-
Start Preamble
Take notice that on July 29, 2020, Texas Gas Transmission, LLC (Texas Gas) requested that the Federal Energy Regulatory Commission (Commission) grant an extension of time, until August 20, 2021, to plug and abandon an Injection/Withdrawal (I/W) well located at its Leesville Storage Field (Project) authorized on August 19, 2019. The Project would enable Texas Gas to plug and abandon I/W Well No. 5710, abandon in-place its related well lateral line and side valve, and abandon by removal its associated above-ground equipment at its Leesville Storage Field in Lawrence County, Indiana.
Texas Gas was initially required to complete all construction of the Project by August 20, 2020. Texas Gas now requests a one-year extension of this deadline through August 20, 2021. Texas Gas states that completion of the abandonment activities associated with the Project was scheduled for April 2020. However, due to the COVID-19 pandemic and the inability of contractor resources to safely travel and perform the activities associated with the Project, Texas Gas was not able to complete the abandonment activities. Accordingly, Texas Gas proposes a new construction schedule, deferring the projected completion date for the Project until 2021.
This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on Texas Gas' request for an extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10).[1]
As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for Natural Gas Act facilities when such requests are contested before order issuance. For those extension requests that are contested,[2] the Commission will aim to issue an order acting on the request within 45 days.[3] The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.[4] The Commission will not consider arguments that re-litigate the issuance of the certificate order, Start Printed Page 48515including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission's environmental analysis for the certificate complied with the National Environmental Policy Act.[5] At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.[6] The OEP Director, or his or her designee, will act on all of those extension requests that are uncontested.
In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page (http://www.ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to Commission's Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID-19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY, (202) 502-8659.
The Commission strongly encourages electronic filings of comments in lieu of paper using the “eFile” link at http://www.ferc.gov. In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern Time on August 20, 2020.
Start SignatureEnd Signature End PreambleFootnotes
1. Only motions to intervene from entities that were party to the underlying proceeding will be accepted. Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 39 (2020).
Back to Citation2. Contested proceedings are those where an intervenor disputes any material issue of the filing. 18 CFR 385.2201(c)(1) (2019).
Back to Citation3. Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).
Back to Citation4. Id. at P 40.
Back to Citation5. Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether the Commission's environmental analysis for the permit order complied with NEPA.
Back to Citation6. Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).
Back to Citation7. 18 CFR 2.1 (2019).
Back to Citation[FR Doc. 2020-17499 Filed 8-10-20; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 08/11/2020
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 2020-17499
- Dates:
- 5:00 p.m. Eastern Time on August 20, 2020.
- Pages:
- 48514-48515 (2 pages)
- Docket Numbers:
- Docket No. CP19-480-000
- PDF File:
- 2020-17499.pdf