99-17441. ALLIANT ENERGY CORPORATE SERVICES, INC., ET AL.; ELECTRIC RATE AND CORPORATE REGULATION FILINGS  

  • [Federal Register Volume 64, Number 131 (Friday, July 9, 1999)]
    [Notices]
    [Pages 37110-37112]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-17441]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. ER99-1984-001, et al.]
    
    
    ALLIANT ENERGY CORPORATE SERVICES, INC., ET AL.; ELECTRIC RATE 
    AND CORPORATE REGULATION FILINGS
    
    July 2, 1999.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. Alliant Energy Corporate Services, Inc.
    
    [Docket No. ER99-1984-001]
    
        Take notice that on June 29, 1999, Alliant Energy Corporate 
    Services, Inc. submitted an amendment on behalf of IES Utilities Inc. 
    (IES), Interstate Power Company (IPC) and Wisconsin Power and Light 
    Company (WPL), in response to the Commission's order dated May 12, 
    1999, in North American Electric Reliability Council, Docket No. EL98-
    52-000 (NERC Order). Alliant Energy has revised the terminology ``firm 
    load curtailment'' to ``firm transmission curtailment''. Alliant Energy 
    also has clarified that the implementation of MAIN Voluntary Interim 
    Regional Redispatch Plan involves the use of the NERC Market Redispatch 
    Pilot Project Summer 1999.
        A copy of this filing has been served upon the Illinois Commerce 
    Commission, the Minnesota Public Utilities Commission, the Iowa 
    Department of Commerce, the Public Service Commission of Wisconsin, and 
    all parties listed on the service list as compiled by the Secretary in 
    this proceeding.
        Comment date: July 19, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    2. California Power Exchange Corporation
    
    [Docket Nos. EC96-19-050 and ER96-1663-052]
    
        Take notice that on June 29, 1999, the California Power Exchange 
    Corporation (PX) filed proposed tariff sheets in compliance with the 
    Commission's June 1, 1999 order in the above proceeding.
        Comment date: July 29, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    3. PP&L Resources, Inc., PP&L, Inc., Sunbury Holdings, LLC, and 
    Sunbury Generation, LLC
    
    [Docket Nos. EC99-91-000 and ER99-3446-000]
    
        Take notice that on June 30, 1999, PP&L Resources, Inc., PP&L, 
    Inc., Sunbury Holdings, LLC and Sunbury Generation, LLC (collectively 
    the Applicants) filed with the Commission a Joint Application for 
    Authorization to Sell Jurisdictional Facilities and for Approval of 
    Interconnection Agreement.
        The Applicants have served a copy of the foregoing on the 
    Pennsylvania Public Utility Commission.
        Comment date: July 30, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    4. Central Hudson Gas & Electric Corporation
    
    [Docket No. ER99-3380-000]
    
        Take notice that on June 28, 1999, Central Hudson Gas & Electric 
    Corporation (CHG&E), tendered for filing pursuant to Section 35.12 of 
    the Federal Energy Regulatory Commission's (Commission) Regulations in 
    18 CFR a Service Agreement between CHG&E and DukeSolutions, Inc. The 
    terms and conditions of service under this Agreement are made pursuant 
    to CHG&E's FERC Open Access Schedule, Original Volume No. 1 
    (Transmission Tariff) filed in compliance with the Commission's Order 
    No. 888 in Docket No. RM95-8-000 and RM94-7-001 and amended in 
    compliance with Commission Order dated May 28, 1997.
    
    [[Page 37111]]
    
        CHG&E also has requested waiver of the 60-day notice provision 
    pursuant to 18 CFR Section 35.11.
        A copy of this filing has been served on the Public Service 
    Commission of the State of New York.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    5. Central Hudson Gas & Electric Corporation
    
    [Docket No. ER99-3381-000]
    
        Take notice that on June 28, 1999, Central Hudson Gas & Electric 
    Corporation (CHG&E), tendered for filing pursuant to Section 35.12 of 
    the Federal Energy Regulatory Commission's (Commission) Regulations, a 
    Service Agreement between CHG&E and Cargill-Alliant, LLC. The terms and 
    conditions of service under this Agreement are made pursuant to CHG&E's 
    FERC Open Access Schedule, Original Volume No. 1 (Transmission Tariff), 
    filed in compliance with the Commission's Order No. 888 in Docket No. 
    RM95-8-000 and RM94-7-001 and amended in compliance with Commission 
    Order dated May 28, 1997.
        CHG&E also has requested a waiver of the 60-day notice provision 
    pursuant to 18 CFR Section 35.11.
        A copy of this filing has been served on the Public Service 
    Commission of the State of New York.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    6. Central Hudson Gas & Electric Corporation
    
    [Docket No. ER99-3382-000]
    
        Take notice that on June 28, 1999, tendered Central Hudson Gas & 
    Electric Corporation (CHG&E), for filing pursuant to Section 35.12 of 
    the Federal Energy Regulatory Commission's (Commission) Regulations, a 
    Service Agreement between CHG&E and Avista Energy Inc. The terms and 
    conditions of service under this Agreement are made pursuant to CHG&E's 
    FERC Open Access Schedule, Original Volume No. 1 (Transmission Tariff), 
    filed in compliance with the Commission's Order No. 888 in Docket No. 
    RM95-8-000 and RM94-7-001 and amended in compliance with Commission 
    Order dated May 28, 1997.
        CHG&E also has requested waiver of the 60-day notice provision 
    pursuant to 18 CFR Section 35.11.
        A copy of this filing has been served on the Public Service 
    Commission of the State of New York.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    7. Central Hudson Gas & Electric Corporation
    
    [Docket No. ER99-3383-000]
    
        Take notice that on June 28, 1999, Central Hudson Gas & Electric 
    Corporation (CHG&E), tendered for filing pursuant to Section 35.12 of 
    the Federal Energy Regulatory Commission's (Commission) Regulations, a 
    Service Agreement between CHG&E and KeySpan-Ravenswood, Inc. The terms 
    and conditions of service under this Agreement are made pursuant to 
    CHG&E's FERC Open Access Schedule, Original Volume No.1 (Transmission 
    Tariff) filed in compliance with the Commission's Order No. 888 in 
    Docket No. RM95-8-000 and RM94-7-001 and amended in compliance with 
    Commission Order dated May 28, 1997.
        CHG&E also has requested waiver of the 60-day notice provision 
    pursuant to 18 CFR Section 35.11.
        A copy of this filing has been served on the Public Service 
    Commission of the State of New York.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    8. Montaup Electric Company
    
    [Docket No. ER99-3384-000]
    
        Take notice that on June 28, 1999, Montaup Electric Company 
    (Montaup), tendered for filing an executed service agreement under 
    Montaup's market-based power sales tariff, FERC Electric Tariff, 
    Original Volume No. 8, between Montaup and Constellation Power Source, 
    Inc.
        Montaup requests a waiver of the sixty-day notice requirement so 
    that the service agreement may become effective as of June 1, 1999.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    9. The Detroit Edison Company
    
    [Docket No. ER99-3386-000]
    
        Take notice that on June 28, 1999, The Detroit Edison Company 
    (Detroit Edison) tendered for filing Service Agreements for wholesale 
    power sales transactions (the Service Agreements) under Detroit 
    Edison's Wholesale Power Sales Tariff (WPS-1), FERC Electric Tariff No. 
    4 (the WPS-1 Tariff), and Wholesale Power Sales Tariff (WPS-2), FERC 
    Electric Tariff No. 3 (the WPS-2 Tariff).
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    10. Avista Corp.
    
    [Docket No. ER99-3391-000]
    
        Take notice that on June 28, 1999, Avista Corp. (AVA), tendered for 
    filing with the Federal Energy Regulatory Commission an executed 
    Service Agreement for Short-Term Firm and Non-Firm Point-To-Point 
    Transmission Service under AVA's Open Access Transmission Tariff--FERC 
    Electric Tariff, Volume No. 8 with Los Angeles Department of Water and 
    Power.
        AVA requests the Service Agreement be given the respective 
    effective date of June 4, 1999.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    11. PJM Interconnection, L.L.C.
    
    [Docket No. ER99-3392-000]
    
        Take notice that on June 28, 1999, PJM Interconnection, L.L.C. 
    (PJM), tendered for filing 3 executed service agreements with PP&L, 
    Inc., Baltimore Gas and Electric Company and Public Service Electric 
    and Gas Company for point-to-point transmission service under the PJM 
    Open Access Transmission Tariff.
        Copies of this filing were served upon the parties to the service 
    agreements.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    12. PJM Interconnection, L.L.C.
    
    [Docket No. ER99-3393-000]
    
        Take notice that on June 28, 1999, PJM Interconnection, L.L.C. 
    (PJM), tendered for filing an executed Service Agreement for Network 
    Integration Transmission Service between PJM and PECO Energy Company to 
    enable PECO Energy Company to sell electricity to the New Jersey 
    Boroughs of Butler, Lavallette, Madison, Pemberton and Seaside Heights.
        PJM requests a waiver of the Commission's notice requirements and 
    an effective dated of June 1, 1999.
        A copy of the filing was served upon PECO Energy Company, Jersey 
    Central Power & Light Company, and the Pennsylvania Public Utility 
    Commission.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    13. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-3394-000]
    
        Take notice that on June 28, 1999, Niagara Mohawk Power Corporation 
    (Niagara Mohawk), tendered for filing with the Federal Energy 
    Regulatory Commission an executed Transmission
    
    [[Page 37112]]
    
    Service Agreement between Niagara Mohawk and NRG Power Marketing, Inc., 
    (NRG). This Transmission Service Agreement specifies that NRG has 
    signed on to and has agreed to the terms and conditions of Niagara 
    Mohawk's Open Access Transmission Tariff as filed in Docket No. OA96-
    194-000. This Tariff, filed with FERC on July 9, 1996, will allow 
    Niagara Mohawk and NRG to enter into separately scheduled transactions 
    under which Niagara Mohawk will provide non-firm transmission service 
    for NRG as the parties may mutually agree.
        Niagara Mohawk requests an effective date of June 17, 1999. Niagara 
    Mohawk has requested waiver of the notice requirements for good cause 
    shown.
        Niagara Mohawk has served copies of the filing upon the New York 
    State Public Service Commission and NRG.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    14. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-3395-000 ]
    
        Take notice that on June 28, 1999, Niagara Mohawk (Niagara Mohawk), 
    tendered for filing with the Federal Energy Regulatory Commission an 
    executed Transmission Service Agreement between Niagara Mohawk and NRG 
    Power Marketing, Inc. (NRG). This Transmission Service Agreement 
    specifies that NRG has signed on to and has agreed to the terms and 
    conditions of Niagara Mohawk's Open Access Transmission Tariff as filed 
    in Docket No. OA96-194-000. This Tariff, filed with FERC on July 9, 
    1996, will allow Niagara Mohawk and NRG to enter into separately 
    scheduled transactions under which Niagara Mohawk will provide firm 
    transmission service for NRG as the parties may mutually agree.
        Niagara Mohawk requests an effective date of June 17, 1999. Niagara 
    Mohawk has requested waiver of the notice requirements for good cause 
    shown.
        Niagara Mohawk has served copies of the filing upon the New York 
    State Public Service Commission and NRG.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    15. Southern Energy NY-GEN, L.L.C.
    
    [Docket No. ER99-3407-000]
    
        Take notice that on June 29, 1999, Southern Energy NY-GEN, L.L.C. 
    (July 2, 1999 Southern NY-GEN), tendered for filing the following 
    agreements as a long-term service agreement under its Market Rate 
    Tariff accepted by the Commission in the Docket No. ER99-2045-000:
        1. Western Load Pocket Call Option Agreement Between Orange and 
    Rockland Utilities, Inc., and Southern Energy NY-GEN, L.L.C., dated 
    November 24, 1998, as amended, June 14, 1999.
        Comment date: July 19, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    16. Avista Corp.
    
    [Docket No. ER99-3408-000]
    
        Take notice that on June 29, 1999, Avista Corp., tendered for 
    filing, pursuant to Section 35.12 of the Commission's Regulations, 18 
    CFR 35.12, an executed service agreement with Cogentrix Energy Power 
    Marketing, Inc., for Dynamic Capacity and Energy Service at cost-based 
    rates under Avista Corp.'s FERC Electric Tariff, Original Volume No. 
    10.
        Avista Corp. requests that the Commission waive its prior notice 
    requirement, pursuant to Section 35.11 of the Commission's regulations, 
    18 CFR 35.11, and accept the service agreement for filing effective 
    June 1, 1999.
        Comment date: July 19, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    17. Puget Sound Energy, Inc.
    
    [Docket No. ER99-3409-000]
    
        Take notice that on June 29, 1999, Puget Sound Energy, Inc., as 
    Transmission Provider, tendered for filing a Service Agreement for Firm 
    Point-To-Point Transmission Service (Firm-To-Point Service Agreement), 
    and a Service Agreement for Non-Firm Point-To-Point Service (Non-Firm 
    Point-To-Point Service Agreement) with Seattle City Light (SCL), as 
    Transmission Customer.
        A copy of the filing was served upon SCL.
        Comment date: July 19, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    18. The Montana Power Company
    
    [Docket No. ER99-3474-000]
    
        Take notice that on June 28, 1999, The Montana Power Company 
    (Montana) tendered for filing with the Federal Energy Regulatory 
    Commission pursuant to 18 CFR 35.13 an unexecuted Firm and executed 
    Non-Firm Point-To-Point Transmission Service Agreements with Arizona 
    Public Service under Montana's FERC Electric Tariff, Fourth Revised 
    Volume No. 5 (Open Access Transmission Tariff).
        A copy of the filing was served upon Arizona Public Service.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    19. El Paso Electric Company
    
    [Docket No. OA96-200-007]
    
        Take notice that on June 25, 1999, El Paso Electric Company (EPE or 
    Company) tendered for filing with the Federal Energy Regulatory 
    Commission, modifications to its open access transmission tariff 
    pursuant to FERC Opinion No. 437 issued May 26, 1999.
        Comment date: July 16, 1999, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    Standard Paragraphs:
    
        E. Any person desiring to be heard or to protest such filing should 
    file a motion to intervene or protest with the Federal Energy 
    Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
    in accordance with Rules 211 and 214 of the Commission's Rules of 
    Practice and Procedure (18 CFR 385.211 and 385.214). All such motions 
    or protests should be filed on or before the comment date. Protests 
    will be considered by the Commission in determining the appropriate 
    action to be taken, but will not serve to make protestants parties to 
    the proceeding. Any person wishing to become a party must file a motion 
    to intervene. Copies of these filings are on file with the Commission 
    and are available for public inspection. This filing may also be viewed 
    on the Internet at http://www.ferc.fed.us/online/rims.htm (call 202-
    208-2222 for assistance).
    David P. Boergers,
    Secretary.
    [FR Doc. 99-17441 Filed 7-8-99; 8:45 am]
    BILLING CODE 6717-01-P
    
    
    

Document Information

Published:
07/09/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-17441
Dates:
July 19, 1999, in accordance with Standard Paragraph E at the end of this notice.
Pages:
37110-37112 (3 pages)
Docket Numbers:
Docket No. ER99-1984-001, et al.
PDF File:
99-17441.pdf