by Algonquin within the existing right-of-way.
Algonquin notes that Ball-Foster will construct a regulator station and
miscellaneous piping on land it owns in Milford, which is adjacent to
Algonquin's right-of-way. Algonquin asserts that the proposed addition
of the proposed facilities will have no impact on its system-wide peak
day deliveries because the deliveries to Ball-Foster will be
interruptible, pursuant to Algonquin's Rate Schedule AIT-1. Algonquin
estimates the cost of facilities to be constructed by Algonquin will be
$81.450. Ball-Foster has agreed to reimburse Algonquin for constructing
these facilities. Algonquin notes that Ball-Foster will pay for
facilities it will construct.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 96-16927 Filed 7-2-96; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 07/03/1996
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 96-16927
- Pages:
- 34804-34804 (1 pages)
- Docket Numbers:
- Docket No. CP96-591-000
- PDF File:
-