[Federal Register Volume 64, Number 131 (Friday, July 9, 1999)]
[Notices]
[Pages 37110-37112]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-17441]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER99-1984-001, et al.]
ALLIANT ENERGY CORPORATE SERVICES, INC., ET AL.; ELECTRIC RATE
AND CORPORATE REGULATION FILINGS
July 2, 1999.
Take notice that the following filings have been made with the
Commission:
1. Alliant Energy Corporate Services, Inc.
[Docket No. ER99-1984-001]
Take notice that on June 29, 1999, Alliant Energy Corporate
Services, Inc. submitted an amendment on behalf of IES Utilities Inc.
(IES), Interstate Power Company (IPC) and Wisconsin Power and Light
Company (WPL), in response to the Commission's order dated May 12,
1999, in North American Electric Reliability Council, Docket No. EL98-
52-000 (NERC Order). Alliant Energy has revised the terminology ``firm
load curtailment'' to ``firm transmission curtailment''. Alliant Energy
also has clarified that the implementation of MAIN Voluntary Interim
Regional Redispatch Plan involves the use of the NERC Market Redispatch
Pilot Project Summer 1999.
A copy of this filing has been served upon the Illinois Commerce
Commission, the Minnesota Public Utilities Commission, the Iowa
Department of Commerce, the Public Service Commission of Wisconsin, and
all parties listed on the service list as compiled by the Secretary in
this proceeding.
Comment date: July 19, 1999, in accordance with Standard Paragraph
E at the end of this notice.
2. California Power Exchange Corporation
[Docket Nos. EC96-19-050 and ER96-1663-052]
Take notice that on June 29, 1999, the California Power Exchange
Corporation (PX) filed proposed tariff sheets in compliance with the
Commission's June 1, 1999 order in the above proceeding.
Comment date: July 29, 1999, in accordance with Standard Paragraph
E at the end of this notice.
3. PP&L Resources, Inc., PP&L, Inc., Sunbury Holdings, LLC, and
Sunbury Generation, LLC
[Docket Nos. EC99-91-000 and ER99-3446-000]
Take notice that on June 30, 1999, PP&L Resources, Inc., PP&L,
Inc., Sunbury Holdings, LLC and Sunbury Generation, LLC (collectively
the Applicants) filed with the Commission a Joint Application for
Authorization to Sell Jurisdictional Facilities and for Approval of
Interconnection Agreement.
The Applicants have served a copy of the foregoing on the
Pennsylvania Public Utility Commission.
Comment date: July 30, 1999, in accordance with Standard Paragraph
E at the end of this notice.
4. Central Hudson Gas & Electric Corporation
[Docket No. ER99-3380-000]
Take notice that on June 28, 1999, Central Hudson Gas & Electric
Corporation (CHG&E), tendered for filing pursuant to Section 35.12 of
the Federal Energy Regulatory Commission's (Commission) Regulations in
18 CFR a Service Agreement between CHG&E and DukeSolutions, Inc. The
terms and conditions of service under this Agreement are made pursuant
to CHG&E's FERC Open Access Schedule, Original Volume No. 1
(Transmission Tariff) filed in compliance with the Commission's Order
No. 888 in Docket No. RM95-8-000 and RM94-7-001 and amended in
compliance with Commission Order dated May 28, 1997.
[[Page 37111]]
CHG&E also has requested waiver of the 60-day notice provision
pursuant to 18 CFR Section 35.11.
A copy of this filing has been served on the Public Service
Commission of the State of New York.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
5. Central Hudson Gas & Electric Corporation
[Docket No. ER99-3381-000]
Take notice that on June 28, 1999, Central Hudson Gas & Electric
Corporation (CHG&E), tendered for filing pursuant to Section 35.12 of
the Federal Energy Regulatory Commission's (Commission) Regulations, a
Service Agreement between CHG&E and Cargill-Alliant, LLC. The terms and
conditions of service under this Agreement are made pursuant to CHG&E's
FERC Open Access Schedule, Original Volume No. 1 (Transmission Tariff),
filed in compliance with the Commission's Order No. 888 in Docket No.
RM95-8-000 and RM94-7-001 and amended in compliance with Commission
Order dated May 28, 1997.
CHG&E also has requested a waiver of the 60-day notice provision
pursuant to 18 CFR Section 35.11.
A copy of this filing has been served on the Public Service
Commission of the State of New York.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
6. Central Hudson Gas & Electric Corporation
[Docket No. ER99-3382-000]
Take notice that on June 28, 1999, tendered Central Hudson Gas &
Electric Corporation (CHG&E), for filing pursuant to Section 35.12 of
the Federal Energy Regulatory Commission's (Commission) Regulations, a
Service Agreement between CHG&E and Avista Energy Inc. The terms and
conditions of service under this Agreement are made pursuant to CHG&E's
FERC Open Access Schedule, Original Volume No. 1 (Transmission Tariff),
filed in compliance with the Commission's Order No. 888 in Docket No.
RM95-8-000 and RM94-7-001 and amended in compliance with Commission
Order dated May 28, 1997.
CHG&E also has requested waiver of the 60-day notice provision
pursuant to 18 CFR Section 35.11.
A copy of this filing has been served on the Public Service
Commission of the State of New York.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
7. Central Hudson Gas & Electric Corporation
[Docket No. ER99-3383-000]
Take notice that on June 28, 1999, Central Hudson Gas & Electric
Corporation (CHG&E), tendered for filing pursuant to Section 35.12 of
the Federal Energy Regulatory Commission's (Commission) Regulations, a
Service Agreement between CHG&E and KeySpan-Ravenswood, Inc. The terms
and conditions of service under this Agreement are made pursuant to
CHG&E's FERC Open Access Schedule, Original Volume No.1 (Transmission
Tariff) filed in compliance with the Commission's Order No. 888 in
Docket No. RM95-8-000 and RM94-7-001 and amended in compliance with
Commission Order dated May 28, 1997.
CHG&E also has requested waiver of the 60-day notice provision
pursuant to 18 CFR Section 35.11.
A copy of this filing has been served on the Public Service
Commission of the State of New York.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
8. Montaup Electric Company
[Docket No. ER99-3384-000]
Take notice that on June 28, 1999, Montaup Electric Company
(Montaup), tendered for filing an executed service agreement under
Montaup's market-based power sales tariff, FERC Electric Tariff,
Original Volume No. 8, between Montaup and Constellation Power Source,
Inc.
Montaup requests a waiver of the sixty-day notice requirement so
that the service agreement may become effective as of June 1, 1999.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
9. The Detroit Edison Company
[Docket No. ER99-3386-000]
Take notice that on June 28, 1999, The Detroit Edison Company
(Detroit Edison) tendered for filing Service Agreements for wholesale
power sales transactions (the Service Agreements) under Detroit
Edison's Wholesale Power Sales Tariff (WPS-1), FERC Electric Tariff No.
4 (the WPS-1 Tariff), and Wholesale Power Sales Tariff (WPS-2), FERC
Electric Tariff No. 3 (the WPS-2 Tariff).
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
10. Avista Corp.
[Docket No. ER99-3391-000]
Take notice that on June 28, 1999, Avista Corp. (AVA), tendered for
filing with the Federal Energy Regulatory Commission an executed
Service Agreement for Short-Term Firm and Non-Firm Point-To-Point
Transmission Service under AVA's Open Access Transmission Tariff--FERC
Electric Tariff, Volume No. 8 with Los Angeles Department of Water and
Power.
AVA requests the Service Agreement be given the respective
effective date of June 4, 1999.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
11. PJM Interconnection, L.L.C.
[Docket No. ER99-3392-000]
Take notice that on June 28, 1999, PJM Interconnection, L.L.C.
(PJM), tendered for filing 3 executed service agreements with PP&L,
Inc., Baltimore Gas and Electric Company and Public Service Electric
and Gas Company for point-to-point transmission service under the PJM
Open Access Transmission Tariff.
Copies of this filing were served upon the parties to the service
agreements.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
12. PJM Interconnection, L.L.C.
[Docket No. ER99-3393-000]
Take notice that on June 28, 1999, PJM Interconnection, L.L.C.
(PJM), tendered for filing an executed Service Agreement for Network
Integration Transmission Service between PJM and PECO Energy Company to
enable PECO Energy Company to sell electricity to the New Jersey
Boroughs of Butler, Lavallette, Madison, Pemberton and Seaside Heights.
PJM requests a waiver of the Commission's notice requirements and
an effective dated of June 1, 1999.
A copy of the filing was served upon PECO Energy Company, Jersey
Central Power & Light Company, and the Pennsylvania Public Utility
Commission.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
13. Niagara Mohawk Power Corporation
[Docket No. ER99-3394-000]
Take notice that on June 28, 1999, Niagara Mohawk Power Corporation
(Niagara Mohawk), tendered for filing with the Federal Energy
Regulatory Commission an executed Transmission
[[Page 37112]]
Service Agreement between Niagara Mohawk and NRG Power Marketing, Inc.,
(NRG). This Transmission Service Agreement specifies that NRG has
signed on to and has agreed to the terms and conditions of Niagara
Mohawk's Open Access Transmission Tariff as filed in Docket No. OA96-
194-000. This Tariff, filed with FERC on July 9, 1996, will allow
Niagara Mohawk and NRG to enter into separately scheduled transactions
under which Niagara Mohawk will provide non-firm transmission service
for NRG as the parties may mutually agree.
Niagara Mohawk requests an effective date of June 17, 1999. Niagara
Mohawk has requested waiver of the notice requirements for good cause
shown.
Niagara Mohawk has served copies of the filing upon the New York
State Public Service Commission and NRG.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
14. Niagara Mohawk Power Corporation
[Docket No. ER99-3395-000 ]
Take notice that on June 28, 1999, Niagara Mohawk (Niagara Mohawk),
tendered for filing with the Federal Energy Regulatory Commission an
executed Transmission Service Agreement between Niagara Mohawk and NRG
Power Marketing, Inc. (NRG). This Transmission Service Agreement
specifies that NRG has signed on to and has agreed to the terms and
conditions of Niagara Mohawk's Open Access Transmission Tariff as filed
in Docket No. OA96-194-000. This Tariff, filed with FERC on July 9,
1996, will allow Niagara Mohawk and NRG to enter into separately
scheduled transactions under which Niagara Mohawk will provide firm
transmission service for NRG as the parties may mutually agree.
Niagara Mohawk requests an effective date of June 17, 1999. Niagara
Mohawk has requested waiver of the notice requirements for good cause
shown.
Niagara Mohawk has served copies of the filing upon the New York
State Public Service Commission and NRG.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
15. Southern Energy NY-GEN, L.L.C.
[Docket No. ER99-3407-000]
Take notice that on June 29, 1999, Southern Energy NY-GEN, L.L.C.
(July 2, 1999 Southern NY-GEN), tendered for filing the following
agreements as a long-term service agreement under its Market Rate
Tariff accepted by the Commission in the Docket No. ER99-2045-000:
1. Western Load Pocket Call Option Agreement Between Orange and
Rockland Utilities, Inc., and Southern Energy NY-GEN, L.L.C., dated
November 24, 1998, as amended, June 14, 1999.
Comment date: July 19, 1999, in accordance with Standard Paragraph
E at the end of this notice.
16. Avista Corp.
[Docket No. ER99-3408-000]
Take notice that on June 29, 1999, Avista Corp., tendered for
filing, pursuant to Section 35.12 of the Commission's Regulations, 18
CFR 35.12, an executed service agreement with Cogentrix Energy Power
Marketing, Inc., for Dynamic Capacity and Energy Service at cost-based
rates under Avista Corp.'s FERC Electric Tariff, Original Volume No.
10.
Avista Corp. requests that the Commission waive its prior notice
requirement, pursuant to Section 35.11 of the Commission's regulations,
18 CFR 35.11, and accept the service agreement for filing effective
June 1, 1999.
Comment date: July 19, 1999, in accordance with Standard Paragraph
E at the end of this notice.
17. Puget Sound Energy, Inc.
[Docket No. ER99-3409-000]
Take notice that on June 29, 1999, Puget Sound Energy, Inc., as
Transmission Provider, tendered for filing a Service Agreement for Firm
Point-To-Point Transmission Service (Firm-To-Point Service Agreement),
and a Service Agreement for Non-Firm Point-To-Point Service (Non-Firm
Point-To-Point Service Agreement) with Seattle City Light (SCL), as
Transmission Customer.
A copy of the filing was served upon SCL.
Comment date: July 19, 1999, in accordance with Standard Paragraph
E at the end of this notice.
18. The Montana Power Company
[Docket No. ER99-3474-000]
Take notice that on June 28, 1999, The Montana Power Company
(Montana) tendered for filing with the Federal Energy Regulatory
Commission pursuant to 18 CFR 35.13 an unexecuted Firm and executed
Non-Firm Point-To-Point Transmission Service Agreements with Arizona
Public Service under Montana's FERC Electric Tariff, Fourth Revised
Volume No. 5 (Open Access Transmission Tariff).
A copy of the filing was served upon Arizona Public Service.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
19. El Paso Electric Company
[Docket No. OA96-200-007]
Take notice that on June 25, 1999, El Paso Electric Company (EPE or
Company) tendered for filing with the Federal Energy Regulatory
Commission, modifications to its open access transmission tariff
pursuant to FERC Opinion No. 437 issued May 26, 1999.
Comment date: July 16, 1999, in accordance with Standard Paragraph
E at the end of this notice.
Standard Paragraphs:
E. Any person desiring to be heard or to protest such filing should
file a motion to intervene or protest with the Federal Energy
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,
in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 385.214). All such motions
or protests should be filed on or before the comment date. Protests
will be considered by the Commission in determining the appropriate
action to be taken, but will not serve to make protestants parties to
the proceeding. Any person wishing to become a party must file a motion
to intervene. Copies of these filings are on file with the Commission
and are available for public inspection. This filing may also be viewed
on the Internet at http://www.ferc.fed.us/online/rims.htm (call 202-
208-2222 for assistance).
David P. Boergers,
Secretary.
[FR Doc. 99-17441 Filed 7-8-99; 8:45 am]