[Federal Register Volume 60, Number 128 (Wednesday, July 5, 1995)]
[Rules and Regulations]
[Pages 34846-34851]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-16403]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
23 CFR Part 645
[FHWA Docket No. 94-8]
RIN 2125-AD31
Utilities
AGENCY: Federal Highway Administration (FHWA), DOT.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The FHWA is amending its regulations on utilities. These
amendments eliminate the requirement for FHWA preaward review and/or
approval of consultant contracts for preliminary engineering and
increase the ceiling for lump sum agreements from $25,000 to $100,000.
They clarify the meaning of the term ``approved program'' and the
methodology to be used to compute indirect or overhead rates. They
require utilities to submit final billings within one year following
completion of the utility relocation work. They eliminate the
requirements for State highway agencies (SHAs) to certify the
completion of utility work and to provide evidence of payment prior to
reimbursement. They bring the definition of ``clear zone'' into
conformance with the American Association of State Highway and
Transportation Officials (AASHTO) ``Roadside Design Guide.'' Finally,
they incorporate an amendment conforming the utilities regulations to
the Intermodal Surface Transportation Efficiency Act of 1991 (ISTEA),
Pub. L. 102-240, 105 Stat. 1914. The FHWA is making these changes to
conform the utilities regulations to more recent laws, regulations, and
guidance; to clarify these regulations; and to give the SHAs more
flexibility in implementing them.
EFFECTIVE DATE: This final rule is effective August 4, 1995.
FOR FURTHER INFORMATION CONTACT: Mr. Jerry L. Poston, Office of
Engineering, 202-366-0450, or Mr. Wilbert Baccus, Office of the Chief
Counsel, 202-366-0780, 400 Seventh Street, SW., Washington, D.C. 20590.
SUPPLEMENTARY INFORMATION:
Background
The amendments in this final rule are based primarily on the notice
of
[[Page 34847]]
proposed rulemaking (NPRM) published in the May 17, 1994, Federal
Register at 59 FR 25579 (FHWA Docket No. 94-8). All comments received
in response to this NPRM have been considered in adopting these
amendments.
Current FHWA regulations regarding utility relocation and
accommodation matters have evolved from basic principles established
decades ago, with many of the policies remaining unchanged. The current
regulations are found in title 23, Code of Federal Regulations, part
645 (23 CFR part 645). Subpart A of this part pertains to utility
relocations, adjustments, and reimbursement. Subpart B pertains to the
accommodation of utilities. Part 645 was revised on May 15, 1985, when
a final rule was published in the Federal Register at 50 FR 20344. Two
significant changes have occurred since then, on February 2 and July 1,
1988, when amendments to the regulation were published in the Federal
Register at 53 FR 2829 and 53 FR 24932. The February 2 amendment
provided that each SHA must decide, as part of its utility relocation
plan, whether to allow longitudinal utility installations within the
access control limits of freeways and, if allowed, under what
circumstances. The July 1 amendment clarified that costs incurred by
highway agencies in implementing projects solely for safety corrective
measures to reduce the hazards of utilities to highway users are
eligible for Federal-aid participation.
This final rule amends these regulations in the following manner
and for the reasons indicated below.
In Sec. 645.109, paragraph (b) is amended to eliminate the
requirement for FHWA preaward review and/or approval of consultant
contracts for preliminary engineering and related work. The amendment
increases the number of consultant contracts that can be advanced
without prior FHWA approval and provides for consistency in the
administration of consultant agreements.
In Sec. 645.113, paragraph (f) is amended to increase the ceiling
for lump sum agreements from $25,000 to $100,000. This provides the
SHAs greater flexibility in utilizing the lump sum payment arrangement.
The purpose of allowing lump sum agreements in lieu of agreements based
on an accounting of actual costs is to reduce the administrative burden
associated with utility relocation projects. Under the lump sum
process, cost accounting is easier, project billings are simplified,
and a final audit of detailed cost records is not required. Final
project costs are typically quite close to the costs estimated for
small, routine projects. The FHWA believes that the small degree of
accuracy that might be realized if more detailed cost accounting
methods were followed does not justify the extra cost involved in
carrying out detailed audits. This revision increases the number of
utility relocations potentially eligible for lump sum payment,
anticipates future needs, and responds, in part, to the fact that since
the $25,000 limit was established in 1983, inflation has reduced the
number and limited the scope of projects eligible for lump sum
payments.
In Sec. 645.113, paragraph (g)(1) is amended to change the term
``approved program'' to ``Statewide transportation improvement
program.'' Title 23, United States Code, section 135 (23 U.S.C. 135)
requires a Statewide transportation improvement program to include all
projects in the State which are proposed for Federal-aid highway
funding. This program replaces the ``approved program'' previously
required in 23 U.S.C. 105. This amendment conforms the utilities
regulation to section 135 by specifying that utility relocation work
must be included in an ``approved Statewide transportation improvement
program.''
In Sec. 645.117, paragraph (d)(1) is amended to clarify the
methodology to be used for computing indirect overhead rates. The
definition of indirect costs, and what may or may not be included, is
set forth in 48 CFR part 31, Contract Cost Principles and Procedures.
Part 31 is referenced in 49 CFR part 18, the common rule for Federal
grants, cooperative agreements, and subawards to State, local, and
Indian tribal governments. However, to avoid any misunderstandings and
to assure consistency with the common rule, a reference to 48 CFR 31 is
added to the utilities regulations.
In Sec. 645.117, paragraph (i)(2) is revised to require utilities
to submit final billings within one year following completion of the
work, otherwise previous payments to utilities may be considered final
and projects may be closed out, except as agreed to between the SHA and
the utility. This change will assist highway agencies in their efforts
to obtain timely final billings from the utilities. Some utility bills
are received years after the work is completed, thus delaying audit
activity and project closure. Billings received from utilities more
than one year following completion of the utility relocation work may
be paid if the SHA so desires, and Federal funds may participate in
these payments.
In Sec. 645.117, paragraph (i)(2) is further revised to eliminate
the requirement that the SHA certify that utility work is complete,
acceptable, and in accordance with the terms of the agreement. These
certifications are no longer considered necessary because all third
party agreements and non-construction contracts are reviewed by the
FHWA on a program basis. This revision will reduce paperwork and
expedite the submittal of final billings from the utilities.
In Sec. 645.117, paragraph (i)(4) is removed. This paragraph
prohibited Federal reimbursement for a final utility billing until the
highway agency furnished evidence that it had paid the utility with its
own funds. This regulation is contrary to the general FHWA practice
whereby the FHWA reimburses the SHAs for costs incurred, not for actual
payments made.
Section 645.207 is amended to change the term ``clear recovery
area'' to ``clear zone,'' to revise the definition of ``clear zone'' to
conform to the one contained in AASHTO's ``Roadside Design Guide,''\1\
and to add a definition of the term ``border area'' which is contained
in the definition of ``clear zone.'' In Sec. 645.209, paragraph (a) is
amended to clarify the FHWA's continuing intent to accommodate
utilities within highway rights-of-way when sufficient clear zone is
not available, and paragraph (b) is amended to change the term ``clear
recovery area'' to ``clear zone.'' These changes provide consistency
with AASHTO's ``Roadside Design Guide,'' a 1989 document which should
be used as a guide for establishing clear zones for various types of
highways and operating conditions. The term ``clear recovery area''
originated in 1985 and, though worded somewhat differently, meant
essentially the same as the term ``clear zone.'' These terms were often
used interchangeably. The ``Roadside Design Guide,'' however, uses the
term ``clear zone'' exclusively. Hence, to avoid confusion, the term
``clear zone'' is incorporated into the utilities regulations.
\1\The ``Roadside Design Guide'' is incorporated by reference at
23 CFR 625.5(a)(3). It is available for purchase from the American
Association of State Highway and Transportation Officials, 444 North
Capitol Street, NW., Washington, DC 20001. Also, it is available for
inspection as provided in 49 CFR part 7, appendix D.
---------------------------------------------------------------------------
In Sec. 645.215, paragraph (a) is amended to change the term
``Federal-aid system'' to ``Federal-aid highway.'' This revision is in
accordance with a conforming amendment in section 1016(f)(1)(B) of the
ISTEA changing the term ``Federal-aid system'' in 23 U.S.C. 109(l) to
``Federal-aid highway.''
[[Page 34848]]
Discussion of Comments
Interested persons were invited to participate in the development
of this final rule by submitting written comments on the NPRM to Docket
94-8 on or before July 18, 1994. Comments were received from 10 SHAs
and 6 utilities representatives. A summary of the comments received
relative to each proposed amendment follows.
In Sec. 645.109, paragraph (b) is amended to eliminate the
requirement for FHWA preaward review and/or approval of consultant
contracts for preliminary engineering. Four SHAs and 5 utilities
commenters were in favor of the amendment proposed in the NPRM to
increase the upper limit on the value of such contracts from $10,000 to
$25,000. One SHA recommended that the upper limit be increased even
more.
In Sec. 645.113, paragraph (f) is amended to increase the ceiling
for lump sum agreements from $25,000 to $100,000. Four SHAs were in
favor of this proposed amendment; 5 utilities commenters recommended
that the upper limit be increased even more.
In Sec. 645.117, paragraph (d)(1) is amended to clarify the
methodology to be used to compute indirect or overhead rates. Four SHAs
and 5 utilities commenters were in favor of this proposed amendment.
In Sec. 645.117, paragraph (i)(2) is amended to require utilities
to submit final billings within one year following completion of work.
Four SHAs were in favor of the amendment proposed in the NPRM to
establish a 180-day final billing deadline. Three SHAs and 6 utilities
commenters recommended that the final billing deadline be established
for a period of time longer than 180 calendar days proposed in the NPRM
and suggested several other time periods.
In Secs. 645.207 and 645.209, the definition of ``clear zone'' is
revised to parallel the definition of this term in AASHTO's ``Roadside
Design Guide.'' Four SHAs were in favor of this proposed amendment; 1
SHA recommended that the Texas Transportation Institute's (TTI) ``A
Supplement to a Guide for Selecting, Designing, and Locating Traffic
Barriers'' be included with the AASHTO ``Roadside Design Guide'' as a
good technical reference; 5 utilities commenters recommended that the
clear zone definition specify that the clear zone ends at the right-of-
way line.
Section 645.215 incorporates a conforming amendment contained in
section 1016(f)(1)(B) of the ISTEA that changes the term ``Federal-aid
systems'' to ``Federal-aid highways.'' Four SHAs were in favor of this
proposed amendment.
A discussion of the specific comments received and the FHWA
responses to them follows.
Comment 1
One SHA recommended that Sec. 645.109(b) be modified to increase
the upper limit on the value of consultant contracts for preliminary
engineering for which the FHWA may forgo preaward review and/or
approval from $10,000 to $100,000, rather than simply increasing it to
$25,000 as the FHWA had proposed.
Response
The FHWA has decided to totally eliminate the requirement for FHWA
preaward review and/or approval of consultant contracts for preliminary
engineering, consistent with the administration of other consultant
agreements. The determination to allow a utility to use a consultant
for preliminary engineering should be made by the SHA, not the FHWA,
when the utility agreement is executed. This change will be
accomplished by eliminating the last sentence of Sec. 645.109(b).
Comment 2
Five utilities commenters recommended that Sec. 645.113(f) be
modified to increase the ceiling for lump sum agreements from $25,000
to $200,000. They asserted that this was desirable because the
administrative cost of tracking ``actual cost'' projects adds
significantly to the cost of the undertaking for both the utility and
the SHAs that must approve the billing.
Response
This recommendation was not adopted. The increase from $25,000 to
$100,000 will increase the number of utility relocations potentially
eligible for lump sum payments and reduce the administrative burden
associated with utility relocation projects. An increase even higher
than $100,000, such as to the recommended $200,000, may have been
possible. However, it is desired at this time to retain the $100,000
figure because it seems to represent a good break point between major
and minor work and because it corresponds more closely to increasing
inflation rates which have over the years reduced the number and
limited the scope of projects eligible for lump sum payments.
Provisions for lump sum payments for utility relocation work were first
addressed by the FHWA in Policy and Procedure Memorandum 30-4 (PPM 30-
4)\2\ dated December 31, 1957. These provisions pertained to very minor
work estimated to cost less than $2,500, work that normally would be
performed by a utility with its own forces. Increases up to the present
$25,000 limit, which was established in 1983, were based primarily upon
inflation rates. Projecting inflation from 1983 to 1995 provides a
figure which is slightly less than $100,000, but the $100,000 figure is
used several other places in the Federal regulations as a break point
between major and minor work. Even so, the FHWA will monitor the
effects of increasing the lump sum ceiling to $100,000, primarily
through discussions with States and utilities' coordinators, and will
consider the possibility of increasing the figure in the near future if
such is deemed appropriate.
\2\The Federal Highway Administration's Policy and Procedure
Memorandums are available for inspection and copying from the FHWA
headquarters and field offices as prescribed at 49 CFR part 7,
appendix D.
---------------------------------------------------------------------------
Comment 3
Three SHAs and 6 utilities commenters had reservations about the
proposed amendment to Sec. 645.117(i)(2) to require utilities to submit
final billings within 180 calendar days following completion of work.
They all basically supported the concept of establishing a deadline for
submitting final billings, but strongly indicated that 180 calendar
days were not enough. The utilities commenters recommended that at
least 270 calendar days be provided. Two SHAs recommended 365 calendar
days. The utilities commenters asserted that (a) a 180 calendar day
requirement would be burdensome to utilities, especially those that are
joint pole users, because of cross billing from other parties, and (b)
it is often very difficult to secure final bills simply because of the
number of parties involved and the time required to verify and
reconcile the accuracy of the billing. One SHA stated that the 180
calendar day limit would not provide the utilities sufficient time to
compile changes and submit their final bills, and that, historically,
80 percent of utility billings are received between 180 and 365
calendar days after completion of the utility relocation work. Another
SHA indicated that the 180 calendar day limit would put an unreasonable
burden on the State since its regulations did not contain a time limit.
Response
These recommendations were adopted with a slight, but more
flexible, modification. The comments revealed a
[[Page 34849]]
general consensus that it would be desirable to establish a time period
following completion of the utility relocation work during which final
billings must be submitted, but that 180 calendar days were not enough.
Hence, Sec. 645.117(i)(2) is amended to require utilities to submit
final billings within one year following completion of the utility
relocation work, otherwise previous payments to the utility may be
considered final, except as agreed to between the SHA and the utility.
Comment 4
One SHA requested clarification of the term ``completion of work''
as it is used in the proposed amendment to Sec. 645.117(i)(2). For
example, the commenter asked whether the work would be completed when
finished in the field by the utility or its contractor, when the
highway project was finished, or at some other milestone.
Response
The intent of the proposed amendment was to require utilities to
submit final billings within a certain time period following physical
completion of the utility relocation work in the field. Hence,
Sec. 645.117(i)(2) is amended to require utilities to submit final
billings within one year following completion of the utility relocation
work.
Comment 5
One SHA suggested that the proposed amendment to require utilities
to submit final billings within 180 calendar days following completion
of work be modified to allow for time extensions beyond the 180
calendar day limit if the SHA should so choose. The SHA argued that
this modification was needed to alleviate conflicts with a State law
permitting claims against the State to be submitted within one year
from the time of accrual.
Response
This recommendation was adopted. As stated in the NPRM, the FHWA
intended to allow billings received after the specified time period to
be paid at the discretion of the highway agency. Hence,
Sec. 645.117(i)(2) is amended to require utilities to submit final
billings within one year following completion of the utility relocation
work, with exceptions as agreed to between the SHA and the utility.
Comment 6
Five utilities commenters recommended that the definition of
``clear zone'' in the proposed amendment to Sec. 645.207 be modified to
clearly indicate that the clear zone ends at the right-of-way line.
Response
This suggested amendment was not made to the ``clear zone''
definition, but was incorporated elsewhere in the regulations. The
purpose for amending Sec. 645.207 was to provide consistency with
AASHTO's ``Roadside Design Guide.'' To do so, the term ``clear recovery
area'' was changed to ``clear zone'' and the definition of ``clear
zone'' in the ``Roadside Design Guide'' was adopted. However, to
clarify the intent of the revised regulation, a definition of ``border
area'' was added. This, taken together with the definition of ``clear
zone,'' means that the area that actually can be made available for the
safe use of errant vehicles is limited by the right-of-way width. For
all practical purposes, the old definition of ``clear recovery area''
is the same as the actual clear zone. In cases where sufficient right-
of-way is not available to accommodate the minimum clear zone distance
required, highway agencies should consider acquiring additional right-
of-way, taking into account not only clear zone but other highway and
utility needs. In all cases, full consideration should be given to
sound engineering principles and economic factors. Utility facilities
should be treated the same as other roadside hazards. Little will be
gained by moving utilities, unless their presence in the clear zone
presents a significantly greater hazard to motorists than any other
hazards.
Comment 7
One SHA suggested that TTI's ``A Supplement to a Guide for
Selecting, Designing, and Locating Traffic Barriers'' be included with
the AASHTO ``Roadside Design Guide'' as a good technical reference in
the proposed amendment to Sec. 645.207.
Response
This suggestion was not adopted. AASHTO's ``Roadside Design
Guide,'' 1989, superseded AASHTO's ``Guide for Selecting, Designing,
and Locating Traffic Barriers,'' 1977, and the TTI supplement which
came into use in the early 1980's, even though much of the guidance in
the new document was the same as in the superseded documents. One
significant difference between the ``Roadside Design Guide'' and the
two earlier documents is the determination of minimum clear zones on
slopes. Current AASHTO guidelines consider embankment slopes between
3:1 and 4:1 to be non-recoverable (i.e., any vehicle leaving the
roadway will likely go to the bottom of the slope). Consequently, the
clear zone should not end on the slope itself, and a clear run-out area
beyond the toe of such a slope is desirable. This was not considered in
the 1977 barrier guide or the TTI supplement, so the information in
these documents is no longer accurate for non-recoverable slopes. Any
SHA may modify the earlier guidance and continue to use it to determine
minimum clear zones on existing facilities. However, the FHWA believes
a more practical approach is for each highway agency to develop and
implement a policy on utility pole locations that encourages maximum
offsets consistent with existing conditions and based on a cost-
effectiveness analysis.
Comment 8
One SHA expressed a concern about non-regulatory guidance in the
FHWA's ``Federal-Aid Policy Guide''\3\ dealing with the use of fixed
amount (lump sum) payments to utilities. The wording in the non-
regulatory supplement to part 645 (NS 23 CFR 645A, Attachment), case I,
paragraph 2, indicates that the lump sum payments may be made for work
performed by a utility with its own forces. It was requested that the
FHWA guidance in the non-regulatory supplement be revised to allow lump
sum payments to be made for work performed for a utility under a
utility-let or continuing contract.
\3\The Federal Highway Administration's ``Federal-Aid Policy
Guide'' is available for inspection and copying from the FHWA
headquarters and field offices as prescribed at 49 CFR part 7,
appendix D.
---------------------------------------------------------------------------
Response
Provisions for lump sum payments for utility relocation work were
first addressed by the FHWA in PPM 30-4 dated December 31, 1957. These
provisions pertained to very minor work estimated to cost less than
$2,500, work that normally would be performed by a utility with its own
forces. There was no apparent intent, however, in PPM 30-4 or any
subsequent FHWA guidance or regulation, to preclude lump sum payments
for work performed by a contractor under a utility-let contract. If the
utility uses an existing continuing contractor, payment should be made
by the method the utility has previously established with the
contractor. If the continuing contract establishes a lump sum payment
for certain types of work, this payment method can be used for the
Federal-aid project if the SHA believes the cost is reasonable. If the
utility lets a contract, payment should be based on the methods that
are customary and acceptable for the work
[[Page 34850]]
involved, which could potentially include the lump sum payment method.
In light of these comments, the FHWA is revising its regulations to
incorporate the amendments outlined in the NPRM with some modifications
to clarify the proposals and to address concerns raised by commenters.
Executive Order 12866 (Regulatory Planning and Review) and DOT
Regulatory Policies and Procedures
The FHWA has determined that this action is not a significant
regulatory action within the meaning of Executive Order 12866 or
significant within the meaning of Department of Transportation
regulatory policies and procedures. The amendments would simply make
minor changes to update the utilities regulations to conform to recent
laws, regulations, and guidance and to clarify existing policies. It is
anticipated that the economic impact of this rulemaking will be minimal
because the amendments would only clarify or simplify procedures
presently being used by SHAs and utilities. Therefore, a full
regulatory evaluation is not required.
Regulatory Flexibility Act
In compliance with the Regulatory Flexibility Act (5 U.S.C. 601-
612), the FHWA has evaluated the effects of this rule on small
entities. Based on the evaluation, the FHWA certifies that this action
will not have a significant economic impact on a substantial number of
small entities. This is because the amendments would only clarify or
simplify procedures used by SHAs and utilities in accordance with
existing laws, regulations, and guidance.
Executive Order 12612 (Federalism Assessment)
This action has been analyzed in accordance with the principles and
criteria contained in Executive Order 12612, and it has been determined
that it does not have sufficient federalism implications to warrant the
preparation of a separate federalism assessment. This action merely
conforms the utilities regulations to recent laws, regulations, and
guidance; clarifies these regulations; and gives the SHAs more
flexibility in implementing them.
Executive Order 12372 (Intergovernmental Review)
Catalog of Federal Domestic Assistance Program Number 20.205,
Highway Planning and Construction. The regulations implementing
Executive Order 12372 regarding intergovernmental consultation on
Federal programs and activities apply to this program.
Paperwork Reduction Act
This action does not contain a collection of information
requirement for purposes of the Paperwork Reduction Act of 1980, 44
U.S.C. 3501-3520.
National Environmental Policy Act
The agency has analyzed this action for the purpose of the National
Environmental Policy Act of 1969 (42 U.S.C. 4321 et. seq.) and has
determined that this action would not have any effect on the quality of
the environment.
Regulation Identification Number
A regulation identification number (RIN) is assigned to each
regulatory action listed in the Unified Agenda of Federal Regulations.
The Regulatory Information Service Center publishes the Unified Agenda
in April and October of each year. The RIN contained in the heading of
this document can be used to cross reference this action with the
Unified Agenda.
List of Subjects in 23 CFR Part 645
Grant Programs--transportation, Highways and roads, Utilities--
relocations, adjustment, reimbursement.
In consideration of the foregoing, title 23, Code of Federal
Regulations, part 645 is amended as set forth below.
Issued on: June 22, 1995.
Rodney E. Slater,
Federal Highway Administrator.
PART 645--UTILITIES
1. The authority citation for part 645 continues to read as
follows:
Authority: 23 U.S.C. 101, 109, 111, 116, 123, and 315; 23 CFR
1.23 and 1.27; 49 CFR 1.48(b); and E.O. 11990, 42 FR 26961 (May 24,
1977).
Sec. 645.109 [Amended]
2. In Sec. 645.109, paragraph (b) is amended by removing the last
sentence.
Sec. 645.113 [Amended]
3. In Sec. 645.113, paragraph (f) is amended by removing the figure
``$25,000'' wherever it appears and adding in its place the figure
``$100,000'', and paragraph (g)(1) is amended by revising the term
``approved program'' to read ``approved Statewide transportation
improvement program''.
4. In Sec. 645.117, paragraph (i)(4) is removed, and paragraphs
(d)(1) and (i)(2) are revised to read as follows:
Sec. 645.117 Cost development and reimbursement.
* * * * *
(d) Overhead and indirect construction costs. (1) Overhead and
indirect construction costs not charged directly to work order or
construction accounts may be allocated to the relocation provided the
allocation is made on an equitable basis. All costs included in the
allocation shall be eligible for Federal reimbursement, reasonable,
actually incurred by the utility, and consistent with the provisions of
48 CFR part 31.
* * * * *
(i) Billings. (1) * * *
(2) The utility shall provide one final and complete billing of all
costs incurred, or of the agreed-to lump-sum, within one year following
completion of the utility relocation work, otherwise previous payments
to the utility may be considered final, except as agreed to between the
SHA and the utility.
* * * * *
5. Section 645.207 is amended by removing the paragraph
designations from all definitions; by placing the definitions in
alphabetical order; by removing the definition of ``clear recovery
area''; by removing the words ``clear recovery area'' from the first
sentence in the definition for ``clear roadside policy'' and adding in
their place the words ``clear zone''; and by adding the definitions of
``border area'' and ``clear zone'' as follows:
Sec. 645.207 Definitions.
* * * * *
Border area--the area between the traveled way and the right-of-way
line.
* * * * *
Clear zone--the total roadside border area starting at the edge of
the traveled way, available for safe use by errant vehicles. This area
may consist of a shoulder, a recoverable slope, a non-recoverable
slope, and/or the area at the toe of a non-recoverable slope available
for safe use by an errant vehicle. The desired width is dependent upon
the traffic volumes and speeds, and on the roadside geometry. The
AASHTO ``Roadside Design Guide,'' 1989, should be used as a guide for
establishing clear zones for various types of highways and operating
conditions. It is available for inspection from the FHWA Washington
Headquarters and all FHWA Division and Regional Offices as prescribed
in 49 CFR part 7, appendix D. Copies of current AASHTO publications are
available for purchase from the American Association of State Highway
and Transportation Officials, Suite 225,
[[Page 34851]]
444 North Capitol Street, NW., Washington, DC. 20001.
* * * * *
6. In Sec. 645.209, paragraph (a) is amended by adding a new
sentence between the existing third and fourth sentences to read as set
forth below, and paragraph (b) is amended by removing the words ``clear
recovery'' in the second sentence and ``clear recovery area'' in the
third sentence and adding in their place the words ``clear zone''.
Sec. 645.209 General requirements.
(a) Safety. * * * The lack of sufficient right-of-way width to
accommodate utilities outside the desirable clear zone, in and of
itself, is not a valid reason to preclude utilities from occupying the
highway right-of-way. * * *
Sec. 645.215 [Amended]
7. In Sec. 645.215, paragraph (a), the fifth sentence, is amended
by removing the words ``of the Federal-aid highway system'' and adding
in their place the words ``of Federal-aid highways''.
[FR Doc. 95-16403 Filed 7-3-95; 8:45 am]
BILLING CODE 4910-22-P