    Environmental Impact Statement: Currituck County, NC
    
    AGENCY: Federal Highway Administration (FHWA), DOT.
    
    ACTION: Notice of Intent.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Federal Highway Administration is issuing this notice to 
    advise the public that an environmental impact statement will be 
    prepared for a Mid-Currituck Sound bridge in Currituck County, North 
    Carolina.
    
    FOR FURTHER INFORMATION CONTACT:
    Roy C. Shelton, Operations Engineer, 310 New Bern Avenue, Suite 410, 
    Raleigh, North Carolina 27601, Telephone: (919) 856-4350.
    
    SUPPLEMENTARY INFORMATION: The FHWA, in cooperation with the North 
    Carolina Department of Transportation (NCDOT), will prepare an 
    environmental impact statement (EIS) on a proposal to build a bridge 
    and approach roadway connecting US 158 on the mainland to NC 12 on the 
    Outer Banks, crossing Currituck Sound. The proposed project would 
    include approximately 3.7 kilometers (2.3 miles) of approach road on 
    the mainland and a bridge across the sound of approximately 7.6 
    kilometers (4.7 miles).
        The proposed project is considered necessary to relieve forecast 
    congestion on US 158 and NC 12, to improve access to public services 
    for Outer Bank residents and to improve future emergency evaluation 
    times. Alternatives under consideration include (1) taking no action 
    and (2) building a bridge in one of six corridors made up of differing 
    combinations of three mainland approach corridors and two Outer Bank 
    termini.
        The alternatives to be evaluated in the EIS were chosen based on 
    the results of an alternatives study conducted in 1994 and 1995. Nine 
    bridge alternatives and several no-bridge alternatives were studied. 
    The no-bridge alternatives were: improve existing roads, improving 
    public services on the Outer Banks, altering storm evacuation plans and 
    a ferry alternative. The reasonableness of widening existing roads in 
    lieu of building the bridge will be examined further. Improving public 
    services on the Outer Banks and altering storm evacuation plans are 
    options Currituck County could implement if the no action alternative 
    was found to be unreasonable.
        In April 1994, a letter describing the proposed action and 
    soliciting comments was sent to appropriate federal, state and local 
    agencies. An interagency scoping meeting was held on May 26, 1994 to 
    introduce the project to federal and state regulatory agencies. Key 
    environmental issues raised during the meeting were (1) the potential 
    for secondary and cumulative impacts, particularly in terms of the 
    potential for the bridge to alter existing development trends in 
    Currituck County, (2) the need to evaluate no bridge alternatives, (3) 
    disturbance of existing communities on the mainland by the approach 
    road and its associated traffic and (4) the sensitivity and importance 
    of Currituck Sound, Maple Swamp and the Outer Banks as natural 
    resources.
        During the alternative study, two sets of citizen informational 
    workshops (August 1994 and April 1995) and one additional interagency 
    meeting (November 1994) were held. Prior to selection of the 
    alternatives to be 
    
    [[Page 35256]]
    evaluated in the EIS, the results of the alternatives study were 
    discussed at the second workshop and second interagency meeting.
        To ensure that the full range of issues related to this proposed 
    action are addressed and all significant issues identified, comments 
    and suggestions are invited from all interested parties. Comments or 
    questions concerning this proposed action and the EIS should be 
    directed to the FHWA at the address provided above.
    
    (Catalog of Federal Domestic Assistance Program Number 20.205, 
    Highway Planning and Construction. The regulations implementing 
    Executive Order 12372 regarding intergovernmental consultation on 
    federal programs and activities apply to this program.)
    
        Issued on: June 27, 1995.
    Roy C. Shelton,
    Operations Engineer, Raleigh, North Carolina.
    [FR Doc. 95-16486 Filed 7-5-95; 8:45 am]
    BILLING CODE 4910-22-M
    
    

Document Information

Published:
07/06/1995
Department:
Federal Highway Administration
Entry Type:
Notice
Action:
Notice of Intent.
Document Number:
95-16486
Pages:
35255-35256 (2 pages)
PDF File:
95-16486.pdf