98-21446. Northern Border Pipeline Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 63, Number 154 (Tuesday, August 11, 1998)]
[Notices]
[Pages 42838-42839]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-21446]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP98-692-000]
Northern Border Pipeline Company; Notice of Request Under Blanket
Authorization
August 6, 1998.
Take notice that on July 24, 1998, Northern Border Pipeline Company
(Northern Border), 1111 South 103rd Street, Omaha, Nebraska 68124-1000
filed in Docket No. CP98-692-000 a request pursuant to Sections 157.205
and 157.212 of the Commission's Regulations under the Natural Gas Act
(18 CFR 157.205, 157.212) for authorization to operate an existing
valve setting and to construct and operate certain measurement
facilities as a new delivery point (Tyler delivery point) to the town
of Tyler, Minnesota under Northern Border's blanket certificate issued
in Docket No. CP84-420-000 pursuant to Section 7 of the natural Gas
Act, all as more fully set forth in the request that is on file with
the Commission and open to public inspection.
Specifically, Northern Border requests authorization to operate an
existing 4-inch valve setting and to construct and operate a single 2-
inch rotary meter and associated piping, RTU, and meter building to
serve as a delivery point to the town of Tyler, Minnesota. The
estimated cost of the proposed facilities is $220,000. Northern Border
will be reimbursed for all costs incurred for constructing the proposed
delivery point.
The natural gas volumes to be delivered at the proposed delivery
point are volumes currently being transported by Northern Border.
Northern Border will deliver to the town of Tyler up to 700 Mcf on a
peak day and an estimated 110,000 Mcf annually. The natural gas volumes
delivered at the Tyler delivery point will be used to serve the town of
Tyler, Minnesota. There will not be any impact on the peak day
capability of Northern Border's existing shippers as a result of the
proposed interconnect and
[[Page 42839]]
any impact on annual deliveries will be de minimis.
Northern Border further states that the proposed change is not
prohibited by Northern Border's existing tariff. Northern Border
asserts that it has sufficient capacity in its system to accomplish
delivery of gas to the proposed delivery point without detriment or
disadvantage to any other customer.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
David P. Boergers,
Secretary.
[FR Doc. 98-21446 Filed 8-10-98; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 08/11/1998
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 98-21446
- Pages:
- 42838-42839 (2 pages)
- Docket Numbers:
- Docket No. CP98-692-000
- PDF File:
-
98-21446.pdf