05-15980. Interconnection for Wind Energy  

  • Start Preamble Issued August 5, 2005.

    AGENCY:

    Federal Energy Regulatory Commission, DOE.

    ACTION:

    Order granting delay of effective date and extending compliance date.

    SUMMARY:

    The Federal Energy Regulatory Commission (Commission) is delaying the effective date of the Final Rule on Interconnection for Wind Energy, Order No. 661, 60 days from the current effective date (August 15, 2005) to October 14, 2005. The Commission is also extending the date by which public utilities must adopt the Appendix G included in the Final Rule to November 14, 2005.

    DATES:

    The effective date for the rule published at 70 FR 34993 on June 16, 2005 is delayed until October 14, 2005.

    Compliance Date: The date by which public utilities must adopt Appendix G is extended to November 14, 2005.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Jeffery S. Dennis (Legal Information), Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. (202) 502-6027.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Before Commissioners: Joseph T. Kelliher, Chairman; Nora Mead Brownell, and Suedeen G. Kelly.

    Order Granting Extension of Effective Date and Extending Compliance Date

    1. On August 4, 2005, the American Wind Energy Association (AWEA) and the North American Electric Reliability Council (NERC) filed a request for extension of the effective date of the Commission's Final Rule, issued June 2, 2005 in this docket.[1] AWEA and NERC state that they have initiated discussions to address the low voltage ride-through provisions of the Commission's Final Start Printed Page 47094Rule. They request a 60-day extension of the effective date of the Final Rule to October 14, 2005.

    2. For good cause shown, the Commission will extend the effective date of the Final Rule 60 days from the current effective date (August 15, 2005) to October 14, 2005. Additionally, we will extend to November 15, 2005, the date by which all public utilities that own, control, or operate transmission facilities in interstate commerce are to adopt the Final Rule Appendix G as amendments to the Large Generator Interconnection Procedures and Large Generator Interconnection Agreements (LGIAs) in their Open Access Transmission Tariffs.[2] The transition period adopted in the Final Rule (which states that the low voltage ride-through, reactive power and supervisory control and data acquisition (SCADA) provisions apply only to LGIAs signed, filed with the Commission in executed form, or filed as non-conforming agreements, on or after January 1, 2006, or the date six months after publication of the Final Rule in the Federal Register) remains unchanged.

    3. NERC and AWEA state that they will file a report with the Commission on or before September 14, 2005, describing the final results of their discussions and any recommended revisions to the low voltage ride-through provisions in the Final Rule. The Commission accepts this commitment, and will take any such recommended revisions submitted on or before September 14, 2005 into consideration as it considers the requests for rehearing filed in this proceeding. Additionally, the Commission will consider any supplemental comments related to the low voltage ride-through provisions of the Final Rule that are filed on or before September 14, 2005. However, the Commission will not consider comments that simply rehash prior arguments.

    The Commission orders:

    (A) The effective date of the Final Rule on Interconnection for Wind Energy is hereby extended to October 14, 2005, as discussed in the body of this order.

    (B) The date by which all public utilities that own, control, or operate transmission facilities in interstate commerce are to adopt the Final Rule Appendix G as amendments to the Large Generator Interconnection Procedures and Large Generator Interconnection Agreements in their Open Access Transmission Tariffs is hereby extended to November 14, 2005, as discussed in the body of this order.

    (C) The Secretary shall promptly publish a copy of this order in the Federal Register.

    Start Signature

    By the Commission.

    Linda Mitry,

    Deputy Secretary.

    End Signature End Supplemental Information

    Footnotes

    1.  Interconnection for Wind Energy, Order No. 661, 70 FR 34993 (June 16, 2005), FERC Stats. & Regs. ¶ 31,186 (2005) (Final Rule), reh'g pending.

    Back to Citation

    2.  This extension also satisfies the request for extension submitted by Midwest Independent Transmission System Operator, Inc. on August 4, 2005.

    Back to Citation

    [FR Doc. 05-15980 Filed 8-11-05; 8:45 am]

    BILLING CODE 6717-01-U

Document Information

Effective Date:
6/16/2005
Published:
08/12/2005
Department:
Federal Energy Regulatory Commission
Entry Type:
Rule
Action:
Order granting delay of effective date and extending compliance date.
Document Number:
05-15980
Dates:
The effective date for the rule published at 70 FR 34993 on June 16, 2005 is delayed until October 14, 2005.
Pages:
47093-47094 (2 pages)
Docket Numbers:
Docket No. RM05-4-001-Order No. 661
EOCitation:
of 2005-08-05
PDF File:
05-15980.pdf
CFR: (1)
18 CFR 35