2019-14132. Letter to the Nuclear Energy Institute Entergy Services, Inc., and NextEra Energy Regarding the Clarification of Regulatory Path for Lead Test Assemblies
-
Start Preamble
AGENCY:
Nuclear Regulatory Commission.
ACTION:
Issuance.
SUMMARY:
The U.S. Nuclear Regulatory Commission (NRC) is issuing a letter to the Nuclear Energy Institute (NEI), Entergy Services, Inc., and NextEra Energy to finalize the NRC staff's views on the regulatory positions regarding lead test assemblies (LTAs) previously discussed in the NRC's letter to NEI dated June 29, 2017.
DATES:
July 3, 2019.
ADDRESSES:
Please refer to Docket ID NRC-2018-0109 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods:
- Federal Rulemaking Website: Go to https://www.regulations.gov/ and search for Docket ID NRC-2018-0109. Address questions about NRC docket IDs in Regulations.gov to Jennifer Borges; telephone: 301-287-9127; email: Jennifer.Borges@nrc.gov. For technical questions, contact the individuals listed in the FOR FURTHER INFORMATION CONTACT section of this document.
- NRC's Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select “Begin Web-based ADAMS Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. For the convenience of the reader, instructions about obtaining materials referenced in this document are provided in the Availability of Documents section.
- NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Kimberly Green, Office of Nuclear Reactor Regulation, telephone: 301-415-1627, email: Kimberly.Green@nrc.gov, or Reed Anzalone, Office of Nuclear Reactor Regulation, telephone: 301-415-2988, email: Reed.Anzalone@nrc.gov. Both are staff of the U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
I. Discussion
The NRC is issuing a letter to NEI, Entergy Services, Inc., and NextEra Energy to clarify the NRC staff's interpretation of Standard Technical Specification (STS) 4.2.1, “Fuel Assemblies.” The first part of STS 4.2.1 places limitations on the number of fuel assemblies in the reactor core, the type of fuel that can be used, the cladding material that can be used (e.g., zircaloy or ZIRLO), and requires the use of NRC-approved codes and methods for the fuel assemblies. The last sentence of Start Printed Page 31927STS 4.2.1 allows for the irradiation of a limited number of LTAs that have not completed representative testing if placed in nonlimiting regions of the reactor core.
In the past, licensees have taken different approaches when conducting LTA campaigns. Some licensees obtained prior NRC approval by license amendments approving changes to Technical Specification (TS) 4.2.1 or exemptions from § 50.46, “Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors,” of title 10 of the Code of Federal Regulations (10 CFR), or both, for their LTA campaigns. Other licensees conducted LTA campaigns under 10 CFR 50.59, “Changes, tests, and experiments,” without prior NRC approval.
This letter clarifies the NRC staff's views on the regulatory positions regarding LTAs previously discussed in the NRC's letter to NEI dated June 29, 2017. The letter provides: Clarification on the LTA provision in STS 4.2.1; clarification on the use of approved methods for LTA campaigns; a regulatory path for LTA campaigns; guidance on the use of NEI 96-07, Revision 1, “Guidelines for 10 CFR 50.59 Implementation,” regarding LTAs; and guidance on exemptions from the requirements in 10 CFR 50.46 for LTAs.
II. Opportunity for Public Participation
The NRC published a notice of the availability of a draft letter to NEI regarding the clarification of regulatory paths for lead test assemblies in the Federal Register on June 7, 2018 (83 FR 26503) for a 20-day public comment period. The public comment period closed on June 27, 2018. After consideration of comments requesting additional time to comment on the draft letter, the NRC reopened the public comment period for an additional 20 days on July 2, 2018. The additional comment period closed on July 23, 2018.
The NRC received 272 comment submissions on the draft guidance letter consisting of approximately 900 comments. Public comments on the draft letter and the staff responses to the public comments are available electronically in ADAMS under Accession No. ML19126A101 (the comment response document). A compilation of all comment submissions with annotated comments is also available.
Table 1, “Commenters on Guidance Letter,” in the comment response document contains a listing of persons or entities that provided comments. The name of the individual and affiliation, if provided, a unique identifier for the commenter, and the ADAMS accession number are listed. Some individuals are listed more than once because they provided more than one comment letter.
Each comment letter was segmented into individual comments, and each comment was then categorized by topic. The topics are provided in Table 2 of the comment response document. The comments are summarized and are followed by a response. If the NRC staff determined that a change to the letter was warranted, because of the comment, it is indicated in the response.
III. Congressional Review Act
This guidance letter is a rule as defined in the Congressional Review Act (5 U.S.C. 801-808). However, the Office of Management and Budget has not found it to be a major rule as defined in the Congressional Review Act.
IV. Backfitting and Issue Finality
The letter provides additional clarification on previous staff preliminary statements and positions regarding the use of LTAs made in a letter to NEI dated June 29, 2017. Issuance of the letter does not constitute backfitting as defined in 10 CFR 50.109 (the Backfit Rule) and is not otherwise inconsistent with the issue finality provisions in 10 CFR part 52. The NRC has no current intention to impose the positions described in the letter on holders of current operating licenses or combined licenses.
V. Availability of Documents
The documents identified in the following table are available to interested persons through one or more of the methods previously indicated.
Start SignatureDocument ADAMS Accession No. Letter from U.S. Nuclear Regulatory Commission to Nuclear Energy Institute, Entergy Services, Inc., and NextEra Energy, Subject: Clarification of Regulatory Path for Lead Test Assemblies, dated June 24, 2019 ML18323A169 Letter from Mirela Gavrilas, U.S. NRC, to Mr. Andrew Mauer, Nuclear Energy Institute. Subject: Response to Nuclear Energy Institute Letter Concerning the Regulatory Path for Lead Test Assemblies. June 29, 2017 ML17150A443 NUREG-1430, Standard Technical Specifications—Babcock and Wilcox Plants, Volume 1, Revision 4 ML12100A177 NUREG-1431, Standard Technical Specifications—Westinghouse Plants, Volume 1, Revision 4 ML12100A222 NUREG-1432, Standard Technical Specifications—Combustion Engineering Plants, Volume 1, Revision 4 ML12102A165 NUREG-1433, Standard Technical Specifications—General Electric Plants (BWR/4), Volume 1, Revision 4 ML12104A192 NUREG-1434, Standard Technical Specifications—General Electric Plants (BWR/6), Volume 1, Revision 4 ML12104A195 NEI 96-07, Revision 1, Guidelines for 10 CFR 50.59 Implementation ML003771157 Draft letter from U.S. Nuclear Regulatory Commission to Nuclear Energy Institute. Subject: Clarification of Regulatory Paths for Lead Test Assemblies, dated May 31, 2018 ML18100A045 Public comments on the draft letter and the staff responses to the public comments ML19126A101 Compilation of comment submissions with annotated comments ML19141A222 Dated at Rockville, Maryland, this 27th day of June, 2019.
For the Nuclear Regulatory Commission.
Craig G. Erlanger,
Director, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2019-14132 Filed 7-2-19; 8:45 am]
BILLING CODE 7590-01-P
Document Information
- Published:
- 07/03/2019
- Department:
- Nuclear Regulatory Commission
- Entry Type:
- Notice
- Action:
- Issuance.
- Document Number:
- 2019-14132
- Dates:
- July 3, 2019.
- Pages:
- 31926-31927 (2 pages)
- Docket Numbers:
- NRC-2018-0109
- PDF File:
- 2019-14132.pdf