2024-18059. Banister Hydro, Inc.; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments  

  • Milestone Target date
    Issue Deficiency Letter (if necessary) October 2024.
    Request Additional Information October 2024.
    Issue Acceptance Letter January 2025.
    Issue Scoping Document 1 for comments February 2025.
    Issue Scoping Document 2 (if necessary) April 2025.