95-16500. Northwest Pipeline Corporation; Request Under Blanket Authorization  

  • [Federal Register Volume 60, Number 129 (Thursday, July 6, 1995)]
    [Notices]
    [Pages 35198-35199]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-16500]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP95-579-000]
    
    
    Northwest Pipeline Corporation; Request Under Blanket 
    Authorization
    
    June 29, 1995.
        Take notice that on June 23, 1995, Northwest Pipeline Corporation 
    (Northwest), 295 Chipeta Way, Salt Lake City, Utah 84158, filed in 
    Docket No. CP95-579-000 a request pursuant to Sections 157.205, 157.216 
    and 157.211 of the Commission's Regulations under the Natural Gas Act 
    (18 CFR 157.205, 157.216, 157.211) for authorization to abandon certain 
    facilities and to construct and operate upgraded replacement 
    facilities, under Northwest's blanket certificate issued in Docket No. 
    CP82-433-000 pursuant to Section 7 of the Natural Gas Act, all as more 
    fully set forth in the request that is on file with the Commission and 
    open to public inspection.
        Northwest promises to increase the capacity of its existing Soda 
    Springs Meter Station, located in Caribou County, Idaho to accommodate 
    a request by Intermountain Gas Company (Intermountain) for additional 
    service at this point. Northwest states that it would remove and retire 
    four 2-inch regular, port regulators and install four new 2-inch large, 
    port regulators to increase the maximum design delivery capacity from 
    10,070 Dth of gas per day to 12,517 Dth of gas per day. Northwest 
    mentions that no reallocation of existing firm, maximum daily delivery 
    obligations have been requested.
        Northwest states that the total cost of the proposed facility 
    upgrade would be approximately $12,572 which includes $300 for removal 
    of the old regulators. Northwest avers that Intermountain has agreed to 
    reimburse Northwest for these costs pursuant to provisions in 
    Northwest's tariff.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    
    [[Page 35199]]
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 95-16500 Filed 7-5-95; 8:45 am]
    BILLING CODE 6717-01-M
    
    

Document Information

Published:
07/06/1995
Department:
Energy Department
Entry Type:
Notice
Document Number:
95-16500
Pages:
35198-35199 (2 pages)
Docket Numbers:
Docket No. CP95-579-000
PDF File: