99-20986. Notice of Application Accepted for Filing and Request for Motions To Intervene and Protests  

  • [Federal Register Volume 64, Number 156 (Friday, August 13, 1999)]
    [Notices]
    [Pages 44216-44217]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-20986]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    
    
    Notice of Application Accepted for Filing and Request for Motions 
    To Intervene and Protests
    
    August 9, 1999.
        Take notice that the following hydroelectric application has been 
    filed with the Commission and is available for public inspection. This 
    is a reissuance of the notice issued on January 28, 1999.
        a. Type of Application: Preliminary Permit
        b. Project No.: P-11653-000.
        c. Date filed: December 28, 1998, and revised on March 26, 1999.
        d. Applicant: Universal Electric Power Corp.
        e. Name of Project: Muskingum L&D #10 Hydroelectric Project.
        f. Location: At the existing Muskingum Lock and Dam #10, which is 
    owned by the Ohio Department of Natural Resources, Division of Parks 
    and Recreation, on the Muskingum River, near the Town of Zanesville, 
    Muskingum County, Ohio.
        g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(i).
        h. Applicant Contact: Mr. Ronald S. Feltenberger, Universal 
    Electric Power Corp., 1145 Highbrook Street, Akron, Ohio 44301, (330) 
    535-7115.
        i. FERC Contact: Susan Tseng (202) 219-2798 or E-mail address at 
    [email protected]
        j. Comment Date: 30 days from the issuance date of this notice.
        k. Description of Project: The proposed project would consist of 
    the following facilities: (1) the existing Muskingum Lock and Dam #10, 
    with a storage of 3,410-acre-feet and a surface area of 470 acres at an 
    upstream pool elevation of 687.55 feet m.s.1.; (2) a powerhouse 
    downstream of the dam having an installed capacity of 4,000 kilowatts; 
    (2) a new transmission line; and (3) appurtenant facilities. The 
    proposed average annual generation is estimated to be 26 gigawatt 
    hours. The cost of the studies under the permit will not exceed 
    $1,750,000.
        l. Available Locations of Application: A copy of the application is 
    available for inspection and reproduction at the Commission's Public 
    Reference and Files Maintenance Branch, located at 888 First, Street, 
    N.E., Room 2-A, Washington, D.C. 20426, or by calling (202) 219-1371. A 
    copy is also available for inspection and reproduction at Universal 
    Electric Power Corp., Mr. Ronald S. Feltenberger 1145 Highbrook
    
    [[Page 44217]]
    
    Street, Akron, Ohio 44301, (330) 535-7115. A copy of the application 
    may also be viewed or printed by accessing the Commission's website on 
    the Internet at www.ferc.fed.us. For assistance, users may call (202) 
    208-2222.
        Preliminary Permit--Anyone desiring to file a competing application 
    for preliminary permit for a proposed project must submit the competing 
    application itself, or a notice of intent to file such an application, 
    to the Commission on or before the specified comment date for the 
    particular application (see 18 CFR 4.36). Submission of a timely notice 
    of intent allows an interested person to file the competing preliminary 
    permit application no later than 30 days after the specified comment 
    date for the particular application. A competing preliminary permit 
    application must conform with 18 CFR 4.30(b) and 4.36.
        Preliminary Permit--Any qualified development application desiring 
    to file a competing development application must submit to the 
    Commission, on or before a specified comment date for the particular 
    application, either a competing development application or a notice of 
    intent to file such an application. Submission of a timely notice of 
    intent to file a development application allows an interested person to 
    file the competing application no later than 120 days after the 
    specified comment date for the particular application. A competing 
    license application must conform with 18 CFR 4.30(b) and 4.36.
        Notice of intent--A notice of intent must specify the exact name, 
    business address, and telephone number of the prospective applicant, 
    and must include an unequivocal statement of intent to submit, if such 
    an application may be filed, either a preliminary permit application or 
    a development application (specify which type of application). A notice 
    of intent must be served on the applicant(s) named in this public 
    notice.
        Proposed Scope of Studies under Permit--A preliminary permit, if 
    issued, does not authorize construction. The term of the proposed 
    preliminary permit would be 36-months. The work proposed under the 
    preliminary permit would include economic analysis, preparation of 
    preliminary engineering plans, and a study of environmental impacts. 
    Based on the results of these studies, the Applicant would decide 
    whether to proceed with the preparation of a development application to 
    construct and operate the project.
        Comments, Protests, or Motions to Intervene--Anyone may submit 
    comments, a protest, or a motion to intervene in accordance with the 
    requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
    .214. In determining the appropriate action to take, the Commission 
    will consider all protests or other comments filed, but only those who 
    file a motion to intervene in accordance with the Commission's Rules 
    may become a party to the proceeding. Any comments, protest, or motions 
    to intervene must be received on or before the specified comment date 
    of the particular application.
        Filing and Service of Responsive Documents--Any filings must bear 
    in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT TO 
    FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', ``PROTEST'', 
    ``MOTION TO INTERVENE'', as applicable, and the Project Number of the 
    particular application to which the filing refers. Any of the above-
    named documents must be filed by providing the original and the number 
    of copies provided by the Commission's regulations to: The Secretary, 
    Federal Energy Regulatory Commission, 888 First Street, N.E., 
    Washington, D.C. 20426. An additional copy must be sent to Director, 
    Division of Project Review, Federal Energy Regulatory Commission, at 
    the above-mentioned address. A copy of any notice of intent, competing 
    application or motion to intervene must also be served upon each 
    representative of the Applicant specified in the particular 
    application.
        Agency Comments--Federal, state, and local agencies are invited to 
    file comments on the described application. A copy of the application 
    may be obtained by agencies directly from the Applicant. If an agency 
    does not file comments within the time specified for filing comments, 
    it will be presumed to have no comments. One copy of an agency's 
    comments must also be sent to the Applicant's representatives.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-20986 Filed 8-12-99; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
08/13/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-20986
Dates:
30 days from the issuance date of this notice.
Pages:
44216-44217 (2 pages)