94-19608. Northern Natural Gas Company, et al.; Natural Gas Certificate Filings  

  • [Federal Register Volume 59, Number 154 (Thursday, August 11, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-19608]
    
    
    [[Page Unknown]]
    
    [Federal Register: August 11, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP94-681-000., et al.]
    
     
    
    Northern Natural Gas Company, et al.; Natural Gas Certificate 
    Filings
    
    August 4, 1994.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. Northern Natural Gas Company
    
    [Docket No. CP94-681-000]
    
        Take notice that on July 22, 1994, Northern Natural Gas Company 
    (Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed 
    in Docket No. CP94-681-000 a request pursuant to Sections 157.205 and 
    157.212 of the Commission's Regulations under the Natural Gas Act for 
    authorization to construct and operate facilities to implement a new 
    delivery point near Blair, Nebraska to accommodate natural gas 
    deliveries to Peoples Natural Gas Company (Peoples), under its blanket 
    certificate issued in Docket No. CP82-401-000,1 all as more fully 
    set forth in the request for authorization on file with the Commission 
    and open for public inspection.
    ---------------------------------------------------------------------------
    
        \1\See, 20 FERC  62,410 (1982).
    ---------------------------------------------------------------------------
    
        Northern states it has entered into a transportation service 
    agreement with Peoples for the firm transportation and delivery of 
    natural gas to Peoples at the proposed delivery point of up to 10 Bcf 
    annually and 11,500 Mcf per peak day. Northern holds a blanket 
    transportation certificate pursuant to Part 284 of the Commission's 
    Regulations issued in Docket No. CP86-435-000.2 Peoples has 
    requested a new delivery point from Northern so they may serve the new 
    Cargill plant near Blair, Nebraska. Northern states that the lateral 
    pipeline route will begin at Northern's ``C'' mainline 24-inch takeoff 
    in the NW \1/4\ of Section 16, Township 18 North, Range 8 East, Dodge 
    County, and continue in an easterly direction approximately 16 miles to 
    Northern's town border station (TBS) following within 30 feet to the 
    north or south, Northern's existing 6-inch lateral line servicing 
    Blair. Northern states that Peoples will construct the entire 24 miles 
    of 8-inch pipeline from Northern's ``C'' mainline to the Cargill. 
    Northern will own and operate approximately 16 miles of the 8-inch 
    lateral pipeline, and Peoples will own and operate 8 miles from 
    Northern's TBS to the Cargill plant.
    ---------------------------------------------------------------------------
    
        \2\See, 37 FERC  61,268 (1986).
    ---------------------------------------------------------------------------
    
        Northern states that the total volumes to be delivered to the 
    customer after the request do not exceed the total volumes authorized 
    prior to the request. Northern states that construction of the proposed 
    delivery point is not prohibited by its existing tariff and that it has 
    sufficient capacity to deliver the requested gas volumes without 
    detriment or disadvantage to it's other customers. Northern estimates 
    the cost of the proposed facilities at $192,000; which includes the 
    meter run, the take-off from the ``C'' mainline and the flange setting.
        Comment date: September 19, 1994, in accordance with Standard 
    Paragraph G at the end of this notice.
    
    2. Transcontinental Gas Pipe Line Corporation
    
    [Docket No. CP94-692-000]
    
        Take notice that on August 1, 1994, Transcontinental Gas Pipe line 
    Corporation (Transco), Post Office Box 1396, Houston, Texas 77251, 
    filed in Docket No. CP94-692-000 an application pursuant to Section 7 
    (b) and (c) of the Natural Gas Act for permission and approval to 
    abandon approximately 0.86 miles of 30-inch pipeline and for a 
    certificate of public convenience and necessity authorizing the 
    construction and operation of approximately 0.86 miles of 30-inch 
    replacement pipeline on its Main Line A across the Neches River in 
    Hardin and Jasper Counties, Texas and across the Village Creek in 
    Hardin County, Texas, all as more fully set forth in the application 
    which is on file with the Commission and open to public inspection.
        Transco proposes to: (1) Construct and operate approximately 4,270 
    feet of 30-inch pipeline by horizontal directional drilling under the 
    Neches River at its existing pipeline river crossing located 8 miles 
    north of Beaumont, Texas and 20 miles west of the Texas-Louisiana 
    boundary and construct and operate approximately 512 feet of 
    conventionally installed tie-in piping on the banks of the river to 
    connect the drilled crossing to Transco's Main Line A; (2) construct 
    and operate approximately 260 feet of 30-inch pipeline by conventional 
    ditching approximately 25 feet to the north of its existing Village 
    Creek crossing of Main Line A located 1.8 miles west of the Neches 
    River crossing in Hardin County, Texas with tie-ins to Main Line A on 
    each river bank when the replaced portion of Main Line A is removed 
    from service; and (3) abandon by removal the portions of Main Line A 
    replaced at the Neches River and the Village Creek crossings. Transco 
    states that the proposed replacements will restore the long-term 
    integrity of its transmission system at the Neches River and the 
    Village River crossings and that the capacity will remain at the 
    existing 624 MMcf per day.
        Transco states that the abandonment of the portions of the Main 
    Line A at the Neches River crossing will be completed in two separate 
    projects. Transco proposes to remove approximately 260 feet of the 
    existing 30-inch line from the point of tie-in on the west side of the 
    river and approximately 80 feet of the existing 30-inch line from the 
    point of tie-in on the east side of the river in 1994, at the time of 
    the pipeline replacement construction. The abandonment of the remaining 
    facilities at the Neches River crossing will be completed in 1995, as a 
    separate project, after necessary permits are obtained. Transco 
    proposes to remove, in 1994, approximately 240 feet of its Main Line A 
    at the Village Creek crossing after the replacement line is constructed 
    and tied in. Transco also requests temporary authorization to complete 
    the river crossing replacements if permanent authorization is not 
    issued by August 19, 1994, for security of gas service during the 
    upcoming heating season. The estimated cost of construction is 
    $4,694,455 with abandonment cost estimated at $972,000. The cost will 
    be initially financed by Transco by funds on hand and short-term loans 
    which will be rolled into permanent financing.
        Comment date: August 19, 1994, in accordance with Standard 
    Paragraph F at the end of this notice.
    
    3. National Fuel Gas Supply Corporation
    
    [Docket No. CP94-693-000]
    
        Take notice that on August 1, 1994, National Fuel Gas Supply 
    Corporation (National Fuel), 10 Lafayette Square, Buffalo, New York 
    14203, filed in Docket No. CP94-693-000 a request pursuant to Sections 
    157.205 and 157.212 of the Commission's Regulations under the Natural 
    Gas Act (18 CFR 157.205 and 157.212) for authorization to construct and 
    operate a new point of delivery to provide service to an existing 
    customer, National Fuel Gas Distribution Corporation (Distribution), 
    under National Fuel's blanket certificate issued in Docket No. CP83-4-
    000, pursuant to Section 7(c) of the Natural Gas Act, all as more fully 
    set forth in the request that is on file with the Commission and open 
    to public inspection.
        National Fuel states that the new delivery point will be located in 
    the town of Grand Island, Erie County, New York, at the same station at 
    which National Fuel will interconnect with the facilities of Empire 
    State Pipeline, an intrastate pipeline, and will be used to provide 
    service to Distribution, and to Distribution's present and future 
    transportation customers. Additionally, National Fuel states that the 
    total volumes to be delivered are estimated to be no more than 
    3,200,000 Dth annually and will have no impact on National Fuel's total 
    peak day and annual deliveries, but will make it more likely that 
    National Fuel will be able to make the deliveries at the points and in 
    the quantities desired by Distribution and its customers. National Fuel 
    estimates that the total cost of constructing the delivery point is 
    $1,525,000.
        National Fuel notes that it has previously applied for approval 
    under Section 7(c) of the Natural Gas Act for the acquisition and 
    construction of certain facilities, including construction of the Grand 
    Island delivery point, and received conditional approval by order 
    issued June 1, 1994, in Docket Nos. CP94-112-000 and CP88-94-008 (67 
    FERC  61,270 (1994)). National Fuel states that it has been unable to 
    commence acquisition and construction because National Fuel cannot 
    satisfy all the conditions included in the June 1 order. National Fuel 
    contends that it urgently needs to commence construction of the Grand 
    Island station in September, in order to have the station in operation 
    by November 1. National Fuel asserts that the new station is necessary 
    to relieve some of the load which currently must be satisfied from gas 
    fed into the eastern end of Line U because Line U operates at its 
    absolute peak capacity on a cold day.
        Comment date: September 19, 1994, in accordance with Standard 
    Paragraph G at the end of this notice.
    
    4. Distrigas of Massachusetts Corporation
    
    [Docket No. CP94-694-000]
    
        Take notice that on August 1, 1994, Distrigas of Massachusetts 
    Corporation (DOMAC), 200 State Street, Boston, Massachusetts 02109, 
    filed in Docket No. CP94-694-000, an abbreviated application pursuant 
    to Section 7(c) of the Natural Gas Act, for a certificate of public 
    convenience and necessity authorizing DOMAC to install additional air 
    stabilization equipment at DOMAC's liquefied natural gas (LNG) terminal 
    in Everett, Massachusetts. DOMAC also requests, pursuant to Section 
    157.17 of the Regulations of the Federal Energy Regulatory Commission 
    (Commission), a temporary certificate authorizing the installation and 
    use, on a temporary basis, of leased air injection equipment, pending 
    the installation and operation of the requested permanent equipment, 
    all as more fully set forth in the application which is on file with 
    the Commission and open to public inspection.
        DOMAC states that it anticipates in the near future it will receive 
    additional cargoes of higher Btu LNG that will require air 
    stabilization capability in excess of DOMAC's current installed 
    capacity.3 In addition, DOMAC states that it needs to be able to 
    accept LNG of varying thermal contents at any time of the year, whether 
    supplied through the long-term contracts of SONATRACH, Distrigas 
    Corporation's Algerian supplier, or short-term or spot transactions 
    with other suppliers in the international marketplace. DOMAC states 
    that the new facilities will consist of one integrated unit of two 
    electric driven compressors and will be constructed wholly within 
    DOMAC's existing Everett facility and placed on a concrete pad within a 
    weather enclosure. DOMAC requests approval on an expedited basis so 
    that the permanent facilities can be installed and operational by 
    January 1, 1995.
    ---------------------------------------------------------------------------
    
        \3\ A 1990 Operating Agreement requires that DOMAC air stabilize 
    any regasified LNG with a heating value in excess of 1,090 Btus per 
    standard cubic foot prior to delivery to Algonquin Gas Transmission 
    Company (Algonquin). DOMAC's existing equipment is capable of air 
    stabilizing high Btu LNG (up to 1125 Btu per standard cubic foot) 
    into Algonquin at an average throughput of 45,000 MMBtu per day.
    ---------------------------------------------------------------------------
    
        DOMAC states that it will likely require additional air 
    stabilization capacity for one or more cargoes in the fall of 1994, 
    before a permanent certificate can be issued and the permanent 
    equipment can be installed and become operational. DOMAC proposes to 
    lease and install by September 1, 1994, temporary air stabilization 
    equipment to permit DOMAC to air stabilize regasified LNG before 
    delivering it into the J-System of Algonquin at the high throughput 
    rates expected for that time period. DOMAC states that the leased 
    temporary air stabilization equipment will consist of one integrated 
    unit of two truck-mounted diesel powered compressors. DOMAC requests 
    that a temporary certificate be issued on or before August 20, 1994, to 
    permit DOMAC to install this leased equipment by September 1, 1994, and 
    to operate the leased equipment pending the Commission's determination 
    concerning the permanent authorization and until such time as the new 
    permanent equipment is operational.
        DOMAC states that the estimated cost of the temporary leased air 
    stabilization facilities will be approximately $295,000, assuming a 
    four-month period of operation, and the cost of the permanent air 
    stabilization facilities will be approximately $1,280,000. DOMAC 
    further states that it will finance the facilities by using funds on 
    hand and it will be fully at risk for the cost of these proposed 
    facilities. DOMAC also states that any financial risk associated with 
    the additional facilities will be borne by DOMAC alone, and not its 
    customers.
        Comment date: August 14, 1994, in accordance with Standard 
    Paragraph F at the end of this notice.
    
    Standard Paragraphs
    
        F. Any person desiring to be heard or to make any protest with 
    reference to said application should on or before the comment date, 
    file with the Federal Energy Regulatory Commission, Washington, D.C. 
    20426, a motion to intervene or a protest in accordance with the 
    requirements of the Commission's Rules of Practice and Procedure (18 
    CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act 
    (18 CFR 157.10). All protests filed with the Commission will be 
    considered by it in determining the appropriate action to be taken but 
    will not serve to make the protestants parties to the proceeding. Any 
    person wishing to become a party to a proceeding or to participate as a 
    party in any hearing therein must file a motion to intervene in 
    accordance with the Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to the jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and Procedure, a hearing will be 
    held without further notice before the Commission or its designee on 
    this application if no motion to intervene is filed within the time 
    required herein, if the Commission on its own review of the matter 
    finds that a grant of the certificate and/or permission and approval 
    for the proposed abandonment are required by the public convenience and 
    necessity. If a motion for leave to intervene is timely filed, or if 
    the Commission on its own motion believes that a formal hearing is 
    required, further notice of such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for applicant to appear or be represented at the 
    hearing.
        G. Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefore, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 94-19608 Filed 8-10-94; 8:45 am]
    BILLING CODE 6717-01-P
    
    
    

Document Information

Published:
08/11/1994
Department:
Energy Department
Entry Type:
Uncategorized Document
Document Number:
94-19608
Dates:
September 19, 1994, in accordance with Standard Paragraph G at the end of this notice.
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: August 11, 1994, Docket No. CP94-681-000., et al.