DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER97-3766-000, et al.]
The Dayton Power and Light Company, et al.; Electric Rate and
Corporate Regulation Filings
August 6, 1997.
Take notice that the following filings have been made with the
Commission:
1. The Dayton Power and Light Company
[Docket No. ER97-3766-000]
Take notice that on July 18, 1997, The Dayton Power and Light
Company (Dayton) submitted service agreements establishing NIPSCO as a
customer under the terms of Dayton's Market-Based Sales Tariff.
Dayton requests an effective date of one day subsequent to this
filing for the service agreements. Accordingly, Dayton requests waiver
of the Commission's notice requirements. Copies of the filing were
served upon NIPSCO and the Public Utilities Commission of Ohio.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
[[Page 43157]]
2. Citizens Power & Light Company, National Gas & Electric L.P.,
InterCoast Power Marketing, Enron Power Marketing, Inc., Valero
Power Service Company, JEB Corporation, and Calpine Power Services
Company
[Docket Nos. ER89-401-032, ER90-168-033, ER94-6-008, ER94-24-020, ER94-
1394-012, ER94-1432-012, ER94-1545-011, (not consolidated)]
Take notice that the following informational filings have been made
with the Commission and are on file and available for public inspection
and copying in the Commission's Public Reference Room:
On July 30, 1997, Citizens Power & Light Company filed certain
information as required by the Commission's August 8, 1989, order in
Docket No. ER89-401-000.
On July 22, 1997, National Gas & Electric L.P., filed certain
information as required by the Commission's March 20, 1990, order in
Docket No. ER90-168-000.
On July 28, 1997, InterCoast Power Marketing filed certain
information as required by the Commission's August 19, 1994, order in
Docket No. ER94-6-000.
On July 30, 1997, Enron Power Marketing, Inc., filed certain
information as required by the Commission's December 2, 1993, order in
Docket No. ER94-24-000.
On July 30, 1997, Valero Power Service Company filed certain
information as required by the Commission's August 24, 1994, order in
Docket No. ER94-1394-000.
On July 30, 1997, JEB Corporation filed certain information as
required by the Commission's September 8, 1994, order in Docket No.
ER94-1432-000.
On July 29, 1997, Calpine Power Services Company filed certain
information as required by the Commission's March 9, 1995, order in
Docket No. ER94-1545-000.
3. Destec Power Services, Inc., Koch Energy Trading Inc., EPEM
Marketing Company and Phibro Inc.
[Docket Nos. ER94-1612-014, ER95-218-010, ER95-428-011, and ER95-430-
011 (not consolidated)]
Take notice that the following informational filings have been made
with the Commission and are on file and available for public inspection
and copying in the Commission's Public Reference Room:
On July 30, 1997, Destec Power Services, Inc., filed certain
information as required by the Commission's January 20, 1995, order in
Docket No. ER94-1612-000.
On July 29, 1997, Koch Energy Trading, Inc., filed certain
information as required by the Commission's January 4, 1995, order in
Docket No. ER95-218-000.
On July 24, 1997, EPEM Marketing Company filed certain information
as required by the Commission's March 30, 1995, order in Docket No.
ER95-428-000.
On July 29, 1997, Phibro Inc., filed certain information as
required by the Commission's March 14, 1995, order in Docket No. ER95-
430-000.
4. Portland General Electric Company
[Docket No. ER97-3767-000]
Take notice that on July 18, 1997, Portland General Electric
Company (PGE), tendered for filing under PGE's Final Rule pro forma
tariff FERC Electric Tariff Original Volume No. 8, Docket No. OA96-137-
000), an executed Service Agreement for Non-Firm Point-to-Point
Transmission Service with Transalta Energy Marketing, Corp.
Pursuant to 18 CFR 35.11, and the Commission's Order in Docket No.
PL93-2-002 issued July 30, 1993, PGE respectfully requests that the
Commission grant a waiver of the notice requirements of 18 CFR 35.3 to
allow the Service Agreement to become effective July 15, 1997.
A copy of this filing was caused to be served upon Transalta Energy
Marketing, Corp., as noted in the filing letter.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
5. The Dayton Power and Light Co.
[Docket No. ER97-3768-000]
Take notice that on July 18, 1997, The Dayton Power and Light
Company (Dayton) submitted service agreements establishing Market
Responsive Energy, Inc., as a customer under the terms of Dayton's
Market-Based Sales Tariff.
Dayton requests an effective date of one day subsequent to this
filing for the service agreements. Accordingly, Dayton requests waiver
of the Commission's notice requirements. Copies of the filing were
served upon Market Responsive Energy, Inc., and the Public Utilities
Commission of Ohio.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
6. Portland General Electric Company
[Docket No. ER97-3769-000]
Take notice that on July 18, 1997, Portland General Electric
Company (PGE), tendered for filing under PGE's Final Rule pro forma
tariff FERC Electric Tariff Original Volume No. 8, Docket No. OA96-137-
000), an executed Service Agreement for Non-Firm Point-to-Point
Transmission Service with PECO Energy Company.
Pursuant to 18 CFR 35.11, and the Commission's Order in Docket No.
PL93-2-002 issued July 30, 1993, PGE respectfully requests that the
Commission grant a waiver of the notice requirements of 18 CFR 35.3 to
allow the Service Agreement to become effective July 15, 1997.
A copy of this filing was caused to be served upon PECO Energy
Company as noted in the filing letter.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
7. Allegheny Power Service Corporation, on behalf of Monongahela
Power Company, The Potomac Edison Company and West Penn Power
Company (Allegheny Power)
[Docket No. ER97-3770-000]
Take notice that on July 18, 1997, Allegheny Power Service
Corporation on behalf of Monongahela Power Company, The Potomac Edison
Company and West Penn Power Company (Allegheny Power) filed Supplement
No. 29 to add one (1) new Customer to the Standard Generation Service
Rate Schedule under which Allegheny Power offers standard generation
and emergency service on an hourly, daily, weekly, monthly or yearly
basis. Allegheny Power requests a waiver of notice requirements to make
service available to Virginia Electric and Power Company as of a date
authorized by the Commission.
Copies of the filing have been provided to the Public Utilities
Commission of Ohio, the Pennsylvania Public Utility Commission, the
Maryland Public Service Commission, the Virginia State Corporation
Commission, the West Virginia Public Service Commission, and all
parties of record.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
8. Allegheny Power Service Corporation, on behalf of Monongahela
Power Company, The Potomac Edison Company and West Penn Power
Company (Allegheny Power)
[Docket No. ER97-3771-000]
Take notice that on July 18, 1997, Allegheny Power Service
Corporation on behalf of Monongahela Power Company, The Potomac Edison
Company and West Penn Power Company (Allegheny Power), filed
[[Page 43158]]
Supplement No. 22 to add Constellation Power Source, Edison Source,
Energy Transfer Group, L.L.C., Equitable Power Services Company, and
Market Responsive Energy, Inc., to Allegheny Power Open Access
Transmission Service Tariff which has been submitted for filing by the
Federal Energy Regulatory Commission in Docket No. OA96-18-000. The
proposed effective date under the Service Agreements is July 17, 1997.
Copies of the filing have been provided to the Public Utilities
Commission of Ohio, the Pennsylvania Public Utility Commission, the
Maryland Public Service Commission, the Virginia State Corporation
Commission, the West Virginia Public Service Commission.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
9. Allegheny Power Service Corporation, on behalf of Monongahela
Power Company, The Potomac Edison Company and West Penn Power
Company (Allegheny Power)
[Docket No. ER97-3772-000]
Take notice that on July 18, 1997, Allegheny Power Service
Corporation on behalf of Monongahela Power Company, The Potomac Edison
Company and West Penn Power Company (Allegheny Power), filed Supplement
No. 30 to add four (4) new Customers to the Standard Generation Service
Rate Schedule under which Allegheny Power offers standard generation
and emergency service on an hourly, daily, weekly, monthly or yearly
basis. Allegheny Power requests a waiver of notice requirements to make
service available as of July 17, 1997, to Edison Source, Energy
Transfer Group, L.L.C., Market Responsive Energy, Inc.; and as of June
25, 1997 for PJM Interconnection, L.L.C.
Copies of the filing have been provided to the Public Utilities
Commission of Ohio, the Pennsylvania Public Utility Commission, the
Maryland Public Service Commission, the Virginia State Corporation
Commission, the West Virginia Public Service Commission and all parties
of record.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
10. IES Utilities Inc. And Union Electric Company
[Docket No. ER97-3773-000]
Take notice that on July 18, 1997, Union Electric Company (UE) and
IES Utilities Inc. (IES), tendered for filing proposed changes to
Fourth Amendment to the 25 Hertz Wholesale Electric Service Agreement
and Fourth Amendment to the Interchange Agreement.
The amendment to the 25 Hertz Wholesale Electric Service Agreement
alters the terms and conditions that UE provides 25 Hertz service to
IES. The Fourth Amendment to the Interchange Agreement includes an
additional 69 kV circuit known as the Keokuk-Carbide 69 kV connection.
It also allows IES to modify the existing Viele-Carbide Tap-Palmyra and
Carbide Tap-Carbide 161 kV lines to allow an additional 161 kV line to
be built into Keokuk and moves existing metering points from Viele 161
kV and Carbide 69 kV to a single 161 kV meter point at Carbide.
Copies of the filing were served upon the Iowa State Utilities
Board.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
11. Houston Lighting & Power Company
[Docket No. ER97-3774-000]
Take notice that on July 18, 1997, Houston Lighting & Power Company
(HL&P), tendered for filing an executed transmission service agreement
(TSA) with Equitable Power Services Company (Equitable) for Non-Firm
Transmission Service under HL&P's FERC Electric Tariff, Second Revised
Volume No. 1, for Transmission Service To, From and Over Certain HVDC
Interconnections. HL&P has requested an effective date of July 18,
1997.
Copies of the filing were served on Equitable and the Public
Utility Commission of Texas.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
12. Union Electric Company
[Docket No. ER97-3775-000]
Take notice that on July 18, 1997, Union Electric Company (UE),
tendered for filing Service Agreements for Firm Point-to-Point
Transmission Services between UE and Koch Energy Trading, Inc. and
Illinois Power Company. UE asserts that the purpose of the Agreements
is to permit UE to provide transmission service to the parties pursuant
to UE's Open Access Transmission Tariff filed in Docket No. OA96-50.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
13. Northern States Power Company (Minnesota Company)
[Docket No. ER97-3776-000]
Take notice that on July 18, 1997, Northern States Power Company
(Minnesota)(NSP), tendered for filing a Non-Firm Point-to-Point
Transmission Service Agreement between NSP and PacifiCorp.
NSP requests that the Commission accept the agreement effective
June 18, 1997, and requests waiver of the Commission's notice
requirements in order for the agreement to be accepted for filing on
the date requested.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
14. Northern States Power Company (Minnesota Company)
[Docket No. ER97-3777-000]
Take notice that on July 18, 1997, Northern States Power Company
(Minnesota) (NSP), tendered for filing a Firm Point-to-Point
Transmission Service Agreement between NSP and Wisconsin Public Service
Corporation.
NSP requests that the Commission accept the agreement effective
November 1, 1997, and requests waiver of the Commission's notice
requirements in order for the agreements to be accepted for filing on
the date requested.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
15. Northern States Power Company (Minnesota Company)
[Docket No. ER97-3778-000]
Take notice that on July 18, 1997, Northern States Power Company
(Minnesota) (NSP), tendered for filing a three Firm Point-to-Point
Transmission Service Agreements between NSP and Morgan Stanley Capital
Group Inc.
NSP requests that the Commission accept the agreements effective
July 1, 1997, August 1, 1997, and September 1, 1997, respectively, and
requests waiver of the Commission's notice requirements in order for
the agreements to be accepted for filing on the date requested.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
16. Duke Power Company
[Docket No. ER97-3781-000]
Take notice that on July 17, 1997, Duke Power Company (Duke),
tendered for filing a Transmission Service Agreement between Duke, on
its own behalf and acting as agent for its wholly-owned subsidiary,
Nantahala Power and
[[Page 43159]]
Light Company, and American Electric Power Service Corporation
(Transmission Customer), dated as of June 24, 1997 (TSA). Duke states
that the TSA sets out the transmission arrangements under which Duke
will provide the Transmission Customer firm point-to-point transmission
service under Duke's Pro Forma Open Access Transmission Tariff. Duke
requests that the Agreement be made effective as of June 24, 1997.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
17. Consolidated Edison Company of New York, Inc.
[Docket No. ER97-3785-000]
Take notice that on July 21, 1997, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing a service agreement to
provide non-firm transmission service pursuant to its Open Access
Transmission Tariff to Market Responsive Energy, Inc.
Con Edison states that a copy of this filing has been served by
mail upon Market Responsive Energy, Inc.
Comment date: August 20, 1997, in accordance with Standard
Paragraph E at the end of this notice.
Standard Paragraph
E. Any person desiring to be heard or to protest said filing should
file a motion to intervene or protest with the Federal Energy
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,
in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such
motions or protests should be filed on or before the comment date.
Protests will be considered by the Commission in determining the
appropriate action to be taken, but will not serve to make protestants
parties to the proceeding. Any person wishing to become a party must
file a motion to intervene. Copies of this filing are on file with the
Commission and are available for public inspection.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 97-21251 Filed 8-11-97; 8:45 am]
BILLING CODE 6717-01-P