2018-17420. Limitation on Claims Against Proposed Public Transportation Projects  

  • Start Preamble

    AGENCY:

    Federal Transit Administration (FTA); U.S. Army Corps of Engineers (USACE), DOT.

    ACTION:

    Notice of limitation on claims for judicial review of actions by the USACE.

    SUMMARY:

    FTA is issuing this notice to announce action taken by the USACE that is final within the meaning of the United States Code. The action relates to the construction of a 16.2-mile light-rail transit (LRT) line, known as the Purple Line, from the Bethesda Metro Station in Montgomery County, Maryland, to the New Carrollton Station in Prince George's County, Maryland (the Project). The USACE granted a Department of the Army permit, pursuant to Section 404 of the Clean Water Act, as amended, authorizing the Maryland Transit Administration (MTA) to discharge dredged or fill material into Waters of the United States at specified locations related to the Project.

    DATES:

    By this notice, FTA is advising the public of final agency actions subject to 23 U.S.C. 139(l). A claim seeking judicial review of the identified Federal agency action related to the Project will be barred unless the claim is filed on or before January 11, 2019. If the Federal law that authorizes judicial review of a claim provides a time period of less than 150 days for filing such claim, then that shorter time period still applies.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    For FTA: Nancy-Ellen Zusman, Assistant Chief Counsel, Office of Chief Counsel, (312) 353-2577 or Alan Tabachnick, Environmental Protection Specialist, Office of Environmental Programs, (202) 366-8541. FTA is located at 1200 New Jersey Avenue SE, Washington, DC 20590. Office hours are from 9 a.m. to 5 p.m., Monday through Friday, except Federal holidays. For USACE: Department of the Army, Baltimore District, U.S. Army Corps of Engineers Regulatory Division, Attn: Maria Teresi, 2 Hopkins Plaza, Baltimore, Maryland 21201; telephone: (410) 962-4501.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Notice is hereby given that USACE has taken final agency action by issuing certain approval related to the Project. The actions on the project, as well as the laws under which such actions were taken, are described in the Department of the Army Permit and related documents in the USACE administrative record for the permit action. Interested parties may contact the USACE Baltimore District Regulatory Division Office for more information on the USACE's permit decision. Contact information for the appropriate USACE representative is above. Contact information for FTA's Regional Offices may be found at https://www.fta.dot.gov.

    This notice applies to all USACE decisions on the listed project as of the issuance date of this notice and all laws under which such actions were taken, including, but not limited to, NEPA [42 U.S.C. 4321-4375], Section 106 of the National Historic Preservation Act [54 U.S.C. 306108], and the Clean Water Act [33 U.S.C. 1251-1387]. This notice does not, however, alter or extend the limitation period for challenges of project decisions subject to previous notices published in the Federal Register. The project and action that is the subject of this notice follow:

    Project name and location: The Purple Line, Montgomery County to Prince George's County, Maryland. Project Sponsor: Maryland Transit Administration (MTA). Project description: The project involves the construction of a 16.2-mile light-rail (LRT) line from Bethesda Metro Station in Montgomery County, Maryland, to the New Carrollton Station in Prince George's County, Maryland. The project utilizes existing trails and roadways for the majority of its length. The transit way will be constructed largely at grade with one tunnel section at Plymouth Road, three sections elevated on structures, and several bridge structures. The project will service 5 major activity centers and 21 stations. Two storage and maintenance facilities will be constructed (Lyttonsville Yard and Glenridge Yard). Final agency action: Department of the Army permit issued pursuant to Section 404 Clean Water Act effective March 14, 2018. Supporting documentation: USACE Record of Decision issued March 14, 2018. The USACE decision and permit No. 2016-61278-M07 are available by contacting USACE at the address provided above.

    This notice applies to all Federal agency decisions as of the issuance date of this notice and all laws under which the final action was taken.

    Start Authority

    Authority: 23 U.S.C. 139(l).

    End Authority Start Signature

    Elizabeth S. Riklin,

    Deputy Associate Administrator Planning and Environment.

    End Signature End Supplemental Information

    [FR Doc. 2018-17420 Filed 8-13-18; 8:45 am]

    BILLING CODE 4910-57-P.

Document Information

Published:
08/14/2018
Department:
Federal Transit Administration
Entry Type:
Notice
Action:
Notice of limitation on claims for judicial review of actions by the USACE.
Document Number:
2018-17420
Dates:
By this notice, FTA is advising the public of final agency actions subject to 23 U.S.C. 139(l). A claim seeking judicial review of the identified Federal agency action related to the Project will be barred unless the claim is filed on or before January 11, 2019. If the Federal law that authorizes judicial review of a claim provides a time period of less than 150 days for filing such claim, then that shorter time period still applies.
Pages:
40388-40388 (1 pages)
PDF File:
2018-17420.pdf
Supporting Documents:
» Protecting Public Transportation Operators From the Risk of Assault
» Funding Opportunity: Solicitation of Project Proposals for the Passenger Ferry Grant Program
» Fiscal Year 2018 Competitive Funding Opportunity: Access and Mobility Partnership Grants
» Pilot Program for Expedited Project Delivery
» Fiscal Year 2018 Apportionments, Allocations, Program Information and Guidance
» Allocation of Public Transportation Emergency Relief Funds in Response to Hurricanes Harvey, Irma, and Maria
» Limitation on Claims against Proposed Public Transportation Projects
» Limitation on Claims against Proposed Public Transportation Projects
» Environmental Impacts and Related Procedures
» Environmental Impact Statements; Availability, etc.: Gateway Corridor Project from Saint Paul to Woodbury in Ramsey and Washington Counties, MN; Rescission