98-21683. Florida Gas Transmission Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 63, Number 156 (Thursday, August 13, 1998)]
    [Notices]
    [Page 43393]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-21683]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP98-704-000]
    
    
    Florida Gas Transmission Company; Notice of Request Under Blanket 
    Authorization
    
    August 7, 1998.
        Take notice that on July 31, 1998, Florida Gas Transmission Company 
    (FGT), filed in Docket No. CP98-704-000 a request for authorization 
    pursuant to sections 157.205 and 157.212 of the Commission's 
    Regulations under the Natural Gas Act (18 CFR 157.205 and 157.212) to 
    construct, own, and operate a new delivery point, PGS-Worthington 
    Springs, on its system to accommodate deliveries of natural gas to the 
    State of Florida, Department of Corrections (The State), under FGT's 
    blanket certificate issued in Docket No. CP82-553-000 pursuant to 
    section 7(c) of the Natural Gas Act, all as more fully set forth in the 
    request that is on file with the Commission and open to public 
    inspection.
        Specifically, FGT proposes to construct, own, and operate a new 
    tap, electronic flow measurement (EFM) equipment and approximately 100 
    feet of 2-inch connecting pipeline in Union County, Florida to deliver 
    natural gas for the State of Florida through a new meter station and 
    6.25 miles of 4-inch non-jurisdictional pipeline constructed, owned, 
    and operated by TECO Peoples Gas Inc. (TECO). FGT asserts that the new 
    delivery point will be added to the existing FTS-1 Service Agreement 
    between FGT and The State to allow deliveries of natural gas to TECO's 
    new meter station.
        FGT states that this new delivery point will not increase the 
    contractual gas quantities nor increase the current certificated level 
    of service under the existing FTS-1 Service Agreements. FGT estimates 
    the total cost of the proposed construction to be approximately 
    $76,000, inclusive of tax gross-up. FGT indicates that TECO will 
    reimburse FGT for all costs directly and indirectly incurred by FGT for 
    the construction of the new delivery point.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    David P. Boergers,
    Secretary.
    [FR Doc. 98-21683 Filed 8-12-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
08/13/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-21683
Pages:
43393-43393 (1 pages)
Docket Numbers:
Docket No. CP98-704-000
PDF File:
98-21683.pdf