98-18228. Pennsylvania Power & Light Company, Susquehanna Steam Electric Station (Units 1 & 2 ); Confirmatory Order Modifying Licenses Effective Immediately  

  • [Federal Register Volume 63, Number 131 (Thursday, July 9, 1998)]
    [Notices]
    [Pages 37145-37146]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-18228]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket Nos. 50-387 and 50-388]
    
    
    Pennsylvania Power & Light Company, Susquehanna Steam Electric 
    Station (Units 1 & 2 ); Confirmatory Order Modifying Licenses Effective 
    Immediately
    
    I
    
        Pennsylvania Power & Light Company, (PP&L or the Licensee) is the 
    holder of Facility Operating Licenses Nos. NPF-17 and NPF-22, which 
    authorize operation of Susquehanna Steam Electric Station Units 1 and 
    2, located in Luzerne County, Pennsylvania.
    
    II
    
        The staff of the U.S. Nuclear Regulatory Commission (NRC) has been 
    concerned that Thermo-Lag 330-1 fire barrier systems installed by 
    licensees may not provide the level of fire endurance intended and that 
    licensees that use Thermo-Lag 330-1 fire barriers may not be meeting 
    regulatory requirements. During the 1992 to 1994 time frame, the NRC 
    staff issued Generic Letter (GL) 92-08, ``Thermo-Lag 330-1 Fire 
    Barriers'' and subsequent requests for additional information that 
    requested licensees to submit plans and schedules for resolving the 
    Thermo-Lag issue. The NRC staff has obtained and reviewed all 
    licensees' corrective plans and implementation schedules. The staff is 
    concerned that some licensees may not be making adequate progress 
    toward resolving the plant-specific issues, and that some 
    implementation schedules may be either too tenuous or too protracted. 
    For example, several licensees informed the NRC staff that their 
    completion dates had slipped by 6 months to as much as 3 years. For 
    plants that have completion action scheduled beyond 1997, the NRC staff 
    has met with the licensees to discuss the progress of the licensees' 
    corrective actions and the extent of licensee management attention 
    regarding completion of Thermo-Lag corrective actions.
    
    [[Page 37146]]
    
        PP&L was one of the licensees with which the NRC staff held 
    meetings. At these meetings, the NRC staff reviewed with PP&L the 
    schedule of Thermo-Lag corrective actions described in the PP&L 
    submittals to the NRC dated April 15, 1993; February 3 and December 22, 
    1994; August 2, 1995; February 4, 1997; and January 6 and May 4, 1998. 
    Based on the information submitted by PP&L, the NRC staff has concluded 
    that the schedules presented by PP&L are reasonable. This conclusion is 
    based on the (1) amount of installed Thermo-Lag, (2) the complexity of 
    the plant-specific fire barrier configurations and issues, and (3) the 
    need to perform certain plant modifications during outages as opposed 
    to those that can be performed while the plant is at power. In order to 
    remove compensatory measures such as fire watches, it has been 
    determined that resolution of the Thermo-Lag corrective actions by PP&L 
    must be completed in accordance with current PP&L's schedules. By 
    letter dated May 19, 1998, the NRC staff notified PP&L of its plan to 
    incorporate PP&L's schedule commitment into a requirement by issuance 
    of an Order and requested consent from the Licensee. By letter dated 
    June 3, 1998, the Licensee provided its consent to issuance of a 
    Confirmatory Order.
    
    III
    
        The Licensee's commitment as set forth in its letter of June 3, 
    1998, is acceptable and is necessary for the NRC to conclude that 
    public health and safety are reasonably assured. To preclude any 
    schedule slippage and to assure public health and safety, the NRC staff 
    has determined that the Licensee's commitment in its June 3, 1998, 
    letter be confirmed by this Order. The Licensee has agreed to this 
    action. Based on the above, and the Licensee's consent, this Order is 
    immediately effective upon issuance.
    
    IV
    
        Accordingly, pursuant to sections 103, 161b, 161i, 161o, 182, and 
    186 of the Atomic Energy Act of 1954, as amended, and the Commission's 
    regulations in 10 CFR 2.202 and 10 CFR Part 50, IT IS HEREBY ORDERED, 
    effective immediately, that:
    
        Pennsylvania Power & Light Company shall complete final 
    implementation of Thermo-Lag 330-1 fire barrier corrective actions 
    at Susquehanna Steam Electric Station, Units 1 and 2, described in 
    the Pennsylvania Power & Light Company's submittals to the NRC dated 
    April 15, 1993; February 3 and December 22, 1994; August 2, 1995; 
    February 4, 1997; and January 6 and May 4, 1998, by completion of 
    the April 2000 refueling outage for SSES, Unit 1. Overall work 
    package closeout will be completed by the end of December 2000.
    
    The Director, Office of Nuclear Reactor Regulation, may relax or 
    rescind, in writing, any provisions of this Confirmatory Order upon a 
    showing by the Licensee of good cause.
    
    V
    
        Any person adversely affected by this Confirmatory Order, other 
    than the Licensee, may request a hearing within 20 days of its 
    issuance. Where good cause is shown, consideration will be given to 
    extending the time to request a hearing. A request for extension of 
    time must be made in writing to the Director, Office of Nuclear Reactor 
    Regulation, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555, 
    and include a statement of good cause for the extension.
        Any request for a hearing shall be submitted to the Secretary, U.S. 
    Nuclear Regulatory Commission, Attention: Chief, Rulemaking and 
    Adjudications Staff, Washington, D.C. 20555. Copies of the hearing 
    request shall also be sent to the Director, Office of Nuclear Reactor 
    Regulation, U. S. Nuclear Regulatory Commission, Washington, D. C. 
    20555, to the Deputy Assistant General Counsel for Enforcement at the 
    same address, to the Regional Administrator, NRC Region I, 475 
    Allendale Road, King of Prussia, Pennsylvania 19406-1415 and to the 
    Licensee. If such a person requests a hearing, that person shall set 
    forth with particularity the manner in which his/her interest is 
    adversely affected by this Order and shall address criteria set forth 
    in 10 CFR 2.714(d).
        If a hearing is requested by a person whose interest is adversely 
    affected, the Commission will issue an Order designating the time and 
    place of any such hearing. If a hearing is held, the issue to be 
    considered at such hearing shall be whether this Confirmatory Order 
    should be sustained.
        In the absence of any request for hearing, or written approval of 
    an extension of time in which to request a hearing, the provisions 
    specified in Section IV above shall be final 20 days from the date of 
    this Order without further order or proceedings. If an extension of 
    time for requesting a hearing has been approved, the provisions 
    specified in Section IV shall be final when the extension expires if a 
    hearing request has not been received. An answer or a request for 
    hearing shall not stay the immediate effectiveness of this Order.
    
        For the Nuclear Regulatory Commission.
    
        Dated at Rockville, Maryland this 2nd day of July 1998.
    Samuel J. Collins,
    Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 98-18228 Filed 7-8-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
07/09/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-18228
Pages:
37145-37146 (2 pages)
Docket Numbers:
Docket Nos. 50-387 and 50-388
PDF File:
98-18228.pdf